up_reraStatus: Completed
CASE ID: 0901126030612022

Appellant / Complainant

Shardenedu Mishra

VS

Respondent

Agrani Homes Pvt Ltd

Developer Firm

agrani homes pvt ltd

Disposal Award

Unknown

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

34 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126030612022 by Shardenedu Mishra against Agrani Homes Pvt Ltd before up_rera.

Non-Compliance & Execution
2
Stage 128/03/2024

for delivery of Judgment/Order

The Tribunal applied the order passed in EA No. 1946/2022 (Appeal No. 31/2021) to the present case.

3
Stage 224/01/2024

Execution

The Tribunal issued a procedural order directing the parties to refer to a previously passed order dated 24.01.2024 in EA No. 1946/2022.

4
Stage 323/01/2024

Execution

This is a procedural order directing the parties to refer to a previous order passed in EA No. 1946/2022 regarding the matter at hand.

5
Stage 419/10/2023

Execution

No text available.

6
Stage 513/09/2023

Execution

No text available.

7
Stage 625/07/2023

Execution

No text available.

8
Stage 717/07/2023

Execution

No text available.

9
Stage 804/05/2023

Execution

No text available.

10
Stage 923/03/2023

Execution

No text available.

11
Stage 1020/02/2023

Execution

No text available.

12
Stage 1118/01/2023

Execution

No text available.

13
Stage 1213/12/2022

Execution

No text available.

14
Stage 1325/11/2022

Execution

The Tribunal directed the District Magistrate of Varanasi to comply with previous orders dated 11.10.2022 and 18.10.2022, warning that failure to do so would result in legal proceedings for contempt of court.

15
Stage 1409/11/2022

Execution

No text available.

16
Stage 1518/10/2022

Execution

No text available.

17
Stage 1611/10/2022

Execution

No text available.

18
Stage 1730/09/2022

Execution

No text available.

19
Stage 1823/09/2022

Execution

The Tribunal directed the judgment debtor to comply with previous orders regarding proposal submission and ordered that all amounts recovered via recovery citations must be deposited into the designated Escrow account.

20
Stage 1912/09/2022

Execution

The Tribunal directed the judgment debtor to provide expressions of interest from joint venture partners and mandated that any asset sales must not be below circle rates, with proceeds deposited into an Escrow Account for proportionate distribution to decree holders.

21
Stage 2030/08/2022

Hearing

The Tribunal directed the judgment debtor to provide audited balance sheets and realistic asset valuations based on realizable value rather than future profit, and ordered the District Magistrate of Varanasi to refrain from disposing of the builder's properties to facilitate a potential settlement.

22
Stage 2116/08/2022

Hearing

The Tribunal directs that any funds recovered through the ongoing execution proceedings by the Regulatory Authority must be deposited into a specific Escrow Account at Indian Overseas Bank, Gomti Nagar Branch, Lucknow.

23
Stage 2210/08/2022

Hearing

The Tribunal adjourned the matter to 16.08.2022 to align with the scheduling of related cases.

24
Stage 2326/07/2022

Hearing

The Tribunal granted the respondent ten days to comply with a previous order dated 07.07.2022 or show cause, and scheduled the next hearing for 10.08.2022.

25
Stage 2407/07/2022

Notice

The Tribunal ordered the issuance of recovery proceedings against the judgment-debtor (Agrani Homes Pvt Ltd) to ensure the decree-holder can realize the fruits of the settlement.

26
Stage 2513/06/2022

Notice

The Tribunal directed the decree holder to file an affidavit of service within three days and scheduled the matter for further orders on July 7, 2022.

27
Stage 2606/06/2022

Execution

The Tribunal directed the Registry to issue a notice for the next hearing on 13.06.2022 and ordered the decree-holder to serve the execution application and notice to the judgment-debtor via speed-post, Dasti, and email.

28
Stage 27Interim Order

Tribunal Order #0901126030612022-23-09-2022

The Tribunal directed the judgment debtor to comply with previous orders regarding proposal submission and ordered that all amounts recovered via recovery citations must be deposited into the designated Escrow account.

29
Stage 28Interim Order

Tribunal Order #0901126030612022-12-09-2022

The Tribunal directed the judgment debtor to provide expressions of interest from joint venture partners and mandated that any asset sales must not be below circle rates, with proceeds deposited into an Escrow Account for proportionate distribution to decree holders.

30
Stage 29Interim Order

Tribunal Order #0901126030612022-30-08-2022

The Tribunal directed the judgment debtor to provide audited balance sheets and realistic asset valuations based on realizable value rather than future profit, and ordered the District Magistrate of Varanasi to refrain from disposing of the builder's properties to facilitate a potential settlement.

31
Stage 30Interim Order

Tribunal Order #0901126030612022-07-07-2022

The Tribunal ordered the issuance of recovery proceedings against the judgment-debtor (Agrani Homes Pvt Ltd) to ensure the decree-holder can realize the fruits of the settlement.

32
Stage 31Interim Order

Tribunal Order #0901126030612022-25-11-2022

The Tribunal directed the District Magistrate of Varanasi to comply with previous orders dated 11.10.2022 and 18.10.2022, warning that failure to do so would result in legal proceedings for contempt of court.

33
Stage 32Interim Order

Tribunal Order #0901126030612022-16-08-2022

The Tribunal directs that any funds recovered through the ongoing execution proceedings by the Regulatory Authority must be deposited into a specific Escrow Account at Indian Overseas Bank, Gomti Nagar Branch, Lucknow.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Unknown Awarded in favor of Unknown.

Disposal Winner: UnknownStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Unknown

Ruling Awarded To

Unknown

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • | | Counsel for Respondent |

Respondent Advocate(s)

  • Sanjay Awasthi

Official RERA Tribunal Orders (6)

INTERIM_ORDEROrder ID: 0901126030612022-23-09-2022

The Tribunal directed the judgment debtor to comply with previous orders regarding proposal submission and ordered that all amounts recovered via recovery citations must be deposited into the designated Escrow account.

INTERIM_ORDEROrder ID: 0901126030612022-12-09-2022

The Tribunal directed the judgment debtor to provide expressions of interest from joint venture partners and mandated that any asset sales must not be below circle rates, with proceeds deposited into an Escrow Account for proportionate distribution to decree holders.

INTERIM_ORDEROrder ID: 0901126030612022-30-08-2022

The Tribunal directed the judgment debtor to provide audited balance sheets and realistic asset valuations based on realizable value rather than future profit, and ordered the District Magistrate of Varanasi to refrain from disposing of the builder's properties to facilitate a potential settlement.

INTERIM_ORDEROrder ID: 0901126030612022-07-07-2022

The Tribunal ordered the issuance of recovery proceedings against the judgment-debtor (Agrani Homes Pvt Ltd) to ensure the decree-holder can realize the fruits of the settlement.

INTERIM_ORDEROrder ID: 0901126030612022-25-11-2022

The Tribunal directed the District Magistrate of Varanasi to comply with previous orders dated 11.10.2022 and 18.10.2022, warning that failure to do so would result in legal proceedings for contempt of court.

INTERIM_ORDEROrder ID: 0901126030612022-16-08-2022

The Tribunal directs that any funds recovered through the ongoing execution proceedings by the Regulatory Authority must be deposited into a specific Escrow Account at Indian Overseas Bank, Gomti Nagar Branch, Lucknow.

TathyaGrid RERA Intelligence AI

Need to research all rulings for agrani homes pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →