up_reraStatus: Completed
CASE ID: 0901126030502024

Appellant / Complainant

Pankaj Bhargava

VS

Respondent

Krishna Estate Developers Pvt Ltd

Developer Firm

krishna estate developers pvt ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

22 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126030502024 by Pankaj Bhargava against Krishna Estate Developers Pvt Ltd before up_rera.

Non-Compliance & Execution
2
Stage 121/08/2025

Hearing

The appeal is dismissed as not pressed following an out-of-court settlement between the appellant-allottee and the respondent-promoter, noting that funds recovered via U.P. RERA execution proceedings are to be disbursed to the appellant.

3
Stage 204/08/2025

Hearing

The parties informed the Tribunal that they are nearing an out-of-court settlement, and the matter has been adjourned to 21.08.2025 for further hearing or orders.

4
Stage 315/07/2025

Hearing

Upon the joint request of both parties, the tribunal has adjourned the appeal and scheduled it for orders/hearing on 04.08.2025.

5
Stage 427/05/2025

Hearing

The parties informed the Tribunal that they are in the advanced stages of a settlement, and the matter has been adjourned to 15.07.2025 for further orders/hearing.

6
Stage 515/05/2025

Hearing

The Tribunal noted that the matter has been part-heard by a Larger Bench and directed the appeal to be listed before the Special Bench on 27.05.2025 at 1:30 p.m.

7
Stage 621/04/2025

Hearing

The Tribunal noted that the respondent promoter executed a sale deed to a third party in breach of a prior decree, and upon the respondent's request to attempt a settlement, the matter is adjourned to 15.05.2025.

8
Stage 724/03/2025

Hearing

The Tribunal adjourned the appeal to 21.04.2025 and imposed a cost of Rs. 1,000/- to be paid by the respondent to the appellant due to the respondent's request for adjournment.

9
Stage 803/03/2025

Hearing

The Tribunal took the respondent's objections dated 30.01.2025 on record and scheduled the appeal for a final hearing on 24.03.2025, noting that no further adjournments will be granted.

10
Stage 910/02/2025

Hearing

The Tribunal granted the respondent three days to upload and supply signed objections and scheduled the case for orders on March 3, 2025.

11
Stage 1016/01/2025

Hearing

The Tribunal granted the respondent one week to upload signed objections and directed the appellant to file a rejoinder within a week of receipt, scheduling the next hearing for 10.02.2025.

12
Stage 1109/12/2024

Hearing

The Tribunal granted the respondent ten days to file objections and serve a soft copy to the appellant, with the next hearing scheduled for 16.01.2025.

13
Stage 1208/11/2024

Hearing

The Tribunal has adjourned the appeal to 09.12.2024 following a request from the respondent's counsel.

14
Stage 1330/09/2024

Delay condonation

The Tribunal condoned the delay in filing the appeal and issued an interim injunction restraining the respondent promoter from executing any sale deeds to third parties regarding the unit in question until proof of existing third-party rights is provided.

15
Stage 1418/09/2024

Delay condonation

The Tribunal granted the respondent one week to file a vakalatnama and objections to the application for condonation of delay, with the matter scheduled for further orders on 30.09.2024.

16
Stage 1530/08/2024

Delay condonation

The Tribunal accepted service of notice upon the respondent and granted them seven days to file objections to the appeal and the application for condonation of delay.

17
Stage 1629/07/2024

Defect Removal

The Tribunal issued notice to the respondent regarding the appeal and the application for condonation of delay, scheduling the matter for hearing on 30.08.2024.

18
Stage 17Final Ruling Order

Tribunal Order #0901126030502024-21-08-2025

The appeal is dismissed as not pressed following an out-of-court settlement between the appellant-allottee and the respondent-promoter, noting that funds recovered via U.P. RERA execution proceedings are to be disbursed to the appellant.

19
Stage 18Interim Order

Tribunal Order #0901126030502024-21-04-2025

The Tribunal noted that the respondent promoter executed a sale deed to a third party in breach of a prior decree, and upon the respondent's request to attempt a settlement, the matter is adjourned to 15.05.2025.

20
Stage 19Interim Order

Tribunal Order #0901126030502024-24-03-2025

The Tribunal adjourned the appeal to 21.04.2025 and imposed a cost of Rs. 1,000/- to be paid by the respondent to the appellant due to the respondent's request for adjournment.

21
Stage 20Interim Order

Tribunal Order #0901126030502024-30-09-2024

The Tribunal condoned the delay in filing the appeal and issued an interim injunction restraining the respondent promoter from executing any sale deeds to third parties regarding the unit in question until proof of existing third-party rights is provided.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The appeal is dismissed as not pressed following an out-of-court settlement between the appellant-allottee and the respondent-promoter, noting that funds recovered via U.P. RERA execution proceedings are to be disbursed to the appellant. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The appeal is dismissed as not pressed following an out-of-court settlement between the appellant-allottee and the respondent-promoter, noting that funds recovered via U.P. RERA execution proceedings are to be disbursed to the appellant.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kshemendra Shukla

Respondent Advocate(s)

  • Harish Pandey

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126030502024-21-08-2025

The appeal is dismissed as not pressed following an out-of-court settlement between the appellant-allottee and the respondent-promoter, noting that funds recovered via U.P. RERA execution proceedings are to be disbursed to the appellant.

INTERIM_ORDEROrder ID: 0901126030502024-21-04-2025

The Tribunal noted that the respondent promoter executed a sale deed to a third party in breach of a prior decree, and upon the respondent's request to attempt a settlement, the matter is adjourned to 15.05.2025.

INTERIM_ORDEROrder ID: 0901126030502024-24-03-2025

The Tribunal adjourned the appeal to 21.04.2025 and imposed a cost of Rs. 1,000/- to be paid by the respondent to the appellant due to the respondent's request for adjournment.

INTERIM_ORDEROrder ID: 0901126030502024-30-09-2024

The Tribunal condoned the delay in filing the appeal and issued an interim injunction restraining the respondent promoter from executing any sale deeds to third parties regarding the unit in question until proof of existing third-party rights is provided.

TathyaGrid RERA Intelligence AI

Need to research all rulings for krishna estate developers pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →