Appellant / Complainant
Lucknow Development Authority
Respondent
Swati Singh, Shashank Singh, Shagun Srivastava
₹13,95,068
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126030232022 by Lucknow Development Authority against Swati Singh, Shashank Singh, Shagun Srivastava before up_rera.
Hearing
The Tribunal modified the previous order to mandate that the promoter pay delay interest at MCLR+1% from 01.08.2019 until the date of physical possession (23.05.2025) and awarded litigation costs of Rs. 20,000 to the respondent.
Hearing
The appeal is adjourned to 11.02.2026 for orders due to a technical glitch with the NIC server.
Hearing
The Tribunal granted a request from the appellant's counsel to list the case for orders on February 2, 2026, and directed the appellant to upload their 2019 advertisement by that date.
Hearing
At the request of the appellant's counsel, the matter is adjourned and listed for orders on January 30, 2026.
Hearing
The Tribunal heard arguments regarding a dispute over delay interest and adjourned the matter for orders on 19.01.2026.
Hearing
The Tribunal granted a request from the appellant's counsel to adjourn the matter, rescheduling the appeal for orders on 12.01.2026.
Hearing
The Tribunal granted a request to list the appeal for orders or hearing on November 28, 2025.
Hearing
The Tribunal noted the appellant's submission that possession of the unit has been handed over to the respondent and adjourned the matter for hearing on 19.11.2025.
Hearing
The Tribunal granted an adjournment application filed by the appellant and rescheduled the appeal for hearing on 11.11.2025.
Hearing
The Tribunal noted the appellant's submission regarding the execution of the sale deed and delivery of possession, and subsequently adjourned the matter to 14.10.2025 for the exchange of pleadings.
Hearing
The Tribunal granted a request to list the appeal for orders or hearing on 16.09.2025.
Hearing
The Tribunal noted the appellant's submission regarding the execution of the sale deed and delivery of possession, and scheduled the appeal for a final hearing on 26.08.2025.
Hearing
The Tribunal noted the execution of the conveyance deed and handover of possession, and scheduled the appeal for further hearing on the issue of delay interest on 05.08.2025.
Hearing
Upon the joint request of the counsel for both parties, the tribunal has adjourned the appeal and scheduled it for a hearing on 15.07.2025.
Hearing
The Tribunal noted the parties' submissions regarding the deposit of the remaining consideration amount and scheduled the appeal for further hearing on 22.05.2025.
Hearing
The Tribunal adjourned the proceedings due to the absence of both parties and rescheduled the hearing for May 5, 2025.
Hearing
The Tribunal directs the respondent allottee to deposit the balance amount of Rs 5 Lakh within three weeks, upon which the appellant promoter must handover possession of the unit in a habitable condition within 60 days.
Hearing
The appeal has been adjourned at the request of the appellant's counsel and is scheduled to be listed on 10.03.2025.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for orders/hearing on 07.02.2025, noting that no further adjournments will be permitted.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal for orders on January 7, 2025.
Hearing
The Tribunal has rescheduled the hearing of Appeal-395/2022 to 25-11-2024 following a request from the counsel representing the parties.
Hearing
The Tribunal has granted a joint request from the counsels for both parties to list the appeal for a final hearing on 25.10.2024.
Hearing
The Tribunal noted that pleadings have been exchanged and scheduled the appeal for orders/hearing on 20.09.2024.
Hearing
The Tribunal granted the appellant, Lucknow Development Authority, one week's time to file a demand letter and scheduled the case for orders on 14.08.2024.
Hearing
The Tribunal granted the appellant a two-day extension to ensure compliance with the previous order dated 08.05.2024 and scheduled the next hearing for 19.07.2024.
Hearing
The Tribunal granted the appellant one week's time to place on record a final demand letter issued by the respondent regarding the execution of a conveyance deed, and scheduled the matter for orders on 24.05.2024.
Hearing
The Tribunal has rescheduled the hearing of Appeal-395/2022 to 08.05.2024 at the request of the appellant's counsel, with a strict directive that no further adjournments will be granted.
Hearing
This is a procedural order indicating that no time was left for arguments or proceedings during the hearing on April 3, 2024.
Hearing
The Tribunal has issued a routine order to list the appeal on 03.04.2024.
Hearing
The Tribunal granted the appellant 10 days to file a reply to the respondent's objection and scheduled the next hearing for February 29, 2024.
Hearing
The Tribunal adjourned the proceedings and rescheduled the hearing for 17.10.2023 due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh.
Hearing
The Tribunal granted a one-week extension to the appellant to file a reply to the respondents' objections and directed the submission of a soft copy of said reply. The matter is scheduled for hearing on 11.09.2023.
Hearing
The Tribunal granted the appellant 10 days' time for preparation and rescheduled the appeal for hearing on 09.08.2023.
Further Order
The Tribunal granted the Lucknow Development Authority time to file its Vakalatnama and reply to the respondents' objections, scheduling the next hearing for July 13, 2023.
Further Order
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 06.01.2023.
Further Order
The Tribunal adjourned the appeal due to the absence of the appellant and scheduled the matter for further orders on 07.12.2022.
Delay condonation
The Tribunal allowed the delay condonation application, noting a negligible two-day delay, and directed the registry to register the defective appeal as a regular appeal. Additionally, the applicant was directed to file an amendment application within three days, with respondents permitted to file objections thereafter.
Delay condonation
The Tribunal granted the applicant one week to file a better affidavit for condonation of delay and granted the respondent 10 days to file objections, scheduling the next hearing for September 12, 2022.
Delay condonation
The Tribunal granted the respondents one week to file objections to the delay condonation application and grounds of appeal, directing a schedule for electronic exchange of documents and listing the matter for 17.08.2022.
Defect Removal
The Tribunal verified the deposit of Rs. 4,13,832/- required under Section 43(5) of the Act and issued notice to the respondents regarding the application for condonation of delay, returnable on 19.07.2022.
Tribunal Order #0901126030232022-10-03-2025
The Tribunal directs the respondent allottee to deposit the balance amount of Rs 5 Lakh within three weeks, upon which the appellant promoter must handover possession of the unit in a habitable condition within 60 days.
Tribunal Order #0901126030232022-11-02-2026
The Tribunal modified the previous order to mandate that the promoter pay delay interest at MCLR+1% from 01.08.2019 until the date of physical possession (23.05.2025) and awarded litigation costs of Rs. 20,000 to the respondent.
Tribunal Order #0901126030232022-12-09-2022
The Tribunal allowed the delay condonation application, noting a negligible two-day delay, and directed the registry to register the defective appeal as a regular appeal. Additionally, the applicant was directed to file an amendment application within three days, with respondents permitted to file objections thereafter.
Tribunal Order #0901126030232022-20-06-2022
The Tribunal verified the deposit of Rs. 4,13,832/- required under Section 43(5) of the Act and issued notice to the respondents regarding the application for condonation of delay, returnable on 19.07.2022.
Tribunal Disposal & Final Award Ruling
The Tribunal modified the previous order to mandate that the promoter pay delay interest at MCLR+1% from 01.08.2019 until the date of physical possession (23.05.2025) and awarded litigation costs of Rs. 20,000 to the respondent. Awarded in favor of Respondent. Awarded interest rate: MCLR+1 percent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal modified the previous order to mandate that the promoter pay delay interest at MCLR+1% from 01.08.2019 until the date of physical possession (23.05.2025) and awarded litigation costs of Rs. 20,000 to the respondent.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1 percent
Interest Period
w.e.f. 01.08.2019 till the date of handling over physical possession of the unit i.e. 23.05.2025
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Abhishek Khare
Respondent Advocate(s)
- Gautam Johri
Official RERA Tribunal Orders (4)
The Tribunal directs the respondent allottee to deposit the balance amount of Rs 5 Lakh within three weeks, upon which the appellant promoter must handover possession of the unit in a habitable condition within 60 days.
The Tribunal modified the previous order to mandate that the promoter pay delay interest at MCLR+1% from 01.08.2019 until the date of physical possession (23.05.2025) and awarded litigation costs of Rs. 20,000 to the respondent.
The Tribunal allowed the delay condonation application, noting a negligible two-day delay, and directed the registry to register the defective appeal as a regular appeal. Additionally, the applicant was directed to file an amendment application within three days, with respondents permitted to file objections thereafter.
The Tribunal verified the deposit of Rs. 4,13,832/- required under Section 43(5) of the Act and issued notice to the respondents regarding the application for condonation of delay, returnable on 19.07.2022.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.