Appellant / Complainant
Shree Kunj Bihariji Infracon Pvt. Ltd.
Respondent
U.P. Real Estate Regulatory Authority
shree kunj bihariji infracon pvt. ltd.
₹2,00,000
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126029412024 by Shree Kunj Bihariji Infracon Pvt. Ltd. against U.P. Real Estate Regulatory Authority before up_rera.
For Order
The Appellate Tribunal dismissed the appeal filed by M/S Shree Kunj Bihariji Infracon Pvt. Ltd., upholding a Rs. 2 lakh penalty imposed by U.P. RERA for violating Section 11(2) of the Act, 2016, ruling that the promoter is responsible for ensuring advertisements include the project's registration number and RERA website, regardless of whether the advertisement was published by an unauthorized third party.
For Order
The appellant's counsel requested an adjournment, resulting in the case being rescheduled for orders/hearing on 17.03.2025.
For Order
The Tribunal granted a request for adjournment due to counsel illness and rescheduled the hearing of the appeal to 24.02.2025.
For Order
The Tribunal granted time to the Respondent's counsel to prepare their brief and adjourned the appeal for hearing to 20.02.2025.
For Order
The Tribunal noted the filing of a rejoinder affidavit by the appellant and scheduled the appeal for hearing on 11.02.2025.
For Order
The Tribunal granted a request by the appellant's counsel to reschedule the hearing to 21.01.2025 and directed the appellant to file a rejoinder affidavit in the interim.
For Order
The Tribunal granted the appellant 10 days to file a rejoinder and scheduled the appeal for hearing on December 13, 2024.
Arguments
The Tribunal has scheduled the appeal for its next hearing on 14.11.2024 and permitted the filing of a rejoinder before that date.
Arguments
The Tribunal granted one week's extension to the respondent for filing objections and rescheduled the appeal hearing to 21.10.2024.
Admission
The Tribunal granted the respondent 10 days to file objections and directed the appellant to file a reply within one week of receiving them. The case is scheduled for orders on 04.10.2024.
Admission
The Tribunal noted the filing of the affidavit of service and scheduled the appeal for a hearing on 12.09.2024.
Admission
The Tribunal has issued notice to the Respondent regarding an appeal against a Rs 2,00,000 penalty imposed on the appellant for an advertisement, with the matter scheduled for hearing on 21.08.2024.
Tribunal Order #0901126029412024-17-03-2025
The Appellate Tribunal dismissed the appeal filed by M/S Shree Kunj Bihariji Infracon Pvt. Ltd., upholding a Rs. 2 lakh penalty imposed by U.P. RERA for violating Section 11(2) of the Act, 2016, ruling that the promoter is responsible for ensuring advertisements include the project's registration number and RERA website, regardless of whether the advertisement was published by an unauthorized third party.
Tribunal Order #0901126029412024-24-07-2024
The Tribunal has issued notice to the Respondent regarding an appeal against a Rs 2,00,000 penalty imposed on the appellant for an advertisement, with the matter scheduled for hearing on 21.08.2024.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal dismissed the appeal filed by M/S Shree Kunj Bihariji Infracon Pvt. Ltd., upholding a Rs. 2 lakh penalty imposed by U.P. RERA for violating Section 11(2) of the Act, 2016, ruling that the promoter is responsible for ensuring advertisements include the project's registration number and RERA website, regardless of whether the advertisement was published by an unauthorized third party. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal dismissed the appeal filed by M/S Shree Kunj Bihariji Infracon Pvt. Ltd., upholding a Rs. 2 lakh penalty imposed by U.P. RERA for violating Section 11(2) of the Act, 2016, ruling that the promoter is responsible for ensuring advertisements include the project's registration number and RERA website, regardless of whether the advertisement was published by an unauthorized third party.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Saurabh Misra
- Krishna Kumar Singh
Respondent Advocate(s)
- Shireesh Kumar
Official RERA Tribunal Orders (2)
The Appellate Tribunal dismissed the appeal filed by M/S Shree Kunj Bihariji Infracon Pvt. Ltd., upholding a Rs. 2 lakh penalty imposed by U.P. RERA for violating Section 11(2) of the Act, 2016, ruling that the promoter is responsible for ensuring advertisements include the project's registration number and RERA website, regardless of whether the advertisement was published by an unauthorized third party.
The Tribunal has issued notice to the Respondent regarding an appeal against a Rs 2,00,000 penalty imposed on the appellant for an advertisement, with the matter scheduled for hearing on 21.08.2024.
Need to research all rulings for shree kunj bihariji infracon pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.