up_reraStatus: Completed
CASE ID: 0901126029192022

Appellant / Complainant

Arjoo Kumari, Rajeev Ranjan

VS

Respondent

Aims Rg Angel Promoters Private Limited

Developer Firm

aims rg angel promoters private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126029192022 by Arjoo Kumari, Rajeev Ranjan against Aims Rg Angel Promoters Private Limited before up_rera.

2
Stage 121/09/2023

Delay condonation

The U.P. Real Estate Appellate Tribunal dismissed Appeal-318/2022 by reference to the order previously passed in Appeal No. 53/2022.

3
Stage 220/09/2023

Delay condonation

The Tribunal directs the parties to refer to the order previously passed in Appeal No. D 71/2022 for the relevant orders.

4
Stage 311/08/2023

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel and directed the parties to exchange pleadings before the next hearing on 20.09.2023.

5
Stage 430/05/2023

Delay condonation

The Tribunal scheduled the case for hearing on August 11, 2023, to consider an application for condonation of delay.

6
Stage 528/04/2023

Delay condonation

The Tribunal has noted that the appeal is defective and has scheduled it for orders or hearing on 30.05.2023.

7
Stage 620/03/2023

Delay condonation

No text available.

8
Stage 709/02/2023

Delay condonation

No text available.

9
Stage 805/01/2023

Delay condonation

No text available.

10
Stage 905/12/2022

Delay condonation

No text available.

11
Stage 1004/11/2022

Delay condonation

No text available.

12
Stage 1127/09/2022

Delay condonation

No text available.

13
Stage 1207/09/2022

Delay condonation

The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and scheduled the case for hearing on September 27, 2022.

14
Stage 1305/08/2022

Delay condonation

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the matter for hearing on September 7, 2022.

15
Stage 1419/07/2022

Defect Removal

The Tribunal has listed this defective appeal for a hearing on 05.08.2022 and referred to a previous order dated 19.07.2022.

16
Stage 1531/05/2022

Defect Removal

The Tribunal directed the appellant to rectify filing defects and established a timeline for the respondent to file objections to the condonation of delay application before the next hearing on 19.07.2022.

17
Stage 16Final Ruling Order

Tribunal Order #0901126029192022-21-09-2023

The U.P. Real Estate Appellate Tribunal dismissed Appeal-318/2022 by reference to the order previously passed in Appeal No. 53/2022.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed Appeal-318/2022 by reference to the order previously passed in Appeal No. 53/2022. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed Appeal-318/2022 by reference to the order previously passed in Appeal No. 53/2022.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Fuhar Gupta
  • Prashant Kumar

Respondent Advocate(s)

  • Azhar Ikram
  • Manish Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126029192022-21-09-2023

The U.P. Real Estate Appellate Tribunal dismissed Appeal-318/2022 by reference to the order previously passed in Appeal No. 53/2022.

TathyaGrid RERA Intelligence AI

Need to research all rulings for aims rg angel promoters private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →