up_reraStatus: Completed
CASE ID: 0901126029162024

Appellant / Complainant

Oro Real Infra Llp

VS

Respondent

Uttar Pradesh Real Estate Regulatory Authority

Developer Firm

oro real infra llp

Disputed Amount

2,00,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126029162024 by Oro Real Infra Llp against Uttar Pradesh Real Estate Regulatory Authority before up_rera.

2
Stage 126/09/2025

for delivery of Judgment/Order

The Appellate Tribunal dismissed the appeals filed by Oro Infra Developers LLP and others, upholding the penalty of Rs. Two Lakhs imposed by the UP RERA for violating Section 11(2) of the Act by failing to prominently display the RERA registration number and authority website on the initial thumbnail/page of their digital advertisement.

3
Stage 210/07/2025

Final Hearing

The Tribunal heard oral arguments from the counsel for both the appellant and respondent in Appeal-246/2024 and subsequently reserved the judgment for delivery.

4
Stage 316/05/2025

Final Hearing

The Tribunal heard arguments from both counsels and adjourned the matter to 10.07.2025 for further hearing or rest of arguments.

5
Stage 422/04/2025

Hearing

The Tribunal granted the appellant's request for more time to prepare their brief and rescheduled the appeal for a final hearing on 16.05.2025.

6
Stage 524/03/2025

Hearing

The Tribunal granted a joint request from the counsel for both parties to reschedule the hearing of Appeal-246/2024 to 22.04.2025.

7
Stage 620/02/2025

Hearing

The Tribunal granted a request for adjournment on behalf of the respondent's counsel and rescheduled the appeal for hearing on 24.03.2025.

8
Stage 705/02/2025

Hearing

The Tribunal granted a request from the appellant's counsel to adjourn the matter and scheduled the appeal for orders/hearing on 20.02.2025.

9
Stage 803/01/2025

Hearing

Upon the joint request of the counsel for both parties, the Tribunal has scheduled the case for a final hearing on February 5, 2025.

10
Stage 905/12/2024

Hearing

The Tribunal granted a request to list the appeal on 03.01.2025 and directed both parties to complete their pleadings in the interim.

11
Stage 1004/11/2024

Admission

The Tribunal noted the absence of advocates due to a Bar Council resolution and scheduled the appeal for its next hearing on 05.12.2024.

12
Stage 1124/09/2024

Admission

The Tribunal granted the respondent one final opportunity to file objections within 10 days and scheduled the next hearing for November 4, 2024.

13
Stage 1222/08/2024

Admission

The Tribunal accepted service of notice upon the respondent and directed them to file objections within 10 days, with a subsequent hearing scheduled for 24.09.2024.

14
Stage 1319/07/2024

Admission

The Tribunal issued notice to the respondent regarding the appeal filed by Oro Real Infra LLP and outlined the procedural requirements for service of notice and filing of objections.

15
Stage 14Final Ruling Order

Tribunal Order #0901126029162024-26-09-2025

The Appellate Tribunal dismissed the appeals filed by Oro Infra Developers LLP and others, upholding the penalty of Rs. Two Lakhs imposed by the UP RERA for violating Section 11(2) of the Act by failing to prominently display the RERA registration number and authority website on the initial thumbnail/page of their digital advertisement.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeals filed by Oro Infra Developers LLP and others, upholding the penalty of Rs. Two Lakhs imposed by the UP RERA for violating Section 11(2) of the Act by failing to prominently display the RERA registration number and authority website on the initial thumbnail/page of their digital advertisement. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeals filed by Oro Infra Developers LLP and others, upholding the penalty of Rs. Two Lakhs imposed by the UP RERA for violating Section 11(2) of the Act by failing to prominently display the RERA registration number and authority website on the initial thumbnail/page of their digital advertisement.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Deepak Agarwal
  • Rajat Bhatia

Respondent Advocate(s)

  • Shireesh Kumar

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126029162024-26-09-2025

The Appellate Tribunal dismissed the appeals filed by Oro Infra Developers LLP and others, upholding the penalty of Rs. Two Lakhs imposed by the UP RERA for violating Section 11(2) of the Act by failing to prominently display the RERA registration number and authority website on the initial thumbnail/page of their digital advertisement.