CASE ID: 0901126028792024

Appellant / Complainant

Narain Singh

VS

Respondent

Abhilasha Singh, Uttar Pradesh Real Estate Regulatory Authority, Aims Golf Town Developers Pvt. Ltd.

Developer Firm

aims golf town developers pvt. ltd.

Disputed Amount

34,50,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Refund of InvestmentJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126028792024 by Narain Singh against Abhilasha Singh, Uttar Pradesh Real Estate Regulatory Authority, Aims Golf Town Developers Pvt. Ltd. before up_rera.

Refund of InvestmentJurisdiction & Maintainability
2
Stage 102/07/2025

Further Hearing

The Appellate Tribunal set aside and quashed the U.P. RERA order dated 04.03.2024, ruling that the appellant was a necessary party whose rights were affected and should have been impleaded in the original complaint.

3
Stage 202/05/2025

For Order

The Tribunal directs the first respondent to file an affidavit stating that the impugned judgment and decree will not be pressed against the appellant's specific unit allotment and investment.

4
Stage 307/04/2025

Delay condonation

The Tribunal allowed the application for condonation of delay, condoning the 59-day delay in filing the appeal and directing the Registry to convert the defective appeal into a regular appeal.

5
Stage 412/03/2025

Delay condonation

The Tribunal granted an adjournment following a request from the respondent's counsel and scheduled the case for hearing/orders on 07.04.2025.

6
Stage 506/02/2025

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the case for orders on March 12, 2025.

7
Stage 621/01/2025

Delay condonation

The Tribunal granted an adjournment request made on behalf of the appellant and rescheduled the appeal for hearing on 06.02.2025.

8
Stage 718/12/2024

Delay condonation

The Tribunal granted a request from both parties to list the appeal for hearing on the application for condonation of delay on 21.01.2024, with a directive to complete the exchange of pleadings in the interim.

9
Stage 819/11/2024

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 18.12.2024.

10
Stage 904/10/2024

Delay condonation

The Tribunal granted the respondent two weeks to file an objection to the appeal and ordered that all execution proceedings pursuant to the impugned order be kept in abeyance until the next hearing on 19.11.2024.

11
Stage 1005/09/2024

Delay condonation

The Tribunal granted respondents 1 and 3 ten days to file objections and directed the applicant to file a reply within seven days of receiving the soft copies. The matter is listed for orders on 04.10.2024.

12
Stage 1106/08/2024

Defect Removal

The Tribunal issued notice to the respondent and directed the appellant to serve the notice, scheduling the next hearing for 05.09.2024.

13
Stage 1229/07/2024

Defect Removal

The Tribunal adjourned the proceedings due to the absence of the applicant and rescheduled the matter for orders on 06.08.2024.

14
Stage 1326/07/2024

Defect Removal

The Tribunal granted the appellant three days to upload a legible copy of the Builder Buyer Agreement (BBA) and scheduled the next hearing for 29.07.2024.

15
Stage 1423/07/2024

Defect Removal

The Tribunal noted a defect regarding the legibility of Annexure-4 and directed the appellant's counsel to upload a legible copy within three days, listing the matter for orders on 26.07.2024.

16
Stage 1519/07/2024

Defect Removal

The Tribunal granted a request by the appellant's counsel to list the appeal for orders on 23.07.2024.

17
Stage 16Final Ruling Order

Tribunal Order #0901126028792024-02-07-2025

The Appellate Tribunal set aside and quashed the U.P. RERA order dated 04.03.2024, ruling that the appellant was a necessary party whose rights were affected and should have been impleaded in the original complaint.

18
Stage 17Interim Order

Tribunal Order #0901126028792024-07-04-2025

The Tribunal allowed the application for condonation of delay, condoning the 59-day delay in filing the appeal and directing the Registry to convert the defective appeal into a regular appeal.

19
Stage 18Interim Order

Tribunal Order #0901126028792024-02-05-2025

The Tribunal directs the first respondent to file an affidavit stating that the impugned judgment and decree will not be pressed against the appellant's specific unit allotment and investment.

20
Stage 19Interim Order

Tribunal Order #0901126028792024-04-10-2024

The Tribunal granted the respondent two weeks to file an objection to the appeal and ordered that all execution proceedings pursuant to the impugned order be kept in abeyance until the next hearing on 19.11.2024.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal set aside and quashed the U.P. RERA order dated 04.03.2024, ruling that the appellant was a necessary party whose rights were affected and should have been impleaded in the original complaint. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal set aside and quashed the U.P. RERA order dated 04.03.2024, ruling that the appellant was a necessary party whose rights were affected and should have been impleaded in the original complaint.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Samrat Vaish

Respondent Advocate(s)

  • Rohit Jaiswal
  • Amit Yadav
  • Jayant Gupta

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126028792024-02-07-2025

The Appellate Tribunal set aside and quashed the U.P. RERA order dated 04.03.2024, ruling that the appellant was a necessary party whose rights were affected and should have been impleaded in the original complaint.

INTERIM_ORDEROrder ID: 0901126028792024-07-04-2025

The Tribunal allowed the application for condonation of delay, condoning the 59-day delay in filing the appeal and directing the Registry to convert the defective appeal into a regular appeal.

INTERIM_ORDEROrder ID: 0901126028792024-02-05-2025

The Tribunal directs the first respondent to file an affidavit stating that the impugned judgment and decree will not be pressed against the appellant's specific unit allotment and investment.

INTERIM_ORDEROrder ID: 0901126028792024-04-10-2024

The Tribunal granted the respondent two weeks to file an objection to the appeal and ordered that all execution proceedings pursuant to the impugned order be kept in abeyance until the next hearing on 19.11.2024.

TathyaGrid RERA Intelligence AI

Need to research all rulings for aims golf town developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →