Appellant / Complainant
Narain Singh
Respondent
Abhilasha Singh, Uttar Pradesh Real Estate Regulatory Authority, Aims Golf Town Developers Pvt. Ltd.
aims golf town developers pvt. ltd.
₹34,50,000
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126028792024 by Narain Singh against Abhilasha Singh, Uttar Pradesh Real Estate Regulatory Authority, Aims Golf Town Developers Pvt. Ltd. before up_rera.
Further Hearing
The Appellate Tribunal set aside and quashed the U.P. RERA order dated 04.03.2024, ruling that the appellant was a necessary party whose rights were affected and should have been impleaded in the original complaint.
For Order
The Tribunal directs the first respondent to file an affidavit stating that the impugned judgment and decree will not be pressed against the appellant's specific unit allotment and investment.
Delay condonation
The Tribunal allowed the application for condonation of delay, condoning the 59-day delay in filing the appeal and directing the Registry to convert the defective appeal into a regular appeal.
Delay condonation
The Tribunal granted an adjournment following a request from the respondent's counsel and scheduled the case for hearing/orders on 07.04.2025.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the case for orders on March 12, 2025.
Delay condonation
The Tribunal granted an adjournment request made on behalf of the appellant and rescheduled the appeal for hearing on 06.02.2025.
Delay condonation
The Tribunal granted a request from both parties to list the appeal for hearing on the application for condonation of delay on 21.01.2024, with a directive to complete the exchange of pleadings in the interim.
Delay condonation
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 18.12.2024.
Delay condonation
The Tribunal granted the respondent two weeks to file an objection to the appeal and ordered that all execution proceedings pursuant to the impugned order be kept in abeyance until the next hearing on 19.11.2024.
Delay condonation
The Tribunal granted respondents 1 and 3 ten days to file objections and directed the applicant to file a reply within seven days of receiving the soft copies. The matter is listed for orders on 04.10.2024.
Defect Removal
The Tribunal issued notice to the respondent and directed the appellant to serve the notice, scheduling the next hearing for 05.09.2024.
Defect Removal
The Tribunal adjourned the proceedings due to the absence of the applicant and rescheduled the matter for orders on 06.08.2024.
Defect Removal
The Tribunal granted the appellant three days to upload a legible copy of the Builder Buyer Agreement (BBA) and scheduled the next hearing for 29.07.2024.
Defect Removal
The Tribunal noted a defect regarding the legibility of Annexure-4 and directed the appellant's counsel to upload a legible copy within three days, listing the matter for orders on 26.07.2024.
Defect Removal
The Tribunal granted a request by the appellant's counsel to list the appeal for orders on 23.07.2024.
Tribunal Order #0901126028792024-02-07-2025
The Appellate Tribunal set aside and quashed the U.P. RERA order dated 04.03.2024, ruling that the appellant was a necessary party whose rights were affected and should have been impleaded in the original complaint.
Tribunal Order #0901126028792024-07-04-2025
The Tribunal allowed the application for condonation of delay, condoning the 59-day delay in filing the appeal and directing the Registry to convert the defective appeal into a regular appeal.
Tribunal Order #0901126028792024-02-05-2025
The Tribunal directs the first respondent to file an affidavit stating that the impugned judgment and decree will not be pressed against the appellant's specific unit allotment and investment.
Tribunal Order #0901126028792024-04-10-2024
The Tribunal granted the respondent two weeks to file an objection to the appeal and ordered that all execution proceedings pursuant to the impugned order be kept in abeyance until the next hearing on 19.11.2024.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal set aside and quashed the U.P. RERA order dated 04.03.2024, ruling that the appellant was a necessary party whose rights were affected and should have been impleaded in the original complaint. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal set aside and quashed the U.P. RERA order dated 04.03.2024, ruling that the appellant was a necessary party whose rights were affected and should have been impleaded in the original complaint.
Ruling Awarded To
Appellant
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Samrat Vaish
Respondent Advocate(s)
- Rohit Jaiswal
- Amit Yadav
- Jayant Gupta
Official RERA Tribunal Orders (4)
The Appellate Tribunal set aside and quashed the U.P. RERA order dated 04.03.2024, ruling that the appellant was a necessary party whose rights were affected and should have been impleaded in the original complaint.
The Tribunal allowed the application for condonation of delay, condoning the 59-day delay in filing the appeal and directing the Registry to convert the defective appeal into a regular appeal.
The Tribunal directs the first respondent to file an affidavit stating that the impugned judgment and decree will not be pressed against the appellant's specific unit allotment and investment.
The Tribunal granted the respondent two weeks to file an objection to the appeal and ordered that all execution proceedings pursuant to the impugned order be kept in abeyance until the next hearing on 19.11.2024.
Need to research all rulings for aims golf town developers pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.