Appellant / Complainant
Ashwani Kumar Chaudhary, Indu Rani
Respondent
Gaursons Realtech Private Limited
gaursons realtech private limited
₹28,05,484
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126028622022 by Ashwani Kumar Chaudhary, Indu Rani against Gaursons Realtech Private Limited before up_rera.
for delivery of Judgment/Order
The Tribunal partially allowed the appeals, ruling that court-ordered construction stays do not constitute 'force majeure' and modifying the interest period for delayed possession to be paid at the rate of MCLR+1%.
Hearing
The Tribunal heard arguments from both counsel and has reserved its judgment for a later date.
Hearing
The Tribunal noted that the appeal is ready for hearing and scheduled it for a subsequent hearing on 19.02.2024.
Hearing
The Tribunal adjourned the proceedings scheduled for 04.09.2023 due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh, rescheduling the hearing to 12.10.2023.
For Order
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the appeal for hearing on September 4, 2023.
Exchange of pleadings
The Tribunal noted a procedural error where the respondent filed objections belonging to a different appeal; the respondent agreed to file corrected objections within a week, with the matter listed for hearing on 13.07.2023.
Exchange of pleadings
The Tribunal directed the appellant to file a replication/rejoinder against the respondent's reply and scheduled the next hearing for December 6, 2022.
Exchange of pleadings
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 10.11.2022, while directing the respondent to provide advance notice for future adjournments to avoid harassing the appellant's counsel.
For Order
The Tribunal directed the respondent to file a reply to the memo of appeal and serve it to the appellant via email before the next hearing scheduled for 10.10.2022.
Further Order
The Tribunal condoned a 155-day delay in filing the appeal due to the COVID-19 pandemic period and directed the respondent to file a reply to the grounds of appeal.
Defect Removal
The Tribunal directed the appellant to provide copies of the delay condonation application and the memo of appeal to the respondent's counsel within one week and scheduled the matter for August 8, 2022.
Tribunal Order #0901126028622022-07-05-2024
The Tribunal partially allowed the appeals, ruling that court-ordered construction stays do not constitute 'force majeure' and modifying the interest period for delayed possession to be paid at the rate of MCLR+1%.
Tribunal Order #0901126028622022-08-08-2022
The Tribunal condoned a 155-day delay in filing the appeal due to the COVID-19 pandemic period and directed the respondent to file a reply to the grounds of appeal.
Tribunal Disposal & Final Award Ruling
The Tribunal partially allowed the appeals, ruling that court-ordered construction stays do not constitute 'force majeure' and modifying the interest period for delayed possession to be paid at the rate of MCLR+1%. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal partially allowed the appeals, ruling that court-ordered construction stays do not constitute 'force majeure' and modifying the interest period for delayed possession to be paid at the rate of MCLR+1%.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR + 1%
Interest Period
from 11.08.2017 till the date of receipt of OC for Ashwani Kumar Chaudhary and from 25.09.2017 till the date of receipt of OC for Ashish Kumar and Ritu Chaudhary
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Asha Jain Madan
Respondent Advocate(s)
- Samrat Vaish
- Mohit Yadav
Official RERA Tribunal Orders (2)
The Tribunal partially allowed the appeals, ruling that court-ordered construction stays do not constitute 'force majeure' and modifying the interest period for delayed possession to be paid at the rate of MCLR+1%.
The Tribunal condoned a 155-day delay in filing the appeal due to the COVID-19 pandemic period and directed the respondent to file a reply to the grounds of appeal.
Need to research all rulings for gaursons realtech private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.