up_reraStatus: Completed
CASE ID: 0901126028622022

Appellant / Complainant

Ashwani Kumar Chaudhary, Indu Rani

VS

Respondent

Gaursons Realtech Private Limited

Developer Firm

gaursons realtech private limited

Disputed Amount

28,05,484

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferUnfair Cancellation & Forfeiture

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

20 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126028622022 by Ashwani Kumar Chaudhary, Indu Rani against Gaursons Realtech Private Limited before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferUnfair Cancellation & Forfeiture
2
Stage 107/05/2024

for delivery of Judgment/Order

The Tribunal partially allowed the appeals, ruling that court-ordered construction stays do not constitute 'force majeure' and modifying the interest period for delayed possession to be paid at the rate of MCLR+1%.

3
Stage 219/02/2024

Hearing

The Tribunal heard arguments from both counsel and has reserved its judgment for a later date.

4
Stage 316/01/2024

Hearing

The Tribunal noted that the appeal is ready for hearing and scheduled it for a subsequent hearing on 19.02.2024.

5
Stage 412/10/2023

Hearing

No text available.

6
Stage 504/09/2023

Hearing

The Tribunal adjourned the proceedings scheduled for 04.09.2023 due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh, rescheduling the hearing to 12.10.2023.

7
Stage 613/07/2023

For Order

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the appeal for hearing on September 4, 2023.

8
Stage 702/05/2023

Exchange of pleadings

The Tribunal noted a procedural error where the respondent filed objections belonging to a different appeal; the respondent agreed to file corrected objections within a week, with the matter listed for hearing on 13.07.2023.

9
Stage 821/03/2023

Exchange of pleadings

No text available.

10
Stage 910/02/2023

Exchange of pleadings

No text available.

11
Stage 1006/01/2023

Exchange of pleadings

No text available.

12
Stage 1106/12/2022

Exchange of pleadings

No text available.

13
Stage 1210/11/2022

Exchange of pleadings

The Tribunal directed the appellant to file a replication/rejoinder against the respondent's reply and scheduled the next hearing for December 6, 2022.

14
Stage 1310/10/2022

Exchange of pleadings

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 10.11.2022, while directing the respondent to provide advance notice for future adjournments to avoid harassing the appellant's counsel.

15
Stage 1405/09/2022

For Order

The Tribunal directed the respondent to file a reply to the memo of appeal and serve it to the appellant via email before the next hearing scheduled for 10.10.2022.

16
Stage 1508/08/2022

Further Order

The Tribunal condoned a 155-day delay in filing the appeal due to the COVID-19 pandemic period and directed the respondent to file a reply to the grounds of appeal.

17
Stage 1613/06/2022

Defect Removal

The Tribunal directed the appellant to provide copies of the delay condonation application and the memo of appeal to the respondent's counsel within one week and scheduled the matter for August 8, 2022.

18
Stage 17Final Ruling Order

Tribunal Order #0901126028622022-07-05-2024

The Tribunal partially allowed the appeals, ruling that court-ordered construction stays do not constitute 'force majeure' and modifying the interest period for delayed possession to be paid at the rate of MCLR+1%.

19
Stage 18Interim Order

Tribunal Order #0901126028622022-08-08-2022

The Tribunal condoned a 155-day delay in filing the appeal due to the COVID-19 pandemic period and directed the respondent to file a reply to the grounds of appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal partially allowed the appeals, ruling that court-ordered construction stays do not constitute 'force majeure' and modifying the interest period for delayed possession to be paid at the rate of MCLR+1%. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.

Disposal Winner: AppellantInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal partially allowed the appeals, ruling that court-ordered construction stays do not constitute 'force majeure' and modifying the interest period for delayed possession to be paid at the rate of MCLR+1%.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1%

Interest Period

from 11.08.2017 till the date of receipt of OC for Ashwani Kumar Chaudhary and from 25.09.2017 till the date of receipt of OC for Ashish Kumar and Ritu Chaudhary

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 11(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Asha Jain Madan

Respondent Advocate(s)

  • Samrat Vaish
  • Mohit Yadav

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126028622022-07-05-2024

The Tribunal partially allowed the appeals, ruling that court-ordered construction stays do not constitute 'force majeure' and modifying the interest period for delayed possession to be paid at the rate of MCLR+1%.

INTERIM_ORDEROrder ID: 0901126028622022-08-08-2022

The Tribunal condoned a 155-day delay in filing the appeal due to the COVID-19 pandemic period and directed the respondent to file a reply to the grounds of appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for gaursons realtech private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →