Appellant / Complainant
Tripti Agrawal
Respondent
Antriksh Developers & Promoters Pvt Ltd
antriksh developers & promoters pvt ltd
₹4,28,500
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126028582024 by Tripti Agrawal against Antriksh Developers & Promoters Pvt Ltd before up_rera.
Hearing
The Tribunal partially allowed the appeal, directing the respondent to pay delay interest at the rate of MCLR+1% from December 2012 until physical possession on March 3, 2017, and setting aside an unjustified demand letter dated October 3, 2020.
Hearing
The Tribunal granted the appellant's request for time to file a rejoinder and scheduled the appeal for final hearing on July 16, 2025.
Hearing
The Tribunal has granted a request to list the case for orders or hearing on May 23, 2025.
Hearing
The Tribunal has scheduled the case for orders on April 22, 2025, and directed that Sri Siddharth Nandwani be recorded as counsel for the respondent.
Hearing
The Tribunal adjourned the appeal to 24.03.2025 and directed the parties to complete their pleadings in the interim.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 24.02.2025.
Hearing
The Tribunal granted the respondent additional time to file an application to recall the order dated 05.12.2024 and scheduled the case for orders on 05.02.2025.
Delay condonation
The Tribunal allowed the appellant's application for condonation of delay and directed the Registry to convert the defective appeal into a regular appeal, scheduling the next hearing for January 3, 2025.
Delay condonation
The Tribunal decided to proceed ex parte against the respondent, Antriksh Developers & Promoters Pvt Ltd, due to their failure to file objections or appear despite sufficient service, and scheduled an ex parte hearing for 13.12.2024.
Delay condonation
The Tribunal noted that advocates are abstaining from judicial work due to a Bar Council resolution and has rescheduled the appeal for hearing on 05.12.2024.
Delay condonation
The Tribunal granted the respondent an extension of 10 days to file objections to the application for condonation of delay and the appeal, with a subsequent deadline for the appellant to file a reply.
Delay condonation
The Tribunal accepted proof of service upon the respondent and directed the respondent to file objections within 10 days, with the matter listed for hearing on 24.09.2024.
Delay condonation
The Tribunal issued notice to the respondent regarding the appeal and application for condonation of delay, directing the applicant to serve the respondent via speed-post and email before the next hearing on 22.08.2024.
Tribunal Order #0901126028582024-13-12-2024
The Tribunal allowed the appellant's application for condonation of delay and directed the Registry to convert the defective appeal into a regular appeal, scheduling the next hearing for January 3, 2025.
Tribunal Order #0901126028582024-16-07-2025
The Tribunal partially allowed the appeal, directing the respondent to pay delay interest at the rate of MCLR+1% from December 2012 until physical possession on March 3, 2017, and setting aside an unjustified demand letter dated October 3, 2020.
Tribunal Order #0901126028582024-05-12-2024
The Tribunal decided to proceed ex parte against the respondent, Antriksh Developers & Promoters Pvt Ltd, due to their failure to file objections or appear despite sufficient service, and scheduled an ex parte hearing for 13.12.2024.
Tribunal Disposal & Final Award Ruling
The Tribunal partially allowed the appeal, directing the respondent to pay delay interest at the rate of MCLR+1% from December 2012 until physical possession on March 3, 2017, and setting aside an unjustified demand letter dated October 3, 2020. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal partially allowed the appeal, directing the respondent to pay delay interest at the rate of MCLR+1% from December 2012 until physical possession on March 3, 2017, and setting aside an unjustified demand letter dated October 3, 2020.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1%
Interest Period
from December 2012 till 03.03.2017
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Vineet K Singh Bisen
Respondent Advocate(s)
- Siddharth Nandwani
Official RERA Tribunal Orders (3)
The Tribunal allowed the appellant's application for condonation of delay and directed the Registry to convert the defective appeal into a regular appeal, scheduling the next hearing for January 3, 2025.
The Tribunal partially allowed the appeal, directing the respondent to pay delay interest at the rate of MCLR+1% from December 2012 until physical possession on March 3, 2017, and setting aside an unjustified demand letter dated October 3, 2020.
The Tribunal decided to proceed ex parte against the respondent, Antriksh Developers & Promoters Pvt Ltd, due to their failure to file objections or appear despite sufficient service, and scheduled an ex parte hearing for 13.12.2024.
Need to research all rulings for antriksh developers & promoters pvt ltd?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.