Appellant / Complainant
Himanshu Chandra
Respondent
Paarth Infra Build Pvt Ltd
paarth infra build pvt ltd
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126028532021 by Himanshu Chandra against Paarth Infra Build Pvt Ltd before up_rera.
Hearing
The appeal was dismissed for want of prosecution due to the non-appearance of the appellant's counsel.
Hearing
The Tribunal has scheduled the appeal for a hearing on March 6, 2025, noting that no parties were present at the time of the order.
Hearing
The Tribunal noted the absence of the appellant's counsel and adjourned the matter to 07.02.2025 for orders/hearing.
Hearing
The Tribunal noted the absence of the appellant's counsel and adjourned the matter, scheduling the appeal for a hearing on 21.01.2025.
Hearing
The Tribunal granted a request to list the appeal for hearing on 18.12.2024.
Final Hearing
The appeal was dismissed for want of prosecution due to the non-appearance of the appellant.
Final Hearing
The Tribunal directed the appellant to file a complete copy of the Allotment Letter within 48 hours and scheduled the matter for hearing on 22.03.2023.
Final Hearing
The Tribunal granted an adjournment application filed by the respondent's counsel and scheduled the next hearing for December 13, 2022.
Final Hearing
The Tribunal corrected a previous erroneous mention of potential settlement between the parties and scheduled the appeal for a hearing on 17.11.2022.
Final Hearing
The Tribunal granted an adjournment application filed by the respondent's counsel and noted the possibility of a settlement between the parties, scheduling the next hearing for 18.10.2022.
Final Hearing
The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the appeal for hearing on 14.09.2022.
Final Hearing
The Tribunal directed the respondent's counsel to file a list of dates and events along with relied-upon cases after exchanging them with the appellant, and scheduled the matter for further orders on 17.08.2022.
Final Hearing
The Tribunal directed the respondent to file a list of dates and events within 10 days and scheduled the appeal for hearing on July 5, 2022.
Final Hearing
The Tribunal heard arguments regarding compensation for delayed registry and directed both parties to file and exchange a list of dates and events before the next hearing on 15.04.2022.
Final Hearing
The Tribunal directed the respondent to file an affidavit clarifying construction details regarding the 'Revti B' tower, its impact on common areas, and the actual delay in possession relative to the Builder Buyer Agreement.
Final Hearing
The Tribunal granted a final three-day extension to the respondent's counsel to rectify defects in the Vakalatnama, warning that failure to do so will result in ex parte proceedings.
Rest Arg. on Merit
The Tribunal directed the respondent's counsel to rectify their Vakalatnama and scheduled the appeal for a hearing on 21.12.2021.
Part Heard
The Tribunal noted that arguments had been heard in part and adjourned the matter to 02.12.2021 for the continuation of arguments.
Delay condonation
The Tribunal ruled that the appeal was filed within the prescribed 60-day limitation period under Section 44(2) of the Act and ordered it to be registered as a Regular Appeal.
Delay condonation
The Tribunal noted the absence of the appellant and ordered that the defective appeal be listed for a further hearing on 25.10.2021.
Delay condonation
The Tribunal directed the Registry to verify the respondent's objections and granted the applicant one week to file a reply via email.
Delay condonation
The Tribunal issued notice on the application for condonation of delay and directed the parties to exchange pleadings via email and upload them to the e-portal before the next hearing on 31.08.2021.
Tribunal Order #0901126028532021-24-12-2021
The Tribunal directed the respondent to file an affidavit clarifying construction details regarding the 'Revti B' tower, its impact on common areas, and the actual delay in possession relative to the Builder Buyer Agreement.
Tribunal Order #0901126028532021-25-10-2021
The Tribunal ruled that the appeal was filed within the prescribed 60-day limitation period under Section 44(2) of the Act and ordered it to be registered as a Regular Appeal.
Tribunal Disposal & Final Award Ruling
Dismissed Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Anurag Arora
Respondent Advocate(s)
- Saurabh Misra
- Azhar Ikram
- Manish Singh
- N A
Official RERA Tribunal Orders (2)
The Tribunal directed the respondent to file an affidavit clarifying construction details regarding the 'Revti B' tower, its impact on common areas, and the actual delay in possession relative to the Builder Buyer Agreement.
The Tribunal ruled that the appeal was filed within the prescribed 60-day limitation period under Section 44(2) of the Act and ordered it to be registered as a Regular Appeal.