up_reraStatus: Completed
CASE ID: 0901126028532021

Appellant / Complainant

Himanshu Chandra

VS

Respondent

Paarth Infra Build Pvt Ltd

Developer Firm

paarth infra build pvt ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

31 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126028532021 by Himanshu Chandra against Paarth Infra Build Pvt Ltd before up_rera.

2
Stage 106/03/2025

Hearing

The appeal was dismissed for want of prosecution due to the non-appearance of the appellant's counsel.

3
Stage 207/02/2025

Hearing

The Tribunal has scheduled the appeal for a hearing on March 6, 2025, noting that no parties were present at the time of the order.

4
Stage 321/01/2025

Hearing

The Tribunal noted the absence of the appellant's counsel and adjourned the matter to 07.02.2025 for orders/hearing.

5
Stage 418/12/2024

Hearing

The Tribunal noted the absence of the appellant's counsel and adjourned the matter, scheduling the appeal for a hearing on 21.01.2025.

6
Stage 527/11/2024

Hearing

The Tribunal granted a request to list the appeal for hearing on 18.12.2024.

7
Stage 603/05/2023

Final Hearing

The appeal was dismissed for want of prosecution due to the non-appearance of the appellant.

8
Stage 722/03/2023

Final Hearing

No text available.

9
Stage 820/02/2023

Final Hearing

The Tribunal directed the appellant to file a complete copy of the Allotment Letter within 48 hours and scheduled the matter for hearing on 22.03.2023.

10
Stage 918/01/2023

Final Hearing

No text available.

11
Stage 1013/12/2022

Final Hearing

No text available.

12
Stage 1117/11/2022

Final Hearing

The Tribunal granted an adjournment application filed by the respondent's counsel and scheduled the next hearing for December 13, 2022.

13
Stage 1219/10/2022

Final Hearing

The Tribunal corrected a previous erroneous mention of potential settlement between the parties and scheduled the appeal for a hearing on 17.11.2022.

14
Stage 1314/09/2022

Final Hearing

The Tribunal granted an adjournment application filed by the respondent's counsel and noted the possibility of a settlement between the parties, scheduling the next hearing for 18.10.2022.

15
Stage 1417/08/2022

Final Hearing

The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the appeal for hearing on 14.09.2022.

16
Stage 1505/07/2022

Final Hearing

The Tribunal directed the respondent's counsel to file a list of dates and events along with relied-upon cases after exchanging them with the appellant, and scheduled the matter for further orders on 17.08.2022.

17
Stage 1628/04/2022

Final Hearing

The Tribunal directed the respondent to file a list of dates and events within 10 days and scheduled the appeal for hearing on July 5, 2022.

18
Stage 1715/04/2022

Final Hearing

No text available.

19
Stage 1822/02/2022

Final Hearing

The Tribunal heard arguments regarding compensation for delayed registry and directed both parties to file and exchange a list of dates and events before the next hearing on 15.04.2022.

20
Stage 1912/01/2022

Final Hearing

No text available.

21
Stage 2024/12/2021

Final Hearing

The Tribunal directed the respondent to file an affidavit clarifying construction details regarding the 'Revti B' tower, its impact on common areas, and the actual delay in possession relative to the Builder Buyer Agreement.

22
Stage 2121/12/2021

Final Hearing

The Tribunal granted a final three-day extension to the respondent's counsel to rectify defects in the Vakalatnama, warning that failure to do so will result in ex parte proceedings.

23
Stage 2202/12/2021

Rest Arg. on Merit

The Tribunal directed the respondent's counsel to rectify their Vakalatnama and scheduled the appeal for a hearing on 21.12.2021.

24
Stage 2317/11/2021

Part Heard

The Tribunal noted that arguments had been heard in part and adjourned the matter to 02.12.2021 for the continuation of arguments.

25
Stage 2425/10/2021

Delay condonation

The Tribunal ruled that the appeal was filed within the prescribed 60-day limitation period under Section 44(2) of the Act and ordered it to be registered as a Regular Appeal.

26
Stage 2521/09/2021

Delay condonation

The Tribunal noted the absence of the appellant and ordered that the defective appeal be listed for a further hearing on 25.10.2021.

27
Stage 2631/08/2021

Delay condonation

The Tribunal directed the Registry to verify the respondent's objections and granted the applicant one week to file a reply via email.

28
Stage 2706/08/2021

Delay condonation

The Tribunal issued notice on the application for condonation of delay and directed the parties to exchange pleadings via email and upload them to the e-portal before the next hearing on 31.08.2021.

29
Stage 28Interim Order

Tribunal Order #0901126028532021-24-12-2021

The Tribunal directed the respondent to file an affidavit clarifying construction details regarding the 'Revti B' tower, its impact on common areas, and the actual delay in possession relative to the Builder Buyer Agreement.

30
Stage 29Interim Order

Tribunal Order #0901126028532021-25-10-2021

The Tribunal ruled that the appeal was filed within the prescribed 60-day limitation period under Section 44(2) of the Act and ordered it to be registered as a Regular Appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anurag Arora

Respondent Advocate(s)

  • Saurabh Misra
  • Azhar Ikram
  • Manish Singh
  • N A

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126028532021-24-12-2021

The Tribunal directed the respondent to file an affidavit clarifying construction details regarding the 'Revti B' tower, its impact on common areas, and the actual delay in possession relative to the Builder Buyer Agreement.

INTERIM_ORDEROrder ID: 0901126028532021-25-10-2021

The Tribunal ruled that the appeal was filed within the prescribed 60-day limitation period under Section 44(2) of the Act and ordered it to be registered as a Regular Appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paarth infra build pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →