Appellant / Complainant
Devidayal Aluminium Industries Private Limited
Respondent
Dheeraj Arora, Parsvnath Buildwell Private Limited, Uttar Pradesh Real Estate Regulatory Authority
parsvnath buildwell private limited
₹50,29,276
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126028372025 by Devidayal Aluminium Industries Private Limited against Dheeraj Arora, Parsvnath Buildwell Private Limited, Uttar Pradesh Real Estate Regulatory Authority before up_rera.
Defect Removal
The U.P. Real Estate Appellate Tribunal dismissed the appeal, ruling that the appellant cannot challenge a consequential recovery certificate without first challenging the underlying decree that established their liability as a co-promoter.
Defect Removal
The Tribunal granted Respondent Nos. 2 and 3 a final 10-day extension to file objections, noting that the matter will proceed ex-parte against them if they fail to do so, and extended existing interim relief until the next hearing.
Defect Removal
The Tribunal granted the appellant 10 days to file a rejoinder and extended the existing interim order until the next hearing date on 19.03.2026.
Defect Removal
The Tribunal adjourned the appeal to 18.02.2026 at the respondent's request, directed the respondent to file objections, and ordered that the existing interim order shall continue until the next hearing.
Defect Removal
The Tribunal granted respondent No. 2 ten days to file objections and extended the existing interim order until the next hearing scheduled for 19.01.2026.
Defect Removal
The Tribunal noted sufficient service upon the respondents and granted ten days for filing objections, with a direction to list the matter for orders on 11.12.2025.
Defect Removal
The Tribunal issued fresh notice to the respondent due to non-service and directed the appellant to serve the notice, application for condonation of delay, and grounds of appeal via email and speed post before the next hearing on 20.11.2025.
Defect Removal
The Tribunal allowed a waiver application following proof of payment of Rs. 19,43,300/- and ordered that the recovery amount against the appellant be kept in abeyance pending the appeal.
Tribunal Order #0901126028372025-19-01-2026
The Tribunal adjourned the appeal to 18.02.2026 at the respondent's request, directed the respondent to file objections, and ordered that the existing interim order shall continue until the next hearing.
Tribunal Order #0901126028372025-15-04-2026
The U.P. Real Estate Appellate Tribunal dismissed the appeal, ruling that the appellant cannot challenge a consequential recovery certificate without first challenging the underlying decree that established their liability as a co-promoter.
Tribunal Order #0901126028372025-23-09-2025
The Tribunal allowed a waiver application following proof of payment of Rs. 19,43,300/- and ordered that the recovery amount against the appellant be kept in abeyance pending the appeal.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed the appeal, ruling that the appellant cannot challenge a consequential recovery certificate without first challenging the underlying decree that established their liability as a co-promoter. Awarded in favor of Respondent. Awarded interest rate: MCLR+1 percent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed the appeal, ruling that the appellant cannot challenge a consequential recovery certificate without first challenging the underlying decree that established their liability as a co-promoter.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1 percent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Puneet S Bisaria
- Manu Lakhotiya
Respondent Advocate(s)
- Deeptanshu Jain
Official RERA Tribunal Orders (3)
The Tribunal adjourned the appeal to 18.02.2026 at the respondent's request, directed the respondent to file objections, and ordered that the existing interim order shall continue until the next hearing.
The U.P. Real Estate Appellate Tribunal dismissed the appeal, ruling that the appellant cannot challenge a consequential recovery certificate without first challenging the underlying decree that established their liability as a co-promoter.
The Tribunal allowed a waiver application following proof of payment of Rs. 19,43,300/- and ordered that the recovery amount against the appellant be kept in abeyance pending the appeal.
Need to research all rulings for parsvnath buildwell private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.