Appellant / Complainant
Raksha Sonkar
Respondent
Paarth Infrabuild Pvt. Ltd.
paarth infrabuild pvt. ltd.
₹4,03,536
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126028072021 by Raksha Sonkar against Paarth Infrabuild Pvt. Ltd. before up_rera.
Hearing
The Appellate Tribunal dismissed the appeal, ruling that the appellant cannot claim a refund under RERA because their status as an 'allottee' ceased upon the cancellation of the unit; however, the appellant is granted liberty to challenge the legality of said cancellation.
Re-Hearing
Upon a joint request from the counsels for both parties, the Tribunal has adjourned the appeal and rescheduled the hearing for April 8, 2025.
Re-Hearing
The Tribunal has adjourned the appeal to 11.03.2025 at the joint request of the parties and directed that pleadings be completed in the interim.
For Order
The Tribunal granted a request from the appellant's counsel to reschedule the hearing of Appeal-485/2021 to 13.02.2025.
For Order
The Tribunal granted a request for adjournment made by the respondent's counsel and rescheduled the hearing of the appeal to 07.02.2025.
For Order
The Tribunal has scheduled the appeal for a hearing on January 29, 2025.
Further Hearing
The Tribunal heard arguments from both counsels regarding the appeal and has reserved the judgment for a later date.
Further Hearing
The Tribunal granted an adjournment to allow both counsels to review cited judgments and prepare further submissions. The matter is rescheduled for hearing on 26.09.2024.
Hearing
The Tribunal adjourned the matter to 12.09.2024 for further arguments upon request of the parties.
Hearing
The Tribunal has adjourned the appeal to 27.08.2024 for hearing based on a joint request from the counsels of both parties.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to his absence from the station and rescheduled the hearing for 05.07.2024.
Hearing
The Tribunal granted the appellant's counsel a one-week adjournment to conduct research and rescheduled the hearing for May 7, 2024.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel on health grounds and rescheduled the appeal for hearing/orders to 08.04.2024.
Hearing
The Tribunal granted the parties one week's time to file their objections and replies on the portal and scheduled the appeal for hearing on 05.03.2024.
Hearing
Upon a joint request from the counsels for both parties, the Tribunal has adjourned the appeal to be listed for hearing on 06.11.2023.
Hearing
The tribunal has rescheduled the hearing of Appeal-485/2021 to 25.05.2023 due to the counsel for the appellant being on sanctioned leave.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for 13.04.2023 due to a change in Bench composition.
Final Hearing
The Tribunal heard arguments regarding an appellant's request for a refund due to project delays and the respondent's contention that the appellant is not a formal allottee; however, no ruling was issued as judgment was reserved.
Final Hearing
The Tribunal granted the respondent permission to submit a written rebuttal and directed them to serve a copy of the reply to the appellant via email before the next hearing.
Final Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for 18.01.2021.
Hearing
This text represents the header/caption of an appeal filed before the U.P. Real Estate Appellate Tribunal involving Raksha Sonkar and M/S Paarth Infrabuild Pvt. Ltd., but it does not contain any substantive rulings or directives.
Hearing
The Tribunal directed the Registry to verify the respondent's vakalatnama and granted the respondent one week to comply with a previous order and email required documents to the appellant.
Hearing
The Tribunal directed the respondent to produce the allotment letter and submit an affidavit detailing the cancellation process of the appellant's unit to ensure compliance with the Act, 2016.
Hearing on Appeal
The Tribunal granted a mutual request for adjournment from both parties and rescheduled the appeal to 29.10.2021, directing the parties to exchange pleadings and file originals in the Registry.
Hearing on Appeal
The Tribunal allowed the respondent's application to recall the order dated 09.08.2021, specifically setting aside the imposition of a Rs. 10,000 cost due to counsel's health and connectivity issues.
Hearing on Appeal
The Tribunal granted the respondent three days to file hard copies of their objection and recall application, and allowed the appellant one week to file a reply. The matter is scheduled for consideration on 07.09.2021.
Hearing on Appeal
The Tribunal imposed a cost of Rs. 10,000/- on the respondent for non-compliance with previous directions and granted a final 10-day extension for filing objections to the appeal.
Hearing on Appeal
The Tribunal directed the appellant to re-send the memo of appeal via email and ordered the respondent to file objections within two weeks, establishing a timeline for subsequent replies and filings.
Tribunal Order #0901126028072021-08-04-2025
The Appellate Tribunal dismissed the appeal, ruling that the appellant cannot claim a refund under RERA because their status as an 'allottee' ceased upon the cancellation of the unit; however, the appellant is granted liberty to challenge the legality of said cancellation.
Tribunal Order #0901126028072021-09-08-2021
The Tribunal imposed a cost of Rs. 10,000/- on the respondent for non-compliance with previous directions and granted a final 10-day extension for filing objections to the appeal.
Tribunal Order #0901126028072021-29-10-2021
The Tribunal directed the respondent to produce the allotment letter and submit an affidavit detailing the cancellation process of the appellant's unit to ensure compliance with the Act, 2016.
Tribunal Order #0901126028072021-07-09-2021
The Tribunal allowed the respondent's application to recall the order dated 09.08.2021, specifically setting aside the imposition of a Rs. 10,000 cost due to counsel's health and connectivity issues.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal dismissed the appeal, ruling that the appellant cannot claim a refund under RERA because their status as an 'allottee' ceased upon the cancellation of the unit; however, the appellant is granted liberty to challenge the legality of said cancellation. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal dismissed the appeal, ruling that the appellant cannot claim a refund under RERA because their status as an 'allottee' ceased upon the cancellation of the unit; however, the appellant is granted liberty to challenge the legality of said cancellation.
Ruling Awarded To
Respondent
Interest Period
from the date of payment till the date of recovery of complete amount
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Mandeep Singh
Respondent Advocate(s)
- Saurabh Misra
- Krishna Kumar Singh
Official RERA Tribunal Orders (4)
The Appellate Tribunal dismissed the appeal, ruling that the appellant cannot claim a refund under RERA because their status as an 'allottee' ceased upon the cancellation of the unit; however, the appellant is granted liberty to challenge the legality of said cancellation.
The Tribunal imposed a cost of Rs. 10,000/- on the respondent for non-compliance with previous directions and granted a final 10-day extension for filing objections to the appeal.
The Tribunal directed the respondent to produce the allotment letter and submit an affidavit detailing the cancellation process of the appellant's unit to ensure compliance with the Act, 2016.
The Tribunal allowed the respondent's application to recall the order dated 09.08.2021, specifically setting aside the imposition of a Rs. 10,000 cost due to counsel's health and connectivity issues.
Need to research all rulings for paarth infrabuild pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.