Appellant / Complainant
Raksha Sonkar
Respondent
Mentor Infrastructure Pvt Ltd
mentor infrastructure pvt ltd
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126028032021 by Raksha Sonkar against Mentor Infrastructure Pvt Ltd before up_rera.
For Order
The appeal was dismissed as withdrawn following a submission by the appellant's counsel that the matter has been settled between the parties.
Hearing
The Tribunal has adjourned the matter to 28.11.2024 following a joint request from counsel indicating a possibility of an out-of-court settlement.
Hearing
The Tribunal granted the respondent's counsel additional time to prepare arguments and scheduled the case for orders on 23.10.2024.
Hearing
The Tribunal granted an adjournment to allow both counsels to review cited judgments and scheduled the matter for further arguments on 26.09.2024.
Hearing
The Tribunal noted that pleadings have been exchanged and, upon joint request from counsel, adjourned the matter for final hearing on 12.09.2024.
Hearing
Upon the joint request of the counsels for both parties, the appeal has been adjourned and listed for hearing on 27.08.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to his absence and scheduled the appeal for hearing on 05.07.2024.
Hearing
The Tribunal granted the appellant's counsel a one-week adjournment to conduct further research and rescheduled the hearing for May 7, 2024.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel on health grounds and rescheduled the appeal for hearing/orders on 08.04.2024.
Hearing
The Tribunal granted the parties one week's time to file their objections and replies on the portal and scheduled the appeal for hearing on 05.03.2024.
Hearing
Upon the joint request of the counsels for both parties, the Tribunal has adjourned the appeal and scheduled it for a hearing on 06.11.2023.
Hearing
The Tribunal adjourned the appeal to 25.05.2023 because the counsel for the appellant was on sanctioned leave.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for 13.04.2023 due to a change in Bench composition.
Final Hearing
The Tribunal heard arguments regarding an appellant's claim for a refund of deposited amounts due to project delays versus the respondent's contention that the appellant is not a formal allottee; judgment has been reserved.
Final Hearing
The Tribunal heard arguments from both parties and directed the respondent to submit a written rebuttal via email, with a copy provided to the appellant.
Final Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for 18.01.2021.
Hearing
The court noted that the case was called for hearing and observed from the record that pleadings have already been exchanged between the parties.
Hearing
The Tribunal granted a one-week extension to the appellant's counsel to prepare his brief and rescheduled the hearing for December 3, 2021.
Hearing
The Tribunal granted the appellant's counsel one week to prepare his brief and scheduled the appeal for hearing on 15.11.2021.
Hearing on Appeal
The Tribunal granted a mutual request for adjournment from both parties and rescheduled the appeal for hearing on 29.10.2021, directing parties to exchange pleadings and file originals in the Registry.
Hearing on Appeal
The Tribunal allowed the respondent's application to recall the order dated 09.08.2021, specifically setting aside the imposition of a Rs. 10,000 cost imposed due to counsel's absence.
Hearing on Appeal
The Tribunal granted the respondent three days to file hard copies of their objection and recall application, and allowed the appellant one week to file a reply. The matter is scheduled for consideration on 07.09.2021.
Hearing on Appeal
The Tribunal imposed a cost of Rs. 10,000/- on the respondent for non-compliance with previous directions and granted a final 10-day extension for filing objections to the appeal.
Hearing on Appeal
The Tribunal directed the appellant to re-send the memo of appeal via email and ordered the respondent to file objections within two weeks, establishing a timeline for subsequent replies and filings.
Tribunal Order #0901126028032021-26-04-2022
The Tribunal heard arguments regarding an appellant's claim for a refund of deposited amounts due to project delays versus the respondent's contention that the appellant is not a formal allottee; judgment has been reserved.
Tribunal Order #0901126028032021-09-08-2021
The Tribunal imposed a cost of Rs. 10,000/- on the respondent for non-compliance with previous directions and granted a final 10-day extension for filing objections to the appeal.
Tribunal Order #0901126028032021-07-09-2021
The Tribunal allowed the respondent's application to recall the order dated 09.08.2021, specifically setting aside the imposition of a Rs. 10,000 cost imposed due to counsel's absence.
Tribunal Disposal & Final Award Ruling
Dismissed as withdrawn Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed as withdrawn
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Mandeep Singh
Respondent Advocate(s)
- Saurabh Misra
- Krishna Kumar Singh
Official RERA Tribunal Orders (3)
The Tribunal heard arguments regarding an appellant's claim for a refund of deposited amounts due to project delays versus the respondent's contention that the appellant is not a formal allottee; judgment has been reserved.
The Tribunal imposed a cost of Rs. 10,000/- on the respondent for non-compliance with previous directions and granted a final 10-day extension for filing objections to the appeal.
The Tribunal allowed the respondent's application to recall the order dated 09.08.2021, specifically setting aside the imposition of a Rs. 10,000 cost imposed due to counsel's absence.
Need to research all rulings for mentor infrastructure pvt ltd?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.