up_reraStatus: Completed
CASE ID: 0901126027622021

Appellant / Complainant

Air Force Naval Housing Board

VS

Respondent

Sunil Rawat

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

23 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126027622021 by Air Force Naval Housing Board against Sunil Rawat before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestNon-Compliance & Execution
2
Stage 107/05/2024

for delivery of Judgment/Order

The Tribunal dismissed 48 appeals filed by the Air Force Naval Housing Board, upholding the RERA Greater Noida orders for interest payments to allottees, and directed that pre-deposited funds be transferred to U.P. RERA for distribution during execution proceedings.

3
Stage 215/02/2024

Hearing

This is a procedural order referring the parties to a previous order passed in Appeal No. D 21/2023.

4
Stage 313/02/2024

For Order

The order refers the parties to a previous order passed in Appeal No. D 866/2021 for directions.

5
Stage 412/02/2024

For Order

The Tribunal has ordered the matter to be listed for hearing tomorrow, February 13, 2024.

6
Stage 510/10/2023

For Order

No text available.

7
Stage 630/08/2023

For Order

No text available.

8
Stage 712/07/2023

For Order

No text available.

9
Stage 802/05/2023

Delay condonation

The Tribunal granted adjournment requests from both the appellant and respondent counsel and rescheduled the appeal for hearing on 12.07.2023.

10
Stage 921/03/2023

Delay condonation

No text available.

11
Stage 1010/02/2023

Delay condonation

No text available.

12
Stage 1106/01/2023

Delay condonation

No text available.

13
Stage 1214/12/2022

Delay condonation

The Tribunal allowed the appellant's application to amend the prayer clause, limiting the challenge specifically to the Regulatory Authority's direction regarding the grant of interest for delayed possession.

14
Stage 1318/11/2022

Hearing

The Tribunal granted the appellant two weeks to file a reply to the respondent's objections and scheduled the matter for 14.12.2022 to consider the application for condonation of delay.

15
Stage 1413/10/2022

Hearing

No text available.

16
Stage 1513/09/2022

Hearing

The Tribunal granted the respondent 10 days to file objections to the condonation of delay application and grounds of appeal, with a subsequent timeline for the appellant's reply and a hearing scheduled for 13.10.2022.

17
Stage 1629/08/2022

Hearing

No text available.

18
Stage 1705/01/2022

Defect Removal

The appeal was dismissed due to the appellant's failure to comply with the mandatory provisions of Section 43(5) of the Act, with liberty granted to the appellant to apply for a refund of the deposited amount.

19
Stage 1801/12/2021

Defect Removal

The Tribunal granted the applicant a final opportunity to comply with Section 43(5) of the Act, 2016, and adjourned the matter to 05.01.2022.

20
Stage 19Final Ruling Order

Tribunal Order #0901126027622021-07-05-2024

The Tribunal dismissed 48 appeals filed by the Air Force Naval Housing Board, upholding the RERA Greater Noida orders for interest payments to allottees, and directed that pre-deposited funds be transferred to U.P. RERA for distribution during execution proceedings.

21
Stage 20Interim Order

Tribunal Order #0901126027622021-14-12-2022

The Tribunal allowed the appellant's application to amend the prayer clause, limiting the challenge specifically to the Regulatory Authority's direction regarding the grant of interest for delayed possession.

22
Stage 21Interim Order

Tribunal Order #0901126027622021-05-01-2022

The appeal was dismissed due to the appellant's failure to comply with the mandatory provisions of Section 43(5) of the Act, with liberty granted to the appellant to apply for a refund of the deposited amount.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed 48 appeals filed by the Air Force Naval Housing Board, upholding the RERA Greater Noida orders for interest payments to allottees, and directed that pre-deposited funds be transferred to U.P. RERA for distribution during execution proceedings. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.

Disposal Winner: RespondentInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed 48 appeals filed by the Air Force Naval Housing Board, upholding the RERA Greater Noida orders for interest payments to allottees, and directed that pre-deposited funds be transferred to U.P. RERA for distribution during execution proceedings.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1%

Interest Period

from 01.07.2012 till offer of possession or obtaining of OC whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Harsh Vardhan

Respondent Advocate(s)

  • Ramakant
  • Pushpendra Kumar

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126027622021-07-05-2024

The Tribunal dismissed 48 appeals filed by the Air Force Naval Housing Board, upholding the RERA Greater Noida orders for interest payments to allottees, and directed that pre-deposited funds be transferred to U.P. RERA for distribution during execution proceedings.

INTERIM_ORDEROrder ID: 0901126027622021-14-12-2022

The Tribunal allowed the appellant's application to amend the prayer clause, limiting the challenge specifically to the Regulatory Authority's direction regarding the grant of interest for delayed possession.

INTERIM_ORDEROrder ID: 0901126027622021-05-01-2022

The appeal was dismissed due to the appellant's failure to comply with the mandatory provisions of Section 43(5) of the Act, with liberty granted to the appellant to apply for a refund of the deposited amount.