up_reraStatus: Completed
CASE ID: 0901126027352021

Appellant / Complainant

Satya Prakash Soni

VS

Respondent

Chinmay Construction, U.P. Real Estate Regulatory Authority Lucknow, Abhisht Developers Builders (P) Limited

Developer Firm

abhisht developers builders (p) limited

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126027352021 by Satya Prakash Soni against Chinmay Construction, U.P. Real Estate Regulatory Authority Lucknow, Abhisht Developers Builders (P) Limited before up_rera.

2
Stage 107/07/2022

Hearing

The appellant withdrew the appeal following a settlement between the parties, leading to the disposal of the case and the consignment of records to the record room.

3
Stage 201/07/2022

Hearing

The Tribunal granted a short adjournment following a submission by the respondent's counsel that the matter has been settled between the parties.

4
Stage 326/04/2022

Hearing

The Tribunal allowed an adjournment application filed by the respondent's counsel and rescheduled the appeal for hearing on 01.07.2022.

5
Stage 419/04/2022

Further Order

The Tribunal granted the appellant three days to file a reply to the respondent's objections, subject to a cost of Rs. 500/- to be used for the Legal Representatives' Library.

6
Stage 502/03/2022

Further Order

The Tribunal directed the appellant to file a replication/rejoinder against the respondent's written statement and scheduled the next hearing for April 19, 2022.

7
Stage 619/01/2022

Further Order

No text available.

8
Stage 717/12/2021

Further Order

The Tribunal granted the respondent a final opportunity to file a reply to the grounds of appeal and scheduled the matter for further orders on 19.01.2022.

9
Stage 817/11/2021

Delay condonation

The Tribunal condoned a 79-day delay in filing the appeal, citing the COVID-19 pandemic and Supreme Court guidelines, and directed the Registry to register the appeal and the respondent to file a reply.

10
Stage 925/10/2021

Delay condonation

The Tribunal granted the respondent a final opportunity to file their Vakalat Nama and reply to the limitation application within one week, scheduling the next hearing for 17.11.2021.

11
Stage 1020/09/2021

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel due to personal difficulties and directed the parties to exchange objections and replies regarding the application for condonation of delay via email.

12
Stage 1124/08/2021

Delay condonation

The Tribunal granted the respondent an additional 10 days to file objections regarding the condonation of delay and grounds of appeal, with a subsequent deadline for the appellant's reply.

13
Stage 1223/08/2021

Delay condonation

No text available.

14
Stage 1303/08/2021

Delay condonation

The Tribunal granted the respondent one week to file objections to the application for condonation of delay and grounds of appeal, with a subsequent deadline for the applicant's reply.

15
Stage 1402/07/2021

Delay condonation

The Tribunal issued notice on the application for condonation of delay and directed the parties to exchange documents via email and upload objections/replies to the e-portal before the next hearing on 03.08.2021.

16
Stage 15Interim Order

Tribunal Order #0901126027352021-17-11-2021

The Tribunal condoned a 79-day delay in filing the appeal, citing the COVID-19 pandemic and Supreme Court guidelines, and directed the Registry to register the appeal and the respondent to file a reply.

17
Stage 16Interim Order

Tribunal Order #0901126027352021-19-04-2022

The Tribunal granted the appellant three days to file a reply to the respondent's objections, subject to a cost of Rs. 500/- to be used for the Legal Representatives' Library.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Disposed of Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Disposed of

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saurabh Misra
  • Krishna Kumar Singh
  • Gautam Johri

Respondent Advocate(s)

  • Swetank Sharma

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126027352021-17-11-2021

The Tribunal condoned a 79-day delay in filing the appeal, citing the COVID-19 pandemic and Supreme Court guidelines, and directed the Registry to register the appeal and the respondent to file a reply.

INTERIM_ORDEROrder ID: 0901126027352021-19-04-2022

The Tribunal granted the appellant three days to file a reply to the respondent's objections, subject to a cost of Rs. 500/- to be used for the Legal Representatives' Library.

TathyaGrid RERA Intelligence AI

Need to research all rulings for abhisht developers builders (p) limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →