up_reraStatus: Completed
CASE ID: 0901126027252022

Appellant / Complainant

Ambuj Shukla

VS

Respondent

Jindal Promoters Pvt Ltd

Developer Firm

jindal promoters pvt ltd

Disputed Amount

51,33,312

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional Misrepresentation

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

22 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126027252022 by Ambuj Shukla against Jindal Promoters Pvt Ltd before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional Misrepresentation
2
Stage 107/05/2024

for delivery of Judgment/Order

The Appellate Tribunal dismissed the appeal filed by Ambuj Shukla against the U.P. Real Estate Regulatory Authority's order, ruling that there was no delay in possession as the offer was made within the timeframe specified in the Builder Buyer Agreement.

3
Stage 225/01/2024

Hearing

The appellant is challenging the Regulatory Authority's rejection of their claim for a refund due to delayed possession; however, the court has reserved its judgment following arguments from both parties.

4
Stage 327/10/2023

Hearing

No text available.

5
Stage 415/09/2023

Hearing

The Tribunal noted the absence of the respondent's counsel and ordered the appeal to be listed for hearing/orders on 27.10.2023.

6
Stage 527/07/2023

Hearing

No text available.

7
Stage 619/05/2023

Hearing

The Tribunal granted a one-week extension to both parties to upload scanned copies of the Builder Buyer Agreement (BBA) and scheduled the next hearing for 27.07.2023, noting that no further adjournments will be permitted.

8
Stage 707/04/2023

Hearing

No text available.

9
Stage 823/02/2023

Delay condonation

The Tribunal granted the appellant's request to bring a scanned copy of the original Builder Buyer Agreement (BBA) on record and scheduled the appeal for a hearing on 07.04.2023.

10
Stage 923/01/2023

Delay condonation

No text available.

11
Stage 1015/12/2022

Delay condonation

The Tribunal allowed the application for condonation of delay, excusing a 40-day delay in filing the appeal based on the Supreme Court's extension of limitation periods, and directed the Registry to convert the defective appeal into a Regular Appeal.

12
Stage 1121/11/2022

Delay condonation

No text available.

13
Stage 1214/10/2022

Delay condonation

No text available.

14
Stage 1315/09/2022

Delay condonation

No text available.

15
Stage 1430/08/2022

Delay condonation

The Tribunal noted that pleadings have been exchanged and ordered the case to be listed for a subsequent hearing on 15.09.2022.

16
Stage 1508/08/2022

Delay condonation

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objection and scheduled the matter for hearing on 30.08.2022 regarding the application for condonation of delay.

17
Stage 1618/07/2022

Delay condonation

The Tribunal directed the respondent's counsel to register on the e-portal and scheduled the matter for August 8, 2022, to consider an application for condonation of delay.

18
Stage 1725/05/2022

Delay condonation

The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and directed specific procedural steps for service of notice and filing of objections.

19
Stage 18Interim Order

Tribunal Order #0901126027252022-15-12-2022

The Tribunal allowed the application for condonation of delay, excusing a 40-day delay in filing the appeal based on the Supreme Court's extension of limitation periods, and directed the Registry to convert the defective appeal into a Regular Appeal.

20
Stage 19Final Ruling Order

Tribunal Order #0901126027252022-07-05-2024

The Appellate Tribunal dismissed the appeal filed by Ambuj Shukla against the U.P. Real Estate Regulatory Authority's order, ruling that there was no delay in possession as the offer was made within the timeframe specified in the Builder Buyer Agreement.

21
Stage 20Interim Order

Tribunal Order #0901126027252022-25-01-2024

The appellant is challenging the Regulatory Authority's rejection of their claim for a refund due to delayed possession; however, the court has reserved its judgment following arguments from both parties.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeal filed by Ambuj Shukla against the U.P. Real Estate Regulatory Authority's order, ruling that there was no delay in possession as the offer was made within the timeframe specified in the Builder Buyer Agreement. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeal filed by Ambuj Shukla against the U.P. Real Estate Regulatory Authority's order, ruling that there was no delay in possession as the offer was made within the timeframe specified in the Builder Buyer Agreement.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 12

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Tushar Bahadur
  • Sachin Gupta

Respondent Advocate(s)

  • Mahendra Singh Sharma

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126027252022-15-12-2022

The Tribunal allowed the application for condonation of delay, excusing a 40-day delay in filing the appeal based on the Supreme Court's extension of limitation periods, and directed the Registry to convert the defective appeal into a Regular Appeal.

FINAL_ORDEROrder ID: 0901126027252022-07-05-2024

The Appellate Tribunal dismissed the appeal filed by Ambuj Shukla against the U.P. Real Estate Regulatory Authority's order, ruling that there was no delay in possession as the offer was made within the timeframe specified in the Builder Buyer Agreement.

INTERIM_ORDEROrder ID: 0901126027252022-25-01-2024

The appellant is challenging the Regulatory Authority's rejection of their claim for a refund due to delayed possession; however, the court has reserved its judgment following arguments from both parties.