Appellant / Complainant
Gorakhpur Development Authority
Respondent
Ranjana
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126027242022 by Gorakhpur Development Authority against Ranjana before up_rera.
For Order
The Tribunal allowed an application to correct several typographical errors regarding specific dates within the judgment and order dated 25.11.2024.
Further Hearing
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the completion date initially declared to RERA (30.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).
Further Hearing
The case was adjourned at the request of the appellant's counsel due to illness, with the matter scheduled for orders on 25.11.2024.
For Order
The Tribunal has scheduled the appeal for further hearing on 16.10.2024.
For Order
The Tribunal granted an adjournment requested by the respondent's counsel due to a bereavement in her family and rescheduled the hearing for 04.10.2024.
For Order
Upon the joint request of the counsels for both parties, the Tribunal has adjourned the appeal to be listed for orders or hearing on 02.08.2024.
For Order
The Tribunal directs the parties to refer to the order passed in Appeal No. 285/2022 for the substantive directions regarding this appeal.
For Order
The Tribunal has scheduled the appeal for a hearing on 09.05.2024.
For Order
Upon the joint request of the counsel for both parties, the tribunal has ordered the appeal to be listed along with similar appeals on 08.04.2024.
For Order
The Tribunal has noted the appellant's counsel is on sanctioned leave and has scheduled the defective appeal for orders on 18.03.2024.
For Order
The Tribunal has scheduled the appeal for a subsequent hearing on 29.02.2024.
For Order
The Tribunal refers the parties to a previous order passed on a different appeal number (D 285/2022) for instructions regarding this matter.
For Order
The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the hearing for 13.10.2023.
Delay condonation
The Tribunal refers the parties to a previously passed order dated 31.03.2023 in a related appeal (Appeal No. (D) 285/2022) for the current order.
Delay condonation
This is a procedural order directing the parties to refer to a previously passed order regarding Appeal No. (D) 285/2022.
Delay condonation
The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and scheduled the next hearing for December 13, 2022.
Delay condonation
The Tribunal condoned the delay in filing the appeal by Gorakhpur Development Authority, citing Supreme Court precedents regarding limitation extensions, and directed the Registry to convert the defective appeal into a regular one.
For Order
The Tribunal recorded the submission regarding the filing of objections by the respondent and directed the appellant to file a reply within one week and upload it to the e-portal, listing the matter for hearing on 21.10.2022.
Defect Removal
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with the case scheduled for hearing on 19.09.2022.
Defect Removal
The Tribunal granted the respondent 15 days to file objections to the application for condonation of delay and the grounds of appeal, with the case scheduled for hearing on 21.07.2022.
Tribunal Order #0901126027242022-25-11-2024
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the completion date initially declared to RERA (30.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).
Tribunal Order #0901126027242022-21-10-2022
The Tribunal condoned the delay in filing the appeal by Gorakhpur Development Authority, citing Supreme Court precedents regarding limitation extensions, and directed the Registry to convert the defective appeal into a regular one.
Tribunal Disposal & Final Award Ruling
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the completion date initially declared to RERA (30.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021). Awarded in favor of Partial.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the completion date initially declared to RERA (30.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).
Ruling Awarded To
Partial
Interest Period
from 13.04.2017 till handing over possession, excluding the period of injunction granted by the NGT from 17.12.2018 to 12.01.2021
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rakesh Bajpai
Respondent Advocate(s)
- Abhishek Khare
- Aahuti Agarwal
Official RERA Tribunal Orders (2)
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the completion date initially declared to RERA (30.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).
The Tribunal condoned the delay in filing the appeal by Gorakhpur Development Authority, citing Supreme Court precedents regarding limitation extensions, and directed the Registry to convert the defective appeal into a regular one.