up_reraStatus: Active
CASE ID: 0901126027222022

Appellant / Complainant

Gorakhpur Development Authority

VS

Respondent

Prem Lata Tripathi

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

31 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126027222022 by Gorakhpur Development Authority against Prem Lata Tripathi before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 121/02/2025

For Order

The Tribunal allowed an application to correct several typographical errors regarding specific dates within the judgment and order dated 25.11.2024.

3
Stage 225/11/2024

Further Hearing

The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the completion date declared during RERA registration (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).

4
Stage 316/10/2024

Further Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to the illness of the lead counsel and scheduled the case for orders on 25.11.2024.

5
Stage 404/10/2024

For Order

The Tribunal condoned a 140-day delay in filing the appeal by the Gorakhpur Development Authority and directed the registry to convert the defective appeal into a regular appeal, scheduling the merit hearing for October 16, 2024.

6
Stage 504/09/2024

For Order

The Tribunal granted an adjournment requested by the respondent's counsel due to a bereavement in her family and rescheduled the hearing for 04.10.2024.

7
Stage 602/08/2024

For Order

No text available.

8
Stage 708/07/2024

For Order

Upon the joint request of both parties' counsel, the tribunal has adjourned the appeal and scheduled it for orders/hearing on 02.08.2024.

9
Stage 809/05/2024

For Order

The Tribunal refers the parties to a previous order passed in Appeal No. 285/2022 for further directions.

10
Stage 908/04/2024

For Order

The Tribunal has scheduled the appeal for a hearing on 09.05.2024 and referred to a previous order passed in Appeal No. 293 of 2022.

11
Stage 1018/03/2024

For Order

Upon the joint request of the counsel for both parties, the appeal has been adjourned and scheduled to be listed along with similar appeals on 08.04.2024.

12
Stage 1129/02/2024

For Order

The Tribunal noted the absence of the appellant's counsel due to sanctioned leave and ordered the defective appeal to be listed for orders on 18.03.2024.

13
Stage 1224/01/2024

For Order

The Tribunal has directed that the appeal be listed for a further hearing on 29.02.2024.

14
Stage 1317/01/2024

For Order

The order refers the parties to a previous order passed in Appeal No. D 285/2022 for directions.

15
Stage 1413/10/2023

For Order

No text available.

16
Stage 1505/09/2023

For Order

The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the hearing for 13.10.2023.

17
Stage 1624/07/2023

For Order

No text available.

18
Stage 1711/05/2023

For Order

No text available.

19
Stage 1831/03/2023

Delay condonation

The Tribunal refers the matter to a previous order passed in Appeal No. (D) 285/2022 regarding Gorakhpur Development Authority Vs. Jagdhatri Mishra.

20
Stage 1920/02/2023

Delay condonation

This is a procedural order referring the matter to a previously passed order dated Appeal No. (D) 285/2022.

21
Stage 2018/01/2023

Delay condonation

No text available.

22
Stage 2113/12/2022

Delay condonation

No text available.

23
Stage 2217/11/2022

Delay condonation

The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and directed that a soft copy be emailed to the respondent and uploaded to the e-portal.

24
Stage 2321/10/2022

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with a subsequent reply period for the applicant, and scheduled the matter for hearing on 17.11.2022.

25
Stage 2419/09/2022

Delay condonation

The Tribunal granted the respondent 10 days to file objections regarding the condonation of delay and grounds of appeal, while noting that the respondent's husband does not qualify as a legal representative under Section 56 of the Act.

26
Stage 2522/08/2022

Delay condonation

The Tribunal granted the appellant's request to issue fresh notice to the respondent regarding an application for condonation of delay and scheduled the matter for hearing on 19.09.2022.

27
Stage 2621/07/2022

Notice

The Tribunal issued notice to the respondent regarding the application for condonation of delay and directed the applicant to serve the notice and appeal documents via speed-post and email.

28
Stage 2727/05/2022

Defect Removal

The Tribunal granted the respondent 15 days to file objections to the application for condonation of delay and the grounds of appeal, with the matter scheduled for hearing on 21.07.2022.

29
Stage 28Final Ruling Order

Tribunal Order #0901126027222022-25-11-2024

The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the completion date declared during RERA registration (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).

30
Stage 29Interim Order

Tribunal Order #0901126027222022-04-10-2024

The Tribunal condoned a 140-day delay in filing the appeal by the Gorakhpur Development Authority and directed the registry to convert the defective appeal into a regular appeal, scheduling the merit hearing for October 16, 2024.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the completion date declared during RERA registration (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021). Awarded in favor of Partial.

Disposal Winner: PartialStatus: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the completion date declared during RERA registration (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).

Ruling Awarded To

Partial

Interest Period

from 13.04.2017 till handing over possession, excluding the period of injunction granted by the NGT from 17.12.2018 to 12.01.2021

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rakesh Bajpai

Respondent Advocate(s)

  • Abhishek Khare

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126027222022-25-11-2024

The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the completion date declared during RERA registration (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).

INTERIM_ORDEROrder ID: 0901126027222022-04-10-2024

The Tribunal condoned a 140-day delay in filing the appeal by the Gorakhpur Development Authority and directed the registry to convert the defective appeal into a regular appeal, scheduling the merit hearing for October 16, 2024.

TathyaGrid RERA Intelligence AI