up_reraStatus: Active
CASE ID: 0901126027162022

Appellant / Complainant

Gorakhpur Development Authority

VS

Respondent

Ramvijay Tripathi

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

31 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126027162022 by Gorakhpur Development Authority against Ramvijay Tripathi before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 121/02/2025

For Order

The Tribunal allowed an application to correct typographical errors regarding specific dates within the judgment and order dated 25.11.2024.

3
Stage 225/11/2024

Further Hearing

The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event.

4
Stage 316/10/2024

Further Hearing

The court granted an adjournment requested by the appellant's counsel due to illness and scheduled the case for orders on 25.11.2024.

5
Stage 404/10/2024

For Order

The Tribunal heard partial arguments from counsel for both parties and adjourned the appeal for further hearing on 16.10.2024.

6
Stage 504/09/2024

For Order

The Tribunal granted an adjournment requested by the respondent's counsel due to a bereavement in her family and rescheduled the hearing for 04.10.2024.

7
Stage 602/08/2024

For Order

No text available.

8
Stage 708/07/2024

For Order

Upon the joint request of both counsels, the tribunal has adjourned the appeal for orders or hearing to 02.08.2024.

9
Stage 809/05/2024

For Order

The Tribunal refers the parties to a previous order passed in Appeal No. 285/2022 for further directions.

10
Stage 908/04/2024

For Order

The Tribunal has scheduled the appeal for a hearing on May 9, 2024, referring to a previous order passed in a related matter.

11
Stage 1018/03/2024

For Order

The court has adjourned the appeal to 08.04.2024 following a joint request from the counsel for both parties to list it alongside similar appeals.

12
Stage 1129/02/2024

For Order

The court noted the absence of the appellant's counsel due to sanctioned leave and adjourned the defective appeal for orders to 18.03.2024.

13
Stage 1224/01/2024

For Order

The Tribunal has scheduled the appeal for a subsequent hearing on February 29, 2024.

14
Stage 1317/01/2024

For Order

The order is a procedural reference directing the parties to refer to a previous order passed in Appeal No. D 285/2022.

15
Stage 1413/10/2023

For Order

No text available.

16
Stage 1505/09/2023

For Order

The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the hearing for 13.10.2023.

17
Stage 1624/07/2023

For Order

No text available.

18
Stage 1711/05/2023

For Order

No text available.

19
Stage 1831/03/2023

For Order

The Tribunal refers the matter to a previously passed order dated 31.03.2023 regarding Appeal No. (D) 285/2022 (Gorakhpur Development Authority Vs. Jagdhatri Mishra).

20
Stage 1920/02/2023

For Order

The Tribunal refers the parties to a previously passed order dated on Appeal No. (D) 285/2022.

21
Stage 2018/01/2023

For Order

No text available.

22
Stage 2113/12/2022

For Order

No text available.

23
Stage 2217/11/2022

For Order

The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and directed that a soft copy be emailed to the respondent and uploaded to the e-portal.

24
Stage 2321/10/2022

Delay condonation

The Tribunal condoned the delay in filing the appeal by the Gorakhpur Development Authority, citing Supreme Court precedents regarding limitation extensions, and directed the Registry to convert the defective appeal into a regular appeal.

25
Stage 2419/09/2022

For Order

The Tribunal directed the respondent to serve objections via email and instructed the appellant to file a reply on the e-portal before the next hearing scheduled for 21.10.2022.

26
Stage 2522/08/2022

Defect Removal

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for September 19, 2022.

27
Stage 2621/07/2022

Defect Removal

No text available.

28
Stage 2727/05/2022

Defect Removal

The Tribunal granted the respondent 15 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for July 21, 2022.

29
Stage 28Final Ruling Order

Tribunal Order #0901126027162022-25-11-2024

The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event.

30
Stage 29Interim Order

Tribunal Order #0901126027162022-21-10-2022

The Tribunal condoned the delay in filing the appeal by the Gorakhpur Development Authority, citing Supreme Court precedents regarding limitation extensions, and directed the Registry to convert the defective appeal into a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event. Awarded in favor of Partial.

Disposal Winner: PartialStatus: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event.

Ruling Awarded To

Partial

Interest Period

from 13.04.2017 till handing over possession, excluding the period of injunction granted by the NGT from 17.12.2018 to 12.01.2021

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rakesh Bajpai

Respondent Advocate(s)

  • Abhishek Khare

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126027162022-25-11-2024

The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event.

INTERIM_ORDEROrder ID: 0901126027162022-21-10-2022

The Tribunal condoned the delay in filing the appeal by the Gorakhpur Development Authority, citing Supreme Court precedents regarding limitation extensions, and directed the Registry to convert the defective appeal into a regular appeal.