Appellant / Complainant
Gorakhpur Development Authority
Respondent
Ghurahu Prasad
gorakhpur development authority
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126027152022 by Gorakhpur Development Authority against Ghurahu Prasad before up_rera.
For Order
The Tribunal allowed an application to correct typographical errors regarding specific dates within the judgment and order dated 25.11.2024.
Further Hearing
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event.
Further Hearing
The court granted an adjournment requested by the appellant's counsel due to illness and scheduled the case for orders on 25.11.2024.
For Order
The Tribunal heard partial arguments from counsel for both parties and adjourned the appeal for further hearing on 16.10.2024.
For Order
The Tribunal granted an adjournment requested by the respondent's counsel due to a bereavement in her family and rescheduled the hearing for 04.10.2024.
For Order
Upon the joint request of the counsels for both parties, the tribunal has adjourned the appeal and scheduled it for orders/hearing on 02.08.2024.
For Order
The Tribunal refers the parties to a previous order passed in Appeal No. 285/2022 for directions regarding this matter.
For Order
The Tribunal has scheduled the appeal for a hearing on 09.05.2024, referring to a previous order passed in Appeal No. 293 of 2022.
For Order
The Tribunal has adjourned the appeal to 08.04.2024 for a joint hearing alongside other similar appeals, following a request from the counsel for both parties.
For Order
The Tribunal noted the absence of the appellant's counsel due to sanctioned leave and ordered the defective appeal to be listed for orders on 18.03.2024.
For Order
The Tribunal has scheduled the appeal for a subsequent hearing on 29.02.2024.
For Order
The order refers the parties to a previous order passed in Appeal No. D 285/2022 for directions.
For Order
The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the hearing for 13.10.2023.
For Order
The Tribunal directs the parties to refer to the order passed in Appeal No. (D) 285/2022 (Gorakhpur Development Authority Vs. Jagdhatri Mishra) for the ruling.
For Order
This is a procedural order referring the matter to a previously passed order dated for Appeal No. (D) 285/2022.
For Order
The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections due to health reasons and scheduled the next hearing for December 13, 2022.
Delay condonation
The Tribunal condoned the delay in filing the appeal by the Gorakhpur Development Authority, citing Supreme Court precedents regarding limitation extensions, and granted the appellant 10 days to file a reply to the respondent's objections.
For Order
The Tribunal directed the respondent to provide soft copies of their objections via email and ordered the applicant to file a reply on the e-portal before the next hearing scheduled for 21.10.2022.
Defect Removal
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for September 19, 2022.
Defect Removal
The Tribunal granted the respondent 15 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for July 21, 2022.
Tribunal Order #0901126027152022-25-11-2024
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event.
Tribunal Disposal & Final Award Ruling
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event. Awarded in favor of Partial.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event.
Ruling Awarded To
Partial
Interest Period
from 13.04.2017 till handing over possession, excluding the period of injunction granted by the NGT from 17.12.2018 to 12.01.2021
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rakesh Bajpai
Respondent Advocate(s)
- Abhishek Khare
Official RERA Tribunal Orders (1)
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event.