up_reraStatus: Completed
CASE ID: 0901126027132023

Appellant / Complainant

Mahaluxmi Infrahome Pvt Ltd

VS

Respondent

Uttar Pradesh Real Estate Regulatory Authority

Developer Firm

mahaluxmi infrahome pvt ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

33 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126027132023 by Mahaluxmi Infrahome Pvt Ltd against Uttar Pradesh Real Estate Regulatory Authority before up_rera.

2
Stage 130/01/2026

Hearing

The U.P. Real Estate Appellate Tribunal dismissed Appeal-510/2023, referring to the order passed in the related Appeal No. 508/2023.

3
Stage 220/01/2026

Delay condonation

The Tribunal condoned a 64-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal, with the next hearing scheduled for 30.01.2026.

4
Stage 308/01/2026

Delay condonation

The Tribunal granted an adjournment requested by the appellant despite a previous stop order, rescheduling the hearing for 20.01.2026 with a warning that no further adjournments will be permitted.

5
Stage 402/12/2025

Delay condonation

The Tribunal has granted a request from the appellant's counsel to list the appeal for orders on 08.01.2026.

6
Stage 525/11/2025

Delay condonation

The Tribunal granted an adjournment requested by the appellant despite a prior stop order and scheduled the appeal for hearing on 02.12.2025, noting that no further adjournments will be permitted.

7
Stage 603/11/2025

Delay condonation

The Tribunal granted the appellant's counsel time to prepare the brief and adjourned the matter to 25.11.2025.

8
Stage 708/10/2025

Delay condonation

The Tribunal has adjourned the appeal to 03.11.2025 for orders or hearing following a joint request from the counsel for both parties.

9
Stage 803/09/2025

Delay condonation

The Tribunal granted a request for time by the respondent's counsel and rescheduled the appeal for hearing on 08.10.2025.

10
Stage 912/08/2025

Delay condonation

The Tribunal has granted a request from the appellant's counsel to list the case for orders on 03.09.2025.

11
Stage 1024/07/2025

Delay condonation

The Tribunal granted an adjournment requested by the appellant and scheduled the matter for hearing on the application for condonation of delay on 12.08.2025, noting that no further adjournments will be permitted.

12
Stage 1108/07/2025

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the appeal for hearing on 24.07.2025.

13
Stage 1208/05/2025

Delay condonation

The Tribunal has adjourned the matter and scheduled it for orders on July 8, 2025, following a request from the counsel for both parties.

14
Stage 1315/04/2025

Delay condonation

Upon the joint request of both parties, the Tribunal has adjourned the appeal to be listed for orders or hearing on May 8, 2025.

15
Stage 1419/03/2025

Delay condonation

The Tribunal has scheduled the defective appeal for hearing on April 15, 2025, to consider the application for condonation of delay, noting that no further adjournments will be granted.

16
Stage 1519/02/2025

Delay condonation

The Tribunal has granted a request from the appellant's counsel to adjourn the matter and has scheduled the appeal for hearing on 19.03.2025.

17
Stage 1630/01/2025

Delay condonation

The Tribunal granted a request from the appellant's counsel to adjourn the matter and rescheduled the hearing for 19.02.2025.

18
Stage 1708/01/2025

For Order

The Tribunal heard arguments in the matter of Mahaluxmi Infrahome Pvt Ltd vs. U.P. Real Estate Regulatory Authority and scheduled the appeal for further hearing on 30.01.2025.

19
Stage 1827/08/2024

Delay condonation

The Tribunal heard arguments regarding the application for condonation of delay and reserved its judgment on the matter.

20
Stage 1929/07/2024

Delay condonation

The Tribunal granted the appellant time to prepare her brief and scheduled the appeal for consideration of the application for condonation of delay and a hearing on 27.08.2024.

21
Stage 2030/05/2024

Delay condonation

The Tribunal granted a final one-week extension to the appellant to file a reply to the respondent's objections and scheduled the matter for hearing on July 29, 2024.

22
Stage 2129/04/2024

Delay condonation

No text available.

23
Stage 2222/03/2024

Delay condonation

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the matter for hearing on April 29, 2024.

24
Stage 2321/02/2024

Delay condonation

The Tribunal refers the parties to a previous order passed in Appeal No. D 508/2023 regarding the current matter.

25
Stage 2429/01/2024

Delay condonation

The Tribunal granted the respondent three days to file objections to the application for condonation of delay and directed the matter to be listed for hearing on 21.02.2024.

26
Stage 2530/10/2023

Delay condonation

No text available.

27
Stage 2618/09/2023

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with the matter scheduled for hearing on 30.10.2023.

28
Stage 2711/09/2023

Delay condonation

The Tribunal adjourned the proceedings due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh, rescheduling the hearing for 18.09.2023.

29
Stage 2820/07/2023

Delay condonation

The Tribunal acknowledges the appellant's compliance with Section 43(5) of the Act via a Rs. 3,00,000 deposit and directs the issuance of notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 11.09.2023.

30
Stage 29Final Ruling Order

Tribunal Order #0901126027132023-30-01-2026

The U.P. Real Estate Appellate Tribunal dismissed Appeal-510/2023, referring to the order passed in the related Appeal No. 508/2023.

31
Stage 30Interim Order

Tribunal Order #0901126027132023-20-07-2023

The Tribunal acknowledges the appellant's compliance with Section 43(5) of the Act via a Rs. 3,00,000 deposit and directs the issuance of notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 11.09.2023.

32
Stage 31Interim Order

Tribunal Order #0901126027132023-20-01-2026

The Tribunal condoned a 64-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal, with the next hearing scheduled for 30.01.2026.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed Appeal-510/2023, referring to the order passed in the related Appeal No. 508/2023. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed Appeal-510/2023, referring to the order passed in the related Appeal No. 508/2023.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Harish Pandey
  • Samrat Vaish
  • Isha Asthana

Respondent Advocate(s)

  • Shobhit Mohan Shukla

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126027132023-30-01-2026

The U.P. Real Estate Appellate Tribunal dismissed Appeal-510/2023, referring to the order passed in the related Appeal No. 508/2023.

INTERIM_ORDEROrder ID: 0901126027132023-20-07-2023

The Tribunal acknowledges the appellant's compliance with Section 43(5) of the Act via a Rs. 3,00,000 deposit and directs the issuance of notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 11.09.2023.

INTERIM_ORDEROrder ID: 0901126027132023-20-01-2026

The Tribunal condoned a 64-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal, with the next hearing scheduled for 30.01.2026.

TathyaGrid RERA Intelligence AI

Need to research all rulings for mahaluxmi infrahome pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →