Appellant / Complainant
Mahaluxmi Infrahome Pvt Ltd
Respondent
Uttar Pradesh Real Estate Regulatory Authority
mahaluxmi infrahome pvt ltd
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126027132023 by Mahaluxmi Infrahome Pvt Ltd against Uttar Pradesh Real Estate Regulatory Authority before up_rera.
Hearing
The U.P. Real Estate Appellate Tribunal dismissed Appeal-510/2023, referring to the order passed in the related Appeal No. 508/2023.
Delay condonation
The Tribunal condoned a 64-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal, with the next hearing scheduled for 30.01.2026.
Delay condonation
The Tribunal granted an adjournment requested by the appellant despite a previous stop order, rescheduling the hearing for 20.01.2026 with a warning that no further adjournments will be permitted.
Delay condonation
The Tribunal has granted a request from the appellant's counsel to list the appeal for orders on 08.01.2026.
Delay condonation
The Tribunal granted an adjournment requested by the appellant despite a prior stop order and scheduled the appeal for hearing on 02.12.2025, noting that no further adjournments will be permitted.
Delay condonation
The Tribunal granted the appellant's counsel time to prepare the brief and adjourned the matter to 25.11.2025.
Delay condonation
The Tribunal has adjourned the appeal to 03.11.2025 for orders or hearing following a joint request from the counsel for both parties.
Delay condonation
The Tribunal granted a request for time by the respondent's counsel and rescheduled the appeal for hearing on 08.10.2025.
Delay condonation
The Tribunal has granted a request from the appellant's counsel to list the case for orders on 03.09.2025.
Delay condonation
The Tribunal granted an adjournment requested by the appellant and scheduled the matter for hearing on the application for condonation of delay on 12.08.2025, noting that no further adjournments will be permitted.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the appeal for hearing on 24.07.2025.
Delay condonation
The Tribunal has adjourned the matter and scheduled it for orders on July 8, 2025, following a request from the counsel for both parties.
Delay condonation
Upon the joint request of both parties, the Tribunal has adjourned the appeal to be listed for orders or hearing on May 8, 2025.
Delay condonation
The Tribunal has scheduled the defective appeal for hearing on April 15, 2025, to consider the application for condonation of delay, noting that no further adjournments will be granted.
Delay condonation
The Tribunal has granted a request from the appellant's counsel to adjourn the matter and has scheduled the appeal for hearing on 19.03.2025.
Delay condonation
The Tribunal granted a request from the appellant's counsel to adjourn the matter and rescheduled the hearing for 19.02.2025.
For Order
The Tribunal heard arguments in the matter of Mahaluxmi Infrahome Pvt Ltd vs. U.P. Real Estate Regulatory Authority and scheduled the appeal for further hearing on 30.01.2025.
Delay condonation
The Tribunal heard arguments regarding the application for condonation of delay and reserved its judgment on the matter.
Delay condonation
The Tribunal granted the appellant time to prepare her brief and scheduled the appeal for consideration of the application for condonation of delay and a hearing on 27.08.2024.
Delay condonation
The Tribunal granted a final one-week extension to the appellant to file a reply to the respondent's objections and scheduled the matter for hearing on July 29, 2024.
Delay condonation
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the matter for hearing on April 29, 2024.
Delay condonation
The Tribunal refers the parties to a previous order passed in Appeal No. D 508/2023 regarding the current matter.
Delay condonation
The Tribunal granted the respondent three days to file objections to the application for condonation of delay and directed the matter to be listed for hearing on 21.02.2024.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with the matter scheduled for hearing on 30.10.2023.
Delay condonation
The Tribunal adjourned the proceedings due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh, rescheduling the hearing for 18.09.2023.
Delay condonation
The Tribunal acknowledges the appellant's compliance with Section 43(5) of the Act via a Rs. 3,00,000 deposit and directs the issuance of notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 11.09.2023.
Tribunal Order #0901126027132023-30-01-2026
The U.P. Real Estate Appellate Tribunal dismissed Appeal-510/2023, referring to the order passed in the related Appeal No. 508/2023.
Tribunal Order #0901126027132023-20-07-2023
The Tribunal acknowledges the appellant's compliance with Section 43(5) of the Act via a Rs. 3,00,000 deposit and directs the issuance of notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 11.09.2023.
Tribunal Order #0901126027132023-20-01-2026
The Tribunal condoned a 64-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal, with the next hearing scheduled for 30.01.2026.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed Appeal-510/2023, referring to the order passed in the related Appeal No. 508/2023. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed Appeal-510/2023, referring to the order passed in the related Appeal No. 508/2023.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Harish Pandey
- Samrat Vaish
- Isha Asthana
Respondent Advocate(s)
- Shobhit Mohan Shukla
Official RERA Tribunal Orders (3)
The U.P. Real Estate Appellate Tribunal dismissed Appeal-510/2023, referring to the order passed in the related Appeal No. 508/2023.
The Tribunal acknowledges the appellant's compliance with Section 43(5) of the Act via a Rs. 3,00,000 deposit and directs the issuance of notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 11.09.2023.
The Tribunal condoned a 64-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal, with the next hearing scheduled for 30.01.2026.