Appellant / Complainant
Gorakhpur Development Authority
Respondent
Vidyawati Pandey
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126027122022 by Gorakhpur Development Authority against Vidyawati Pandey before up_rera.
For Order
The Tribunal allowed an application to correct several typographical errors regarding specific dates within the judgment and order dated 25.11.2024.
Further Hearing
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the original completion date declared to RERA (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).
Further Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and scheduled the case for orders on 25.11.2024.
For Order
The Tribunal has heard partial arguments from both parties and adjourned the appeal for further hearing on 16.10.2024.
For Order
The Tribunal granted an adjournment requested by the respondent's counsel due to a bereavement in her family and rescheduled the matter for hearing on 04.10.2024.
For Order
Upon the joint request of both counsels, the tribunal has adjourned the appeal for orders/hearing to 02.08.2024.
For Order
The Tribunal refers the parties to a previous order passed in Appeal No. 285/2022 regarding the current matter.
For Order
The Tribunal has scheduled the appeal for a hearing on 09.05.2024 and referred to a previous order passed in Appeal No. 293 of 2022.
For Order
The Tribunal directed that the matter be listed for a hearing on 08.04.2024, referring to a previous order passed in Appeal No. D285 of 2022.
For Order
The Tribunal has scheduled the defective appeal for further orders on March 18, 2024, due to the absence of the appellant's counsel on sanctioned leave.
For Order
The Tribunal directed that the appeal be listed for a hearing on 29.02.2024, referring to a previous order passed in Appeal No. D285/2022.
For Order
The Tribunal refers the parties to a previous order passed on a different appeal number (D 285/2022) for instructions regarding this matter.
For Order
The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the hearing for 13.10.2023.
Delay condonation
The Tribunal refers the matter to a previous order passed on Appeal No. (D) 285/2022 regarding Gorakhpur Development Authority Vs. Jagdhatri Mishra.
Delay condonation
This is a procedural order referring the matter to a previously passed order dated for Appeal No. (D) 285/2022.
Delay condonation
The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and directed that a soft copy be emailed to the respondent and uploaded to the e-portal.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for November 17, 2022.
For Order
The Tribunal granted the respondent one week to file objections regarding the application for condonation of delay and grounds of appeal, scheduling the next hearing for 21.10.2022.
Defect Removal
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for September 19, 2022.
Defect Removal
The Tribunal granted the respondent a 15-day extension to file objections to the application for condonation of delay and the grounds of appeal, adjourning the case to July 21, 2022.
Tribunal Order #0901126027122022-25-11-2024
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the original completion date declared to RERA (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).
Tribunal Disposal & Final Award Ruling
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the original completion date declared to RERA (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021). Awarded in favor of Partial.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the original completion date declared to RERA (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).
Ruling Awarded To
Partial
Interest Period
from 13.04.2017 till handing over possession, excluding the period of injunction granted by the NGT from 17.12.2018 to 12.01.2021
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rakesh Bajpai
Respondent Advocate(s)
- Abhishek Khare
Official RERA Tribunal Orders (1)
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the original completion date declared to RERA (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).