up_reraStatus: Completed
CASE ID: 0901126027012021

Appellant / Complainant

Joginder Kumar

VS

Respondent

Proview Infrastructure Pvt. Ltd.

Developer Firm

proview infrastructure pvt. ltd.

Disputed Amount

31,90,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

14 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126027012021 by Joginder Kumar against Proview Infrastructure Pvt. Ltd. before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 119/04/2022

Delay condonation

The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposit (after settling the outstanding HDFC bank loan) along with interest at the rate of MCLR+1% per annum.

3
Stage 210/03/2022

Further Order

The Tribunal noted the absence of both parties and adjourned the matter to 19.04.2022 for hearing.

4
Stage 305/01/2022

Further Order

The Tribunal closed the respondent's opportunity to file an objection to the memo of appeal due to their repeated failure to appear and submit objections despite being granted a final opportunity.

5
Stage 401/12/2021

Further Order

The Tribunal granted the respondent a final opportunity to file objections to the memo of appeal and adjourned the matter to 05.01.2022.

6
Stage 509/11/2021

Delay condonation

The Tribunal condoned a 150-day delay in filing the appeal by applying the Supreme Court's relaxation of limitation periods due to the Covid-19 pandemic and directed the defective appeal to be registered as a Regular Appeal.

7
Stage 620/09/2021

Delay condonation

The Tribunal noted the absence of the respondent despite service of notice and ordered that a fresh notice be issued via email to inform them of the next hearing date for the disposal of the limitation application.

8
Stage 725/08/2021

Admission

The Tribunal granted the appellant three days to take necessary steps and directed the exchange of documents via email regarding the application for condonation of delay and the memo of appeal.

9
Stage 829/07/2021

Notice

The Tribunal directed the appellant to file a hard copy of Form-L within three days and ordered the issuance of fresh notice to the respondent via registered post and email.

10
Stage 902/07/2021

Defect Removal

The Tribunal noted the removal of registry defects and directed that notice be issued to the respondent via registered post and email, scheduling the hearing for July 29, 2021.

11
Stage 10Final Ruling Order

Tribunal Order #0901126027012021-19-04-2022

The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposit (after settling the outstanding HDFC bank loan) along with interest at the rate of MCLR+1% per annum.

12
Stage 11Interim Order

Tribunal Order #0901126027012021-09-11-2021

The Tribunal condoned a 150-day delay in filing the appeal by applying the Supreme Court's relaxation of limitation periods due to the Covid-19 pandemic and directed the defective appeal to be registered as a Regular Appeal.

13
Stage 12Interim Order

Tribunal Order #0901126027012021-05-01-2022

The Tribunal closed the respondent's opportunity to file an objection to the memo of appeal due to their repeated failure to appear and submit objections despite being granted a final opportunity.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposit (after settling the outstanding HDFC bank loan) along with interest at the rate of MCLR+1% per annum. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% per annum.

Disposal Winner: AppellantInterest Rate: MCLR + 1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposit (after settling the outstanding HDFC bank loan) along with interest at the rate of MCLR+1% per annum.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1% per annum

Interest Period

from the date of deposit till the refund of the amount

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Sarvesh Tiwari

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126027012021-19-04-2022

The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposit (after settling the outstanding HDFC bank loan) along with interest at the rate of MCLR+1% per annum.

INTERIM_ORDEROrder ID: 0901126027012021-09-11-2021

The Tribunal condoned a 150-day delay in filing the appeal by applying the Supreme Court's relaxation of limitation periods due to the Covid-19 pandemic and directed the defective appeal to be registered as a Regular Appeal.

INTERIM_ORDEROrder ID: 0901126027012021-05-01-2022

The Tribunal closed the respondent's opportunity to file an objection to the memo of appeal due to their repeated failure to appear and submit objections despite being granted a final opportunity.

TathyaGrid RERA Intelligence AI

Need to research all rulings for proview infrastructure pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →