Appellant / Complainant
Shailja Yadav
Respondent
Agrani Homes Pvt Ltd
agrani homes pvt ltd
Partial
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126026812021 by Shailja Yadav against Agrani Homes Pvt Ltd before up_rera.
Further Order
The Tribunal disposed of the appeal following a settlement reached between the appellant, Shailja Yadav, and the respondent, Agrani Homes Pvt Ltd, as per the terms of their submitted settlement deed.
Hearing
The Tribunal adjourned the matter to 27.10.2021 to allow the parties to file a settlement deed following an out-of-court settlement.
Defect Removal
The Tribunal adjourned the appeal to 08.10.2021 for hearing, noting that similar cases between the parties were settled in Lok Adalat and requesting consolidation of hearing dates for convenience.
Notice
The Tribunal directed the respondent's counsel to file their Vakalatnama and ordered the appellant to file a delay condonation application within 15 days. The case is listed for September 15, 2021, for disposal of the delay condonation application.
Notice
The Tribunal granted the respondent two weeks to file objections to the appeal and directed that all subsequent filings be uploaded to the e-Portal and submitted to the Registry before the next hearing on 13.08.2021.
Delay condonation
The Tribunal noted that the appeals were filed beyond the limitation period and granted the appellant 15 days to file an application for condonation of delay, while directing notice to be issued to the respondent.
Tribunal Order #0901126026812021-27-10-2021
The Tribunal disposed of the appeal following a settlement reached between the appellant, Shailja Yadav, and the respondent, Agrani Homes Pvt Ltd, as per the terms of their submitted settlement deed.
Tribunal Order #0901126026812021-13-08-2021
The Tribunal directed the respondent's counsel to file their Vakalatnama and ordered the appellant to file a delay condonation application within 15 days. The case is listed for September 15, 2021, for disposal of the delay condonation application.
Tribunal Disposal & Final Award Ruling
The Tribunal disposed of the appeal following a settlement reached between the appellant, Shailja Yadav, and the respondent, Agrani Homes Pvt Ltd, as per the terms of their submitted settlement deed. Awarded in favor of Partial.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal disposed of the appeal following a settlement reached between the appellant, Shailja Yadav, and the respondent, Agrani Homes Pvt Ltd, as per the terms of their submitted settlement deed.
Ruling Awarded To
Partial
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Arvind Kumar Shukla
- Shobhit Singh
Official RERA Tribunal Orders (2)
The Tribunal disposed of the appeal following a settlement reached between the appellant, Shailja Yadav, and the respondent, Agrani Homes Pvt Ltd, as per the terms of their submitted settlement deed.
The Tribunal directed the respondent's counsel to file their Vakalatnama and ordered the appellant to file a delay condonation application within 15 days. The case is listed for September 15, 2021, for disposal of the delay condonation application.