Appellant / Complainant
Varinder Kumar Suri, Vinod Bala Suri
Respondent
Mmr Saha Infrastructure Private Limited
mmr saha infrastructure private limited
₹33,97,042
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126026542024 by Varinder Kumar Suri, Vinod Bala Suri against Mmr Saha Infrastructure Private Limited before up_rera.
Delay condonation
The Tribunal set aside the Regulatory Authority's direction to postpone a refund to a future date, ruling that under Section 18 of the RERA Act, an allottee has an absolute right to withdraw from a delayed project and seek an immediate refund.
Delay condonation
Upon a joint request from the counsels for both parties, the Tribunal has rescheduled the final hearing of the appeal to 03.01.2025.
Delay condonation
The Tribunal granted the respondent three weeks to file objections and directed that the appellant may file a reply within one week of receiving said objections. The matter is listed for orders on 06.12.2024.
For Order
The Tribunal granted the respondent seven days to file a vakalatnama and objections, with instructions for electronic service and subsequent filing of a reply by the appellant.
Defect Removal
The Tribunal issued notice to the respondent regarding the appeal filed by Varinder Kumar Suri against an order dated 09.04.2024 and set a procedural timeline for service of notice and filing of objections.
Defect Removal
The Tribunal granted time for the office to remove defects and adjourned the appeal to 28.08.2024 for orders or hearing.
Defect Removal
The Tribunal noted the absence of the applicant's counsel and adjourned the matter to 20.08.2024 to allow the office to report on the removal of defects in the appeal.
Defect Removal
The Tribunal directed the NIC to rectify PAN Card defects in the appeal filing and scheduled the matter for hearing on 14.08.2024.
Defect Removal
The Tribunal granted the appellant one week to rectify registry defects and scheduled the matter for hearing on August 6, 2024.
Tribunal Order #0901126026542024-03-01-2025
The Tribunal set aside the Regulatory Authority's direction to postpone a refund to a future date, ruling that under Section 18 of the RERA Act, an allottee has an absolute right to withdraw from a delayed project and seek an immediate refund.
Tribunal Disposal & Final Award Ruling
The Tribunal set aside the Regulatory Authority's direction to postpone a refund to a future date, ruling that under Section 18 of the RERA Act, an allottee has an absolute right to withdraw from a delayed project and seek an immediate refund. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal set aside the Regulatory Authority's direction to postpone a refund to a future date, ruling that under Section 18 of the RERA Act, an allottee has an absolute right to withdraw from a delayed project and seek an immediate refund.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1%
Interest Period
till the date of payments
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rudransh Singh
Respondent Advocate(s)
- Madhvendra Singh
- S.K. Singh
Official RERA Tribunal Orders (1)
The Tribunal set aside the Regulatory Authority's direction to postpone a refund to a future date, ruling that under Section 18 of the RERA Act, an allottee has an absolute right to withdraw from a delayed project and seek an immediate refund.
Need to research all rulings for mmr saha infrastructure private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.