up_reraStatus: Completed
CASE ID: 0901126026222021

Appellant / Complainant

Himanshu Kumar Gaur

VS

Respondent

Agrani Homes Pvt Ltd

Developer Firm

agrani homes pvt ltd

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

9 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126026222021 by Himanshu Kumar Gaur against Agrani Homes Pvt Ltd before up_rera.

2
Stage 127/10/2021

Further Order

The U.P. Real Estate Appellate Tribunal disposed of the appeal following a settlement reached between the appellant and respondent, with the terms of the settlement deed forming part of the final order.

3
Stage 208/10/2021

Hearing

The Tribunal granted an adjournment as the parties informed the court that a settlement has been reached out of court and requested time to file the settlement deed.

4
Stage 315/09/2021

Notice

The Tribunal adjourned the appeal to 08.10.2021 for hearing to align with other cases involving the same builder-company.

5
Stage 413/08/2021

Notice

The Tribunal directed the respondent to file objections to the appeal within two weeks and instructed counsel to file their Vakalatnama within 15 days. The matter is scheduled for further hearing on 15.09.2021.

6
Stage 515/07/2021

Notice

The Tribunal granted the respondent two weeks to file objections to the appeal and directed counsel to file a vakalatnama, scheduling the next hearing for 13.08.2021.

7
Stage 618/06/2021

Hearing on Appeal

No text available.

8
Stage 7Final Ruling Order

Tribunal Order #0901126026222021-27-10-2021

The U.P. Real Estate Appellate Tribunal disposed of the appeal following a settlement reached between the appellant and respondent, with the terms of the settlement deed forming part of the final order.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal disposed of the appeal following a settlement reached between the appellant and respondent, with the terms of the settlement deed forming part of the final order. Awarded in favor of Partial.

Disposal Winner: PartialStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal disposed of the appeal following a settlement reached between the appellant and respondent, with the terms of the settlement deed forming part of the final order.

Ruling Awarded To

Partial

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Arvind Kumar Shukla
  • Shobhit Singh

Respondent Advocate(s)

  • Sanjay Awasthi

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126026222021-27-10-2021

The U.P. Real Estate Appellate Tribunal disposed of the appeal following a settlement reached between the appellant and respondent, with the terms of the settlement deed forming part of the final order.

TathyaGrid RERA Intelligence AI