up_reraStatus: Completed
CASE ID: 0901126025922023

Appellant / Complainant

Siddhartha Bhargawa

VS

Respondent

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disputed Amount

3,93,838

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestUnfair Cancellation & Forfeiture

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

32 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126025922023 by Siddhartha Bhargawa against Uppal Chadha Hi-Tech Developers Pvt. Ltd. before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestUnfair Cancellation & Forfeiture
2
Stage 117/09/2025

Hearing

The Tribunal quashed the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposit of Rs. 3,93,838 with interest (MCLR+1%) and pay Rs. 6,00,000 as compensation for illegally transferring the allotted unit to a third party.

3
Stage 202/09/2025

Hearing

The court granted a request for adjournment on behalf of the appellant's counsel and scheduled the case for orders on 17.09.2025.

4
Stage 314/08/2025

Hearing

The Tribunal granted the respondent additional time to seek instructions and adjourned the matter to 02.09.2025 for orders.

5
Stage 405/08/2025

Hearing

The Tribunal heard arguments regarding the appellant's claim for possession and delay interest of unit T-4/1002, noting the respondent's claim that the unit has since been cancelled and allotted to a third party; the matter is listed for orders on 14.08.2025.

6
Stage 521/07/2025

Hearing

The Tribunal granted an adjournment requested by the respondent and scheduled the appeal for hearing on 05.08.2025, noting that the matter will proceed ex parte if no written statement is filed.

7
Stage 629/05/2025

Hearing

The Tribunal allowed an amendment application and established a procedural timeline for the filing of the amended memo of appeal, objections, and rejoinder.

8
Stage 723/05/2025

Hearing

The Tribunal recorded the payment of costs by the respondent's counsel and, upon request, adjourned the appeal for hearing to 29.05.2025.

9
Stage 820/05/2025

Hearing

The Tribunal has adjourned the appeal to 23.05.2025 for orders/hearing following a joint request from the counsel for both parties.

10
Stage 925/04/2025

Hearing

The Tribunal adjourned the appeal to 20.05.2025 and imposed a cost of Rs. 3,000 to be paid by the respondent to the appellant due to the respondent's request for adjournment.

11
Stage 1027/03/2025

Hearing

The Tribunal granted a request from the respondent's counsel to adjourn the appeal, rescheduling the matter for hearing on 25.04.2025.

12
Stage 1104/03/2025

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 27.03.2025.

13
Stage 1217/02/2025

Hearing

The Tribunal has adjourned the appeal to 04.03.2025 following a joint request from the counsels for both parties.

14
Stage 1329/01/2025

Hearing

The Tribunal granted an adjournment requested by the respondent and rescheduled the appeal for hearing on 17.02.2025, noting that no further adjournments will be permitted.

15
Stage 1416/01/2025

Hearing

The matter is adjourned because the appellant's counsel is on sanctioned leave, and the case is rescheduled for hearing on 29.01.2025.

16
Stage 1517/12/2024

Hearing

The Tribunal granted an adjournment requested by both parties and rescheduled the appeal for hearing on 16.01.2025.

17
Stage 1629/11/2024

Hearing

No text available.

18
Stage 1725/10/2024

Hearing

The proceedings were adjourned due to the illness of the respondent's counsel, with the matter rescheduled for hearing on 29-11-2024.

19
Stage 1818/09/2024

Hearing

The Tribunal has scheduled the appeal for a final hearing on 25.10.2024 following the exchange of pleadings.

20
Stage 1922/08/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the appeal for a final hearing on 18.09.2024.

21
Stage 2019/07/2024

Hearing

The Tribunal noted that pleadings have been exchanged and adjourned the appeal for a hearing on 22.08.2024.

22
Stage 2119/04/2024

Hearing

The Tribunal granted the respondent a 10-day extension to file objections to the appeal and scheduled the next hearing for May 20, 2024.

23
Stage 2214/03/2024

Hearing

The Tribunal granted the appellant a final 10-day extension to file a reply to the respondent's objection and scheduled the matter for hearing on 19.04.2024.

24
Stage 2308/02/2024

Hearing

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the next hearing for 14.03.2024.

25
Stage 2409/11/2023

Hearing

No text available.

26
Stage 2526/09/2023

Hearing

The Tribunal granted the respondent 10 days to file objections to the grounds of appeal and directed the parties to exchange copies and upload their respective filings on the e-portal before the next hearing on 09.11.2023.

27
Stage 2616/08/2023

Notice

The Tribunal ruled that service of notice to the respondent is sufficient based on postal and electronic records, and granted the respondent 10 days to file an objection.

28
Stage 2721/06/2023

Admission

The Tribunal issued a notice to the respondent and established a procedural timeline for the service of appeal documents and the filing of objections and replies.

29
Stage 28Final Ruling Order

Tribunal Order #0901126025922023-17-09-2025

The Tribunal quashed the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposit of Rs. 3,93,838 with interest (MCLR+1%) and pay Rs. 6,00,000 as compensation for illegally transferring the allotted unit to a third party.

30
Stage 29Interim Order

Tribunal Order #0901126025922023-05-08-2025

The Tribunal heard arguments regarding the appellant's claim for possession and delay interest of unit T-4/1002, noting the respondent's claim that the unit has since been cancelled and allotted to a third party; the matter is listed for orders on 14.08.2025.

31
Stage 30Interim Order

Tribunal Order #0901126025922023-25-04-2025

The Tribunal adjourned the appeal to 20.05.2025 and imposed a cost of Rs. 3,000 to be paid by the respondent to the appellant due to the respondent's request for adjournment.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal quashed the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposit of Rs. 3,93,838 with interest (MCLR+1%) and pay Rs. 6,00,000 as compensation for illegally transferring the allotted unit to a third party. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.

Disposal Winner: AppellantInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal quashed the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposit of Rs. 3,93,838 with interest (MCLR+1%) and pay Rs. 6,00,000 as compensation for illegally transferring the allotted unit to a third party.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1%

Interest Period

w.e.f. 28.10.2013 till the date of payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Sunendra Kumar
  • N A

Respondent Advocate(s)

  • Surangama Sharma
  • Naveen Kumar Tiwari

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126025922023-17-09-2025

The Tribunal quashed the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposit of Rs. 3,93,838 with interest (MCLR+1%) and pay Rs. 6,00,000 as compensation for illegally transferring the allotted unit to a third party.

INTERIM_ORDEROrder ID: 0901126025922023-05-08-2025

The Tribunal heard arguments regarding the appellant's claim for possession and delay interest of unit T-4/1002, noting the respondent's claim that the unit has since been cancelled and allotted to a third party; the matter is listed for orders on 14.08.2025.

INTERIM_ORDEROrder ID: 0901126025922023-25-04-2025

The Tribunal adjourned the appeal to 20.05.2025 and imposed a cost of Rs. 3,000 to be paid by the respondent to the appellant due to the respondent's request for adjournment.

TathyaGrid RERA Intelligence AI