Appellant / Complainant
Sri Colonizers & Developers Pvt. Ltd
Respondent
Renu Agarwal, Rakesh Agarwal
sri colonizers & developers pvt. ltd
₹13,79,986
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126025262022 by Sri Colonizers & Developers Pvt. Ltd against Renu Agarwal, Rakesh Agarwal before up_rera.
For Order
The Tribunal disposed of the application by correcting clerical errors regarding Demand Draft numbers and amounts in the previous order dated 08.07.2022.
For Order
The Tribunal directed the transmission of Rs. 13,79,986/- deposited by the applicant to RERA, with instructions that the funds be released to the respondent during execution proceedings and any surplus returned to the promoter.
For Order
The Tribunal adjourned the application for the release of funds deposited under Section 43(5) of the Act to July 8, 2022, as no one appeared on behalf of the applicant.
Tribunal Order #0901126025262022-08-07-2022
The Tribunal directed the transmission of Rs. 13,79,986/- deposited by the applicant to RERA, with instructions that the funds be released to the respondent during execution proceedings and any surplus returned to the promoter.
Tribunal Disposal & Final Award Ruling
The Tribunal directed the transmission of Rs. 13,79,986/- deposited by the applicant to RERA, with instructions that the funds be released to the respondent during execution proceedings and any surplus returned to the promoter. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal directed the transmission of Rs. 13,79,986/- deposited by the applicant to RERA, with instructions that the funds be released to the respondent during execution proceedings and any surplus returned to the promoter.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Official RERA Tribunal Orders (1)
The Tribunal directed the transmission of Rs. 13,79,986/- deposited by the applicant to RERA, with instructions that the funds be released to the respondent during execution proceedings and any surplus returned to the promoter.
Need to research all rulings for sri colonizers & developers pvt. ltd?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.