up_reraStatus: Completed
CASE ID: 0901126025252021

Appellant / Complainant

Anil Kumar

VS

Respondent

Agrani Homes Pvt Ltd

Developer Firm

agrani homes pvt ltd

Disposal Award

Both (Settled)

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

9 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126025252021 by Anil Kumar against Agrani Homes Pvt Ltd before up_rera.

2
Stage 127/10/2021

Further Order

The appeal is disposed of following a settlement reached between the appellant, Anil Kumar, and the respondent, Agrani Homes Pvt Ltd, with the terms of the settlement deed forming part of the order.

3
Stage 208/10/2021

Hearing

The Tribunal granted an adjournment as the parties informed the court that a settlement has been reached out of court and requested time to file the settlement deed. The matter is listed for 27.10.2021.

4
Stage 315/09/2021

Notice

The Tribunal adjourned the appeal to 08.10.2021 for hearing, noting that similar cases involving the same builder are scheduled for that date.

5
Stage 413/08/2021

Notice

The Tribunal directed the respondent to file objections to the appeal within two weeks and set a timeline for the appellant's reply, while also ordering counsel for the respondent to file their Vakalatnama within 15 days.

6
Stage 515/07/2021

Notice

The Tribunal granted the respondent two weeks to file objections to the appeal and directed both parties to exchange replies via email and upload documents to the e-Portal before the next hearing on 13.08.2021.

7
Stage 618/06/2021

Hearing on Appeal

No text available.

8
Stage 7Final Ruling Order

Tribunal Order #0901126025252021-27-10-2021

The appeal is disposed of following a settlement reached between the appellant, Anil Kumar, and the respondent, Agrani Homes Pvt Ltd, with the terms of the settlement deed forming part of the order.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The appeal is disposed of following a settlement reached between the appellant, Anil Kumar, and the respondent, Agrani Homes Pvt Ltd, with the terms of the settlement deed forming part of the order. Awarded in favor of Both (Settled).

Disposal Winner: Both (Settled)Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The appeal is disposed of following a settlement reached between the appellant, Anil Kumar, and the respondent, Agrani Homes Pvt Ltd, with the terms of the settlement deed forming part of the order.

Ruling Awarded To

Both (Settled)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Arvind Kumar Shukla
  • Shobhit Singh

Respondent Advocate(s)

  • Sanjay Awasthi

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126025252021-27-10-2021

The appeal is disposed of following a settlement reached between the appellant, Anil Kumar, and the respondent, Agrani Homes Pvt Ltd, with the terms of the settlement deed forming part of the order.