up_reraStatus: Completed
CASE ID: 0901126025132022

Appellant / Complainant

UH Realcon Private Limited

VS

Respondent

Prakash Ahuja

Developer Firm

uh realcon private limited

Disputed Amount

15,35,691

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestUnfair Cancellation & Forfeiture

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

37 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126025132022 by UH Realcon Private Limited against Prakash Ahuja before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestUnfair Cancellation & Forfeiture
2
Stage 130/01/2025

For Order

The Tribunal set aside the Regulatory Authority's order for a full refund, ruling that since the allottee continued in the project until completion and only sought withdrawal after receiving the CC/OC, they are entitled to interest for the delay but the promoter is permitted to deduct earnest money as per the agreement.

3
Stage 215/01/2025

For Order

The Tribunal has granted a request from the parties to list the appeal on 30.01.2025.

4
Stage 329/07/2024

Hearing

The Tribunal heard arguments from both parties regarding Appeal-257/2022 and has reserved the judgment for a later date.

5
Stage 424/07/2024

Hearing

The Tribunal granted a final one-week extension to the respondent's counsel to reply to arguments and judgments cited by the appellant, scheduling the matter for orders on 29.07.2024.

6
Stage 527/05/2024

Hearing

The appeal was adjourned because no one appeared for the appellant; the matter is now listed for hearing on 24.07.2024.

7
Stage 626/04/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to personal illness and rescheduled the appeal for hearing on 27.05.2024.

8
Stage 716/04/2024

Hearing

The Tribunal adjourned the proceedings to allow the respondent's counsel time to respond to legal precedents cited by the appellant regarding the concealment of facts.

9
Stage 804/04/2024

Hearing

The Tribunal granted a one-week extension to the appellant's counsel to conduct legal research regarding claims of concealment and adjourned the matter to 16.04.2024.

10
Stage 901/03/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and rescheduled the hearing for April 4, 2024.

11
Stage 1012/02/2024

Hearing

The Tribunal has rescheduled the hearing for Appeal-257/2022 to March 1, 2024, following a joint request from the counsels of both parties.

12
Stage 1118/01/2024

Hearing

The Tribunal allowed the appellant's application to amend the memo of appeal to include legal grounds regarding an allottee's duty to take possession within two months of the issuance of an Occupancy Certificate (OC).

13
Stage 1216/10/2023

Hearing

No text available.

14
Stage 1306/09/2023

Hearing

The Tribunal adjourned the proceedings due to a call by the Bar Council of Uttar Pradesh for lawyers to abstain from judicial work, rescheduling the hearing to 16.10.2023.

15
Stage 1418/07/2023

Hearing

The Tribunal granted a 10-day extension to the appellant to file a reply to the respondent's objections and rescheduled the hearing for September 6, 2023.

16
Stage 1505/05/2023

Hearing

The Tribunal adjourned today's proceedings due to the absence of the respondent's counsel and scheduled the appeal for a hearing on 18.07.2023.

17
Stage 1603/04/2023

Hearing

The Tribunal granted the respondent one week to file objections to the appellant's amendment application, with a subsequent timeline set for the appellant's reply and a new hearing date of 05.05.2023.

18
Stage 1723/03/2023

Hearing

The Tribunal granted a one-week adjournment at the request of the counsels and scheduled the case for orders/hearing on 03.04.2023.

19
Stage 1815/02/2023

Hearing

The Tribunal granted an adjournment request from the appellant's counsel and rescheduled the hearing for March 23, 2023.

20
Stage 1913/01/2023

Hearing

No text available.

21
Stage 2012/12/2022

Hearing

No text available.

22
Stage 2123/11/2022

For Order

The Tribunal adjourned today's proceedings due to the unavailability of the appellant's counsel and scheduled the appeal for hearing on 12.12.2022.

23
Stage 2211/11/2022

Further Hearing

The Tribunal adjourned the matter for 10 days to allow the parties to formulate terms for an amicable settlement regarding interest payments and possession.

24
Stage 2309/11/2022

Hearing

The Tribunal granted the appellant's request for more time to study the matter and adjourned the hearing to 11.11.2022.

25
Stage 2417/10/2022

For Order

The Tribunal granted an interim stay on recovery proceedings against the appellant following a finding that the respondent failed to approach the High Court with clean hands by misrepresenting the status of the appeal.

26
Stage 2512/10/2022

For Order

The Tribunal granted a joint request from the parties to list the appeal for orders or hearing on 17.10.2022.

27
Stage 2610/10/2022

For Order

The Tribunal granted a request for an urgent hearing and scheduled the matter for orders on 12.10.2022 due to the absence of the respondent's counsel.

28
Stage 2729/09/2022

For Order

The Tribunal noted that pleadings have been exchanged and scheduled the matter for the next hearing on 10.10.2022.

29
Stage 2816/09/2022

For Order

The court granted an adjournment to the respondent's counsel, who requested additional time to examine a rejoinder received only four days prior.

30
Stage 2930/08/2022

Further Order

The Tribunal has scheduled the appeal for a hearing on 16.09.2022 following the exchange of pleadings.

31
Stage 3004/08/2022

Further Order

The proceeding is adjourned because the counsel for the appellant is on sanctioned leave, and the case is rescheduled for 23.08.2022.

32
Stage 3107/07/2022

Notice

The Tribunal directed the Registry to convert the defective appeal into a regular appeal upon verification of defect removal and granted the respondent two weeks to file objections.

33
Stage 3216/05/2022

Defect Removal

The Tribunal issued notice to the respondent and directed the appellant to rectify procedural defects and complete service of the appeal documents via speed-post and email.

34
Stage 33Final Ruling Order

Tribunal Order #0901126025132022-30-01-2025

The Tribunal set aside the Regulatory Authority's order for a full refund, ruling that since the allottee continued in the project until completion and only sought withdrawal after receiving the CC/OC, they are entitled to interest for the delay but the promoter is permitted to deduct earnest money as per the agreement.

35
Stage 34Interim Order

Tribunal Order #0901126025132022-17-10-2022

The Tribunal granted an interim stay on recovery proceedings against the appellant following a finding that the respondent failed to approach the High Court with clean hands by misrepresenting the status of the appeal.

36
Stage 35Interim Order

Tribunal Order #0901126025132022-18-01-2024

The Tribunal allowed the appellant's application to amend the memo of appeal to include legal grounds regarding an allottee's duty to take possession within two months of the issuance of an Occupancy Certificate (OC).

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order for a full refund, ruling that since the allottee continued in the project until completion and only sought withdrawal after receiving the CC/OC, they are entitled to interest for the delay but the promoter is permitted to deduct earnest money as per the agreement. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order for a full refund, ruling that since the allottee continued in the project until completion and only sought withdrawal after receiving the CC/OC, they are entitled to interest for the delay but the promoter is permitted to deduct earnest money as per the agreement.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

till the date of payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kshemendra Shukla

Respondent Advocate(s)

  • Prasoon Kumar Anjor
  • Vinay Pandey

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126025132022-30-01-2025

The Tribunal set aside the Regulatory Authority's order for a full refund, ruling that since the allottee continued in the project until completion and only sought withdrawal after receiving the CC/OC, they are entitled to interest for the delay but the promoter is permitted to deduct earnest money as per the agreement.

INTERIM_ORDEROrder ID: 0901126025132022-17-10-2022

The Tribunal granted an interim stay on recovery proceedings against the appellant following a finding that the respondent failed to approach the High Court with clean hands by misrepresenting the status of the appeal.

INTERIM_ORDEROrder ID: 0901126025132022-18-01-2024

The Tribunal allowed the appellant's application to amend the memo of appeal to include legal grounds regarding an allottee's duty to take possession within two months of the issuance of an Occupancy Certificate (OC).

TathyaGrid RERA Intelligence AI

Need to research all rulings for uh realcon private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →