up_reraStatus: Completed
CASE ID: 0901126025122022

Appellant / Complainant

Priyadarshini Misra

VS

Respondent

WTC Noida Development Company Pvt. Ltd

Developer Firm

wtc noida development company pvt. ltd

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

11 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126025122022 by Priyadarshini Misra against WTC Noida Development Company Pvt. Ltd before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 121/10/2022

for delivery of Judgment/Order

The Uttar Pradesh Real Estate Appellate Tribunal rejected the review application filed by WTC Noida Development Company Pvt. Ltd., upholding the previous order that directed the developer to pay interest at MCLR+1% per annum for delay in possession.

3
Stage 230/09/2022

Hearing

The Tribunal allowed an application to amend the prayer clause of a review petition and heard arguments regarding whether interest for delay under Section 18 of the Act should be granted despite the payment of assured returns.

4
Stage 312/09/2022

For Order

The Tribunal granted the appellant a one-week extension to prepare their brief and scheduled the review application for hearing on 30.09.2022.

5
Stage 424/08/2022

Hearing

The Tribunal adjourned the review petition to 12.09.2022 due to the absence of the respondent's counsel and directed that the order be communicated to the respondent via email.

6
Stage 528/07/2022

Hearing

No text available.

7
Stage 607/07/2022

Notice

The Tribunal granted the appellant 10 days to file a reply to the objections and scheduled the review application for hearing on July 28, 2022.

8
Stage 716/05/2022

For Order

The Tribunal issued notice to the respondent regarding the applicant's review petition and provided specific procedural instructions for service of notice and filing of objections.

9
Stage 8Final Ruling Order

Tribunal Order #0901126025122022-21-10-2022

The Uttar Pradesh Real Estate Appellate Tribunal rejected the review application filed by WTC Noida Development Company Pvt. Ltd., upholding the previous order that directed the developer to pay interest at MCLR+1% per annum for delay in possession.

10
Stage 9Interim Order

Tribunal Order #0901126025122022-30-09-2022

The Tribunal allowed an application to amend the prayer clause of a review petition and heard arguments regarding whether interest for delay under Section 18 of the Act should be granted despite the payment of assured returns.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Uttar Pradesh Real Estate Appellate Tribunal rejected the review application filed by WTC Noida Development Company Pvt. Ltd., upholding the previous order that directed the developer to pay interest at MCLR+1% per annum for delay in possession. Awarded in favor of Appellant. Awarded interest rate: MCLR+1% per annum.

Disposal Winner: AppellantInterest Rate: MCLR+1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Uttar Pradesh Real Estate Appellate Tribunal rejected the review application filed by WTC Noida Development Company Pvt. Ltd., upholding the previous order that directed the developer to pay interest at MCLR+1% per annum for delay in possession.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1% per annum

Interest Period

from 14.10.2018 till the date of legal offer of possession after obtaining OC/CC from the competent authority

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • U. K. Misra

Respondent Advocate(s)

  • Uma Kant Mishra

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126025122022-21-10-2022

The Uttar Pradesh Real Estate Appellate Tribunal rejected the review application filed by WTC Noida Development Company Pvt. Ltd., upholding the previous order that directed the developer to pay interest at MCLR+1% per annum for delay in possession.

INTERIM_ORDEROrder ID: 0901126025122022-30-09-2022

The Tribunal allowed an application to amend the prayer clause of a review petition and heard arguments regarding whether interest for delay under Section 18 of the Act should be granted despite the payment of assured returns.

TathyaGrid RERA Intelligence AI

Need to research all rulings for wtc noida development company pvt. ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →