up_reraStatus: Completed
CASE ID: 0901126023882024

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Zubair Ahmad

Disputed Amount

27,93,174

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126023882024 by Lucknow Development Authority against Zubair Ahmad before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 111/03/2025

Defect Removal

The Appellate Tribunal ruled that a promoter's obligation to pay delay interest under Section 18(1) of the RERA Act is mandatory and cannot be waived by the allottee accepting possession, subsequently ordering the appellant to pay interest at MCLR+1% for the period from 31.08.2015 to 31.07.2019.

3
Stage 213/02/2025

Defect Removal

The Tribunal has adjourned the appeal to 11.03.2025 upon the joint request of the parties and directed that pleadings be completed in the interim.

4
Stage 313/01/2025

Defect Removal

No text available.

5
Stage 402/12/2024

Defect Removal

The Tribunal issued notice to the respondent and outlined the procedural steps for service of process and filing objections regarding the application for condonation of delay.

6
Stage 525/10/2024

Defect Removal

The Tribunal granted the Appellant a one-week extension to file a fresh CA certificate to comply with Section 43(5) of the Act and scheduled the hearing for December 2, 2024.

7
Stage 618/09/2024

Defect Removal

The Tribunal granted the appellant 10 days to file a CA certificate and address deficiencies regarding compliance with Section 43(5) of the Act, rescheduling the matter for 25.10.2024.

8
Stage 709/09/2024

Defect Removal

The Tribunal granted the appellant one week's time to file a fresh CA certificate as requested by the Registry and rescheduled the hearing for 18.09.2024.

9
Stage 8Final Ruling Order

Tribunal Order #0901126023882024-11-03-2025

The Appellate Tribunal ruled that a promoter's obligation to pay delay interest under Section 18(1) of the RERA Act is mandatory and cannot be waived by the allottee accepting possession, subsequently ordering the appellant to pay interest at MCLR+1% for the period from 31.08.2015 to 31.07.2019.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal ruled that a promoter's obligation to pay delay interest under Section 18(1) of the RERA Act is mandatory and cannot be waived by the allottee accepting possession, subsequently ordering the appellant to pay interest at MCLR+1% for the period from 31.08.2015 to 31.07.2019. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.

Disposal Winner: PartialInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal ruled that a promoter's obligation to pay delay interest under Section 18(1) of the RERA Act is mandatory and cannot be waived by the allottee accepting possession, subsequently ordering the appellant to pay interest at MCLR+1% for the period from 31.08.2015 to 31.07.2019.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR+1%

Interest Period

w.e.f. 31.08.2015 to 31.07.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • Suyash Gupta

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126023882024-11-03-2025

The Appellate Tribunal ruled that a promoter's obligation to pay delay interest under Section 18(1) of the RERA Act is mandatory and cannot be waived by the allottee accepting possession, subsequently ordering the appellant to pay interest at MCLR+1% for the period from 31.08.2015 to 31.07.2019.