up_reraStatus: Completed
CASE ID: 0901126023872024

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Hari Pratap Shahi

Disputed Amount

49,50,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

11 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126023872024 by Lucknow Development Authority against Hari Pratap Shahi before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 111/03/2025

Defect Removal

The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at the rate of MCLR+1% from 14.09.2014 until possession, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act.

3
Stage 213/02/2025

Defect Removal

The Tribunal has adjourned the appeal to 11.03.2025 at the joint request of the parties and directed that pleadings be completed in the interim.

4
Stage 313/01/2025

Defect Removal

No text available.

5
Stage 402/12/2024

Defect Removal

The Tribunal issued notice to the respondent and directed the appellant to comply with the mandate of Section 43(5) of the Real Estate Act, 2016, as per the impugned order. The matter is scheduled for hearing on the application for condonation of delay and the appeal itself on 13.01.2025.

6
Stage 525/10/2024

Defect Removal

The Tribunal granted the appellant a one-week extension to file a fresh CA certificate to comply with Section 43(5) of the Act and scheduled the matter for hearing on December 2, 2024.

7
Stage 618/09/2024

Defect Removal

The Tribunal granted the appellant 10 days to file a CA certificate and rectify deficiencies regarding compliance with Section 43(5) of the Act, rescheduling the matter for 25.10.2024.

8
Stage 709/09/2024

Defect Removal

The Tribunal granted the appellant a one-week extension to file a fresh CA certificate to rectify a defect pointed out by the Registry and rescheduled the matter for 18.09.2024.

9
Stage 8Final Ruling Order

Tribunal Order #0901126023872024-11-03-2025

The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at the rate of MCLR+1% from 14.09.2014 until possession, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act.

10
Stage 9Interim Order

Tribunal Order #0901126023872024-02-12-2024

The Tribunal issued notice to the respondent and directed the appellant to comply with the mandate of Section 43(5) of the Real Estate Act, 2016, as per the impugned order. The matter is scheduled for hearing on the application for condonation of delay and the appeal itself on 13.01.2025.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at the rate of MCLR+1% from 14.09.2014 until possession, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at the rate of MCLR+1% from 14.09.2014 until possession, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

w.e.f. 14.09.2014 till handing over possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • Harish Pandey

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126023872024-11-03-2025

The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at the rate of MCLR+1% from 14.09.2014 until possession, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act.

INTERIM_ORDEROrder ID: 0901126023872024-02-12-2024

The Tribunal issued notice to the respondent and directed the appellant to comply with the mandate of Section 43(5) of the Real Estate Act, 2016, as per the impugned order. The matter is scheduled for hearing on the application for condonation of delay and the appeal itself on 13.01.2025.