up_reraStatus: Completed
CASE ID: 0901126023862024

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Sarvjeet Yadav

Disputed Amount

49,50,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126023862024 by Lucknow Development Authority against Sarvjeet Yadav before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 111/03/2025

Defect Removal

The Appellate Tribunal ruled that a promoter's obligation to pay delay interest under Section 18(1) of the RERA Act is mandatory and cannot be waived by the allottee taking possession; consequently, it ordered the appellant to pay interest at MCLR+1% from 14.09.2014 until possession.

3
Stage 213/02/2025

Defect Removal

The Tribunal has adjourned the appeal to 11.03.2025 at the joint request of the parties and directed that pleadings be completed in the interim.

4
Stage 313/01/2025

Defect Removal

No text available.

5
Stage 402/12/2024

Defect Removal

The Tribunal issued notice to the respondent and directed the appellant to serve the appeal documents via speed-post and email, scheduling the next hearing for January 13, 2025.

6
Stage 525/10/2024

Defect Removal

The Tribunal granted the appellant a one-week extension to file a fresh CA certificate and comply with Section 43(5) of the Act, scheduling the matter for December 2, 2024.

7
Stage 618/09/2024

Defect Removal

The Tribunal granted the appellant 10 days to file a CA certificate and rectify deficiencies regarding compliance with Section 43(5) of the Act, rescheduling the matter for 25.10.2024.

8
Stage 709/09/2024

Defect Removal

The Tribunal granted a one-week extension to the appellant to file a fresh CA certificate as requested by the Registry and rescheduled the hearing for 18.09.2024.

9
Stage 8Final Ruling Order

Tribunal Order #0901126023862024-11-03-2025

The Appellate Tribunal ruled that a promoter's obligation to pay delay interest under Section 18(1) of the RERA Act is mandatory and cannot be waived by the allottee taking possession; consequently, it ordered the appellant to pay interest at MCLR+1% from 14.09.2014 until possession.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal ruled that a promoter's obligation to pay delay interest under Section 18(1) of the RERA Act is mandatory and cannot be waived by the allottee taking possession; consequently, it ordered the appellant to pay interest at MCLR+1% from 14.09.2014 until possession. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal ruled that a promoter's obligation to pay delay interest under Section 18(1) of the RERA Act is mandatory and cannot be waived by the allottee taking possession; consequently, it ordered the appellant to pay interest at MCLR+1% from 14.09.2014 until possession.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

w.e.f. 14.09.2014 till handing over possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • Harish Pandey

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126023862024-11-03-2025

The Appellate Tribunal ruled that a promoter's obligation to pay delay interest under Section 18(1) of the RERA Act is mandatory and cannot be waived by the allottee taking possession; consequently, it ordered the appellant to pay interest at MCLR+1% from 14.09.2014 until possession.