Appellant / Complainant
Lucknow Development Authority
Respondent
Mahender Pratap Singh
₹25,70,000
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126023852024 by Lucknow Development Authority against Mahender Pratap Singh before up_rera.
Defect Removal
The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at a rate of MCLR+1% for the period from 31.08.2015 to 31.07.2019, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act.
Defect Removal
The Tribunal has adjourned the appeal to 11.03.2025 upon the joint request of the parties and directed that pleadings be completed in the interim.
Defect Removal
The Tribunal issued notice to the respondent and directed the appellant to serve the appeal documents via speed-post and email, while mandating compliance with Section 43(5) of the Act, 2016 in the interim.
Defect Removal
The Tribunal granted a one-week extension to the Appellant for filing a fresh CA certificate to comply with Section 43(5) of the Act and scheduled the hearing for December 2, 2024.
Defect Removal
The Tribunal granted the appellant a 10-day extension to file a CA certificate and address deficiencies regarding compliance with Section 43(5) of the Act, rescheduling the matter for 25.10.2024.
Defect Removal
The Tribunal granted the appellant a one-week extension to file a fresh CA certificate as requested by the Registry and rescheduled the defective appeal for orders on 18.09.2024.
Tribunal Order #0901126023852024-11-03-2025
The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at a rate of MCLR+1% for the period from 31.08.2015 to 31.07.2019, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act.
Tribunal Order #0901126023852024-02-12-2024
The Tribunal issued notice to the respondent and directed the appellant to serve the appeal documents via speed-post and email, while mandating compliance with Section 43(5) of the Act, 2016 in the interim.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at a rate of MCLR+1% for the period from 31.08.2015 to 31.07.2019, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at a rate of MCLR+1% for the period from 31.08.2015 to 31.07.2019, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR+1%
Interest Period
w.e.f. 31.08.2015 to 31.07.2019
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Abhishek Khare
Respondent Advocate(s)
- Suyash Gupta
Official RERA Tribunal Orders (2)
The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at a rate of MCLR+1% for the period from 31.08.2015 to 31.07.2019, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act.
The Tribunal issued notice to the respondent and directed the appellant to serve the appeal documents via speed-post and email, while mandating compliance with Section 43(5) of the Act, 2016 in the interim.