up_reraStatus: Completed
CASE ID: 0901126023842024

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Vijai Raj Saxena

Disputed Amount

44,50,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126023842024 by Lucknow Development Authority against Vijai Raj Saxena before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 111/03/2025

Defect Removal

The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at the rate of MCLR+1% from 14.09.2014 until possession is handed over, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act.

3
Stage 213/02/2025

Defect Removal

The Tribunal has adjourned the appeal to 11.03.2025 upon the joint request of the parties and directed that pleadings be completed in the interim.

4
Stage 313/01/2025

Defect Removal

No text available.

5
Stage 402/12/2024

Defect Removal

The Tribunal has adjourned the appeal to 13.01.2025 following a joint request from both parties.

6
Stage 525/10/2024

Defect Removal

The Tribunal granted the appellant a one-week extension to file a fresh CA certificate to comply with Section 43(5) of the Act and scheduled the hearing for December 2, 2024.

7
Stage 618/09/2024

Defect Removal

The Tribunal granted the appellant 10 days to file a CA certificate and address deficiencies regarding compliance with Section 43(5) of the Act, rescheduling the matter for 25.10.2024.

8
Stage 709/09/2024

Defect Removal

The Tribunal granted the appellant a one-week extension to file a fresh CA certificate as requested by counsel to rectify a defect in the appeal.

9
Stage 8Final Ruling Order

Tribunal Order #0901126023842024-11-03-2025

The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at the rate of MCLR+1% from 14.09.2014 until possession is handed over, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at the rate of MCLR+1% from 14.09.2014 until possession is handed over, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at the rate of MCLR+1% from 14.09.2014 until possession is handed over, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

w.e.f. 14.09.2014 till handing over possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • Suyash Bajpai

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126023842024-11-03-2025

The Appellate Tribunal modified the previous order to mandate that the promoter pay delay interest at the rate of MCLR+1% from 14.09.2014 until possession is handed over, ruling that an allottee's acceptance of possession does not waive their statutory right to interest under Section 18(1) of the Act.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.