up_reraStatus: Active
CASE ID: 0901126023722022

Appellant / Complainant

Anand Lifespace Development LLP

VS

Respondent

Atul Dixit

Developer Firm

anand lifespace development llp

Disputed Amount

20,84,744

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126023722022 by Anand Lifespace Development LLP against Atul Dixit before up_rera.

2
Stage 121/04/2023

For Order

The Tribunal corrected a clerical error in its previous order dated 30.01.2023 to accurately reflect the deposited amount as Rs. 8,84,744/- instead of Rs. 84,744/-.

3
Stage 219/04/2023

For Order

The Tribunal granted a request from the respondent's counsel to reschedule the hearing of Appeal-327/2022 to 21.04.2023.

4
Stage 330/01/2023

Hearing

The Tribunal permitted the appellant to withdraw the appeal following an amicable settlement and directed the release of deposited funds totaling Rs. 20,84,744 to the respondent.

5
Stage 421/12/2022

Hearing

The Tribunal granted a request by the appellant's counsel to adjourn the matter and rescheduled the hearing for 30.01.2023.

6
Stage 529/11/2022

Hearing

No text available.

7
Stage 625/11/2022

Hearing

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and directed that a soft copy be shared with the respondent and uploaded to the e-portal.

8
Stage 731/10/2022

Hearing

The Tribunal adjourned the proceedings due to the appellant's counsel's illness and granted the appellant 10 days to file a reply to the respondent's objections.

9
Stage 823/09/2022

Hearing

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and directed that a soft copy be emailed to the respondent. The matter is scheduled for hearing on 31.10.2022.

10
Stage 931/08/2022

Hearing

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the next hearing for September 23, 2022.

11
Stage 1004/08/2022

Defect Removal

The Tribunal condoned the eight-day delay in filing the appeal, directed the Registry to convert the defective appeal into a regular one, and scheduled the matter for hearing on 31.08.2022.

12
Stage 1118/07/2022

Defect Removal

The Tribunal granted the appellant additional time to file a certified copy of the impugned order and allowed the respondent one week to submit their objections in English.

13
Stage 1231/05/2022

Defect Removal

The Tribunal issued notice to the respondent after finding that the appellant complied with Section 43(5) of the Act by depositing Rs. 28,84,744/- and set a hearing date for July 18, 2022.

14
Stage 13Final Ruling Order

Tribunal Order #0901126023722022-30-01-2023

The Tribunal permitted the appellant to withdraw the appeal following an amicable settlement and directed the release of deposited funds totaling Rs. 20,84,744 to the respondent.

15
Stage 14Interim Order

Tribunal Order #0901126023722022-31-05-2022

The Tribunal issued notice to the respondent after finding that the appellant complied with Section 43(5) of the Act by depositing Rs. 28,84,744/- and set a hearing date for July 18, 2022.

16
Stage 15Interim Order

Tribunal Order #0901126023722022-21-04-2023

The Tribunal corrected a clerical error in its previous order dated 30.01.2023 to accurately reflect the deposited amount as Rs. 8,84,744/- instead of Rs. 84,744/-.

17
Stage 16Interim Order

Tribunal Order #0901126023722022-04-08-2022

The Tribunal condoned the eight-day delay in filing the appeal, directed the Registry to convert the defective appeal into a regular one, and scheduled the matter for hearing on 31.08.2022.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal permitted the appellant to withdraw the appeal following an amicable settlement and directed the release of deposited funds totaling Rs. 20,84,744 to the respondent. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal permitted the appellant to withdraw the appeal following an amicable settlement and directed the release of deposited funds totaling Rs. 20,84,744 to the respondent.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Siddharth Nandwani

Respondent Advocate(s)

  • Aahuti Agarwal
  • Prem Kuar Pandey

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126023722022-30-01-2023

The Tribunal permitted the appellant to withdraw the appeal following an amicable settlement and directed the release of deposited funds totaling Rs. 20,84,744 to the respondent.

INTERIM_ORDEROrder ID: 0901126023722022-31-05-2022

The Tribunal issued notice to the respondent after finding that the appellant complied with Section 43(5) of the Act by depositing Rs. 28,84,744/- and set a hearing date for July 18, 2022.

INTERIM_ORDEROrder ID: 0901126023722022-21-04-2023

The Tribunal corrected a clerical error in its previous order dated 30.01.2023 to accurately reflect the deposited amount as Rs. 8,84,744/- instead of Rs. 84,744/-.

INTERIM_ORDEROrder ID: 0901126023722022-04-08-2022

The Tribunal condoned the eight-day delay in filing the appeal, directed the Registry to convert the defective appeal into a regular one, and scheduled the matter for hearing on 31.08.2022.

TathyaGrid RERA Intelligence AI

Need to research all rulings for anand lifespace development llp?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →