Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126023652021 by Earthcon Construction Pvt. Ltd. against Sabita Singh before up_rera.
Defect Removal
The defective appeal filed by Earthcon Construction Pvt. Ltd. was dismissed due to the appellant's failure to comply with the mandatory provisions of Section 43(5) of the Act.
Defect Removal
The Tribunal granted the appellant a final opportunity to comply with Section 43(5) of the Act and rectify registry defects, noting that compliance is a condition precedent for entertaining the appeal.
Defect Removal
The Tribunal directed the appellant to rectify five registry-identified defects within one week and scheduled the matter for further orders on 24.09.2021.
Tribunal Order #0901126023652021-27-10-2021
The defective appeal filed by Earthcon Construction Pvt. Ltd. was dismissed due to the appellant's failure to comply with the mandatory provisions of Section 43(5) of the Act.
Tribunal Order #0901126023652021-24-09-2021
The Tribunal granted the appellant a final opportunity to comply with Section 43(5) of the Act and rectify registry defects, noting that compliance is a condition precedent for entertaining the appeal.
Tribunal Disposal & Final Award Ruling
The defective appeal filed by Earthcon Construction Pvt. Ltd. was dismissed due to the appellant's failure to comply with the mandatory provisions of Section 43(5) of the Act. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The defective appeal filed by Earthcon Construction Pvt. Ltd. was dismissed due to the appellant's failure to comply with the mandatory provisions of Section 43(5) of the Act.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Kartikey Dubey
Official RERA Tribunal Orders (2)
The defective appeal filed by Earthcon Construction Pvt. Ltd. was dismissed due to the appellant's failure to comply with the mandatory provisions of Section 43(5) of the Act.
The Tribunal granted the appellant a final opportunity to comply with Section 43(5) of the Act and rectify registry defects, noting that compliance is a condition precedent for entertaining the appeal.