up_reraStatus: Completed
CASE ID: 0901126023592021

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Ram Shankar Verma

Disputed Amount

84,50,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

29 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126023592021 by Lucknow Development Authority against Ram Shankar Verma before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 130/05/2024

for delivery of Judgment/Order

The Tribunal partially allowed the allottee's appeal by directing the Lucknow Development Authority to pay delay interest at MCLR+1% from 10.09.2014 until actual possession and dismissed the promoter's cross-appeal.

3
Stage 201/04/2024

Hearing

The Tribunal has reserved the judgment for Appeal-330/2021, referring to a previous order passed in cross Appeal No. 564/2020.

4
Stage 328/02/2024

Hearing

The Tribunal has issued a routine procedural order to list the appeal for hearing on 01.04.2024.

5
Stage 409/02/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and ordered that Appeal-330/2021 be listed for hearing alongside Appeal No. 564 of 2020 on 28.02.2024.

6
Stage 509/10/2023

Hearing

No text available.

7
Stage 629/08/2023

Hearing

No text available.

8
Stage 711/07/2023

Hearing

No text available.

9
Stage 801/05/2023

Hearing

No text available.

10
Stage 910/04/2023

Hearing

The Tribunal adjourned the proceedings and ordered that Appeal-330/2021 be listed for hearing on 01.05.2023 along with the cross-appeal, Appeal No. 564/2020.

11
Stage 1013/03/2023

Hearing

The Tribunal directed that the current appeal be listed alongside Appeal No. 564/2020 (Ram Shankar Verma Vs. Lucknow Development Authority) on 10.04.2023 following a request for consolidation.

12
Stage 1102/02/2023

Hearing

No text available.

13
Stage 1221/12/2022

Hearing

The Tribunal adjourned the appeal due to the absence of the respondent and scheduled the matter for a hearing on 02.02.2023.

14
Stage 1313/09/2022

Exchange of pleadings

The Tribunal heard arguments from both parties and reserved the judgment for a later date.

15
Stage 1418/08/2022

Exchange of pleadings

The Tribunal granted an adjournment to both parties and directed the respondent to file objections to the grounds of appeal within one week, with subsequent timelines set for the appellant's reply.

16
Stage 1520/07/2022

Hearing

The Tribunal granted the respondent a final 10-day extension to file objections to the appeal and scheduled the next hearing for August 18, 2022.

17
Stage 1610/05/2022

Hearing

The Tribunal adjourned the matter to 20.07.2022 due to the absence of the respondent and a lawyer strike by the Oudh Bar Association.

18
Stage 1706/04/2022

Hearing

The Tribunal allowed the application for condonation of delay in filing the appeal, subject to a cost of Rs. 5000/-, and directed the respondent to file a reply to the grounds of appeal before the next hearing on 20.05.2022.

19
Stage 1804/03/2022

Further Order

The Tribunal directed the respondent to file an objection against the limitation application within two weeks and scheduled the matter for April 6, 2022, to dispose of said application.

20
Stage 1921/01/2022

Further Order

No text available.

21
Stage 2024/12/2021

Delay condonation

The Tribunal directed the respondent to file objections against the appellant's limitation application within 15 days and scheduled the matter for January 21, 2022, to dispose of said application.

22
Stage 2126/11/2021

Delay condonation

The Tribunal directed the respondent's counsel to file a Vakalatnama and an objection to the application for condonation of delay within one week, scheduling the next hearing for 23.12.2021.

23
Stage 2209/11/2021

Defect Removal

The Tribunal directed the parties to upload their pleadings on the e-portal and file originals with the Registry, scheduling the matter for consideration of the condonation of delay application on 26.11.2021.

24
Stage 2305/10/2021

Defect Removal

The Tribunal directed the appellant to rectify a defective Form 'L' and issued notice to the respondent regarding the application for condonation of delay, scheduling the matter for 09.11.2021.

25
Stage 2419/04/2021

Defect Removal

No text available.

26
Stage 2506/04/2021

Defect Removal

No text available.

27
Stage 26Final Ruling Order

Tribunal Order #0901126023592021-30-05-2024

The Tribunal partially allowed the allottee's appeal by directing the Lucknow Development Authority to pay delay interest at MCLR+1% from 10.09.2014 until actual possession and dismissed the promoter's cross-appeal.

28
Stage 27Interim Order

Tribunal Order #0901126023592021-06-04-2022

The Tribunal allowed the application for condonation of delay in filing the appeal, subject to a cost of Rs. 5000/-, and directed the respondent to file a reply to the grounds of appeal before the next hearing on 20.05.2022.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal partially allowed the allottee's appeal by directing the Lucknow Development Authority to pay delay interest at MCLR+1% from 10.09.2014 until actual possession and dismissed the promoter's cross-appeal. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% p.a..

Disposal Winner: AppellantInterest Rate: MCLR + 1% p.a.Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal partially allowed the allottee's appeal by directing the Lucknow Development Authority to pay delay interest at MCLR+1% from 10.09.2014 until actual possession and dismissed the promoter's cross-appeal.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1% p.a.

Interest Period

from 10.09.2014 till the actual date of possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • Abhinav Singh

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126023592021-30-05-2024

The Tribunal partially allowed the allottee's appeal by directing the Lucknow Development Authority to pay delay interest at MCLR+1% from 10.09.2014 until actual possession and dismissed the promoter's cross-appeal.

INTERIM_ORDEROrder ID: 0901126023592021-06-04-2022

The Tribunal allowed the application for condonation of delay in filing the appeal, subject to a cost of Rs. 5000/-, and directed the respondent to file a reply to the grounds of appeal before the next hearing on 20.05.2022.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →