up_reraStatus: Completed
CASE ID: 0901126023122022

Appellant / Complainant

Vijay Kumar Singh, Suman Singh

VS

Respondent

Lucknow Development Authority

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126023122022 by Vijay Kumar Singh, Suman Singh against Lucknow Development Authority before up_rera.

Delay Compensation / Interest
2
Stage 130/12/2022

for delivery of Judgment/Order

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, it directed the transfer of deposited funds under Section 43(5) of the Act to the Regulatory Authority.

3
Stage 206/12/2022

Delay condonation

No text available.

4
Stage 317/11/2022

Delay condonation

The Tribunal allowed an adjournment application filed by the respondent's counsel and rescheduled the hearing for December 6, 2022.

5
Stage 402/11/2022

Delay condonation

The Tribunal noted the absence of the respondent's counsel and ordered the case to be listed for a subsequent hearing on 17.11.2022.

6
Stage 517/10/2022

Delay condonation

The Tribunal scheduled the matter for a final hearing on November 2, 2022.

7
Stage 610/10/2022

Delay condonation

No text available.

8
Stage 706/09/2022

Delay condonation

The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the defective appeal for hearing on 10.10.2022.

9
Stage 805/08/2022

Notice

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the matter to 06.09.2022 for the disposal of a delay condonation application.

10
Stage 906/06/2022

Defect Removal

The Tribunal directed the appellant to remove registry defects within a week and outlined specific procedural steps for issuing notice to the respondent and serving documents via speed-post and email.

11
Stage 10Final Ruling Order

Tribunal Order #0901126023122022-30-12-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, it directed the transfer of deposited funds under Section 43(5) of the Act to the Regulatory Authority.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, it directed the transfer of deposited funds under Section 43(5) of the Act to the Regulatory Authority. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, it directed the transfer of deposited funds under Section 43(5) of the Act to the Regulatory Authority.

Ruling Awarded To

Respondent

Interest Period

from 27.04.2013 to 26.10.2016

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Atul Tripathi

Respondent Advocate(s)

  • Prashant Kumar Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126023122022-30-12-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, it directed the transfer of deposited funds under Section 43(5) of the Act to the Regulatory Authority.