up_reraStatus: Completed
CASE ID: 0901126022452023

Appellant / Complainant

Ratan Buildtech Private Limited

VS

Respondent

Anil Kumar

Developer Firm

ratan buildtech private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

24 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126022452023 by Ratan Buildtech Private Limited against Anil Kumar before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 114/05/2025

Hearing

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but settled the dispute by awarding the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 13.10.2022, excluding a six-month COVID-19 force majeure period.

3
Stage 221/04/2025

Hearing

The Tribunal granted an adjournment application filed by the appellant's counsel and scheduled the next hearing for 14.05.2025, with a warning that no further adjournments will be permitted.

4
Stage 321/03/2025

Hearing

Upon a joint request from the counsel for both parties, the matter has been adjourned and listed for orders on 21.04.2025.

5
Stage 428/02/2025

Hearing

The Tribunal granted a request for adjournment from the appellant's counsel and rescheduled the hearing to 21.03.2025, with a clarification that no further adjournments will be permitted.

6
Stage 505/02/2025

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to personal illness and rescheduled the hearing for 28.02.2025.

7
Stage 624/09/2024

for delivery of Judgment/Order

The Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that since the impugned orders prima facie appeared to be passed without jurisdiction, the delay should be excused to allow for a merit-based adjudication.

8
Stage 714/08/2024

Delay condonation

The Tribunal heard arguments regarding the application for condonation of delay and has reserved its order.

9
Stage 816/07/2024

Delay condonation

The Tribunal has scheduled the appeal for orders/hearing on 14.08.2024, referring to a previous order passed in Appeal No. 260/2023.

10
Stage 916/05/2024

Delay condonation

No text available.

11
Stage 1010/05/2024

Delay condonation

The Tribunal has scheduled the appeal for a hearing on 16.05.2024, noting that similar cases are being listed on that date.

12
Stage 1124/04/2024

Delay condonation

The Tribunal noted that pleadings have been exchanged and the appeal is ripe for hearing; consequently, the matter is scheduled for orders/hearing on 10.05.2024.

13
Stage 1229/03/2024

Delay condonation

The Tribunal refers the parties to a previously passed order dated in Appeal No. D382/2023 for the relevant directions.

14
Stage 1315/03/2024

Delay condonation

The Tribunal granted an extension to the appellant's counsel to rectify potential deficiencies in compliance with Section 43(5) of the Act and scheduled the matter for hearing on March 29, 2024.

15
Stage 1413/02/2024

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for hearing on 15.03.2024 regarding the application for condonation of delay.

16
Stage 1505/01/2024

Delay condonation

The Tribunal granted the applicant 10 days to file a reply to the objection for condonation of delay, subject to a cost of Rs. 500/-, and directed the respondent to file objections to the grounds of appeal within one week.

17
Stage 1628/09/2023

Delay condonation

No text available.

18
Stage 1721/08/2023

Delay condonation

The Tribunal granted the respondent 10 days to file objections regarding the condonation of delay and grounds of appeal, with subsequent timelines set for the appellant's reply.

19
Stage 1803/07/2023

Delay condonation

The Tribunal noted the appellant's compliance with Section 43(5) regarding the deposit of Rs.10,85,047/- and issued notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 21.08.2023.

20
Stage 19Interim Order

Tribunal Order #0901126022452023-05-01-2024

The Tribunal granted the applicant 10 days to file a reply to the objection for condonation of delay, subject to a cost of Rs. 500/-, and directed the respondent to file objections to the grounds of appeal within one week.

21
Stage 20Interim Order

Tribunal Order #0901126022452023-03-07-2023

The Tribunal noted the appellant's compliance with Section 43(5) regarding the deposit of Rs.10,85,047/- and issued notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 21.08.2023.

22
Stage 21Final Ruling Order

Tribunal Order #0901126022452023-14-05-2025

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but settled the dispute by awarding the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 13.10.2022, excluding a six-month COVID-19 force majeure period.

23
Stage 22Interim Order

Tribunal Order #0901126022452023-24-09-2024

The Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that since the impugned orders prima facie appeared to be passed without jurisdiction, the delay should be excused to allow for a merit-based adjudication.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but settled the dispute by awarding the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 13.10.2022, excluding a six-month COVID-19 force majeure period. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but settled the dispute by awarding the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 13.10.2022, excluding a six-month COVID-19 force majeure period.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.01.2020 to 13.10.2022 (except for the six months force majeure period on account of Covid-19)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Mahima Pahwa

Respondent Advocate(s)

  • Shivendra Rao

Official RERA Tribunal Orders (4)

INTERIM_ORDEROrder ID: 0901126022452023-05-01-2024

The Tribunal granted the applicant 10 days to file a reply to the objection for condonation of delay, subject to a cost of Rs. 500/-, and directed the respondent to file objections to the grounds of appeal within one week.

INTERIM_ORDEROrder ID: 0901126022452023-03-07-2023

The Tribunal noted the appellant's compliance with Section 43(5) regarding the deposit of Rs.10,85,047/- and issued notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 21.08.2023.

FINAL_ORDEROrder ID: 0901126022452023-14-05-2025

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but settled the dispute by awarding the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 13.10.2022, excluding a six-month COVID-19 force majeure period.

INTERIM_ORDEROrder ID: 0901126022452023-24-09-2024

The Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that since the impugned orders prima facie appeared to be passed without jurisdiction, the delay should be excused to allow for a merit-based adjudication.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ratan buildtech private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →