Appellant / Complainant
Ratan Buildtech Private Limited
Respondent
Akhil Saxena
ratan buildtech private limited
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126022362023 by Ratan Buildtech Private Limited against Akhil Saxena before up_rera.
Hearing
The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but exercised its own powers to award the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 30.09.2022, excluding a six-month COVID-19 force majeure period.
Hearing
The Tribunal granted an adjournment application filed by the appellant's counsel and scheduled the next hearing for 14.05.2025, with a strict directive that no further adjournments will be permitted.
Hearing
The Tribunal has adjourned the matter to 21.04.2025 for orders upon a joint request from both parties.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for 21.03.2025, noting that no further adjournments will be permitted.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to personal illness and rescheduled the hearing for February 28, 2025.
for delivery of Judgment/Order
The Uttar Pradesh Real Estate Appellate Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that the impugned orders prima facie appeared to be passed without jurisdiction and prioritizing substantial justice over technical limitations.
Delay condonation
The Tribunal heard arguments regarding the application for condonation of delay and has reserved its order.
Delay condonation
The Tribunal has listed the appeal for orders/hearing on 14.08.2024, referring to a previous order passed in Appeal No. 260/2023.
Delay condonation
The Tribunal has scheduled the appeal for a hearing on 16.05.2024, noting that similar cases are being listed on that date.
Delay condonation
The Tribunal noted that pleadings have been exchanged and scheduled the appeal for orders/hearing on 10.05.2024.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel due to a conflict with a High Court engagement and rescheduled the hearing for 24.04.2024.
Delay condonation
The Tribunal noted that pleadings have been exchanged and scheduled the defective appeal for a hearing or orders on 16.04.2024.
Delay condonation
The Tribunal granted an adjournment requested by the respondent's counsel on health grounds and scheduled the matter for hearing on the application for condonation of delay on 15.03.2024.
Delay condonation
The Tribunal granted the appellant a final two-week extension to file a reply to the respondent's objections, subject to a cost of Rs. 500/- to be used for the legal library.
Delay condonation
The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for consideration of the application for condonation of delay on 28.09.2023.
Delay condonation
The Tribunal noted the appellant's compliance with Section 43(5) regarding the deposit of Rs. 6,36,453.84 and granted the respondent 10 days to file objections to the condonation of delay application and grounds of appeal.
Tribunal Order #0901126022362023-05-01-2024
The Tribunal granted the appellant a final two-week extension to file a reply to the respondent's objections, subject to a cost of Rs. 500/- to be used for the legal library.
Tribunal Order #0901126022362023-21-06-2023
The Tribunal noted the appellant's compliance with Section 43(5) regarding the deposit of Rs. 6,36,453.84 and granted the respondent 10 days to file objections to the condonation of delay application and grounds of appeal.
Tribunal Order #0901126022362023-14-05-2025
The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but exercised its own powers to award the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 30.09.2022, excluding a six-month COVID-19 force majeure period.
Tribunal Order #0901126022362023-24-09-2024
The Uttar Pradesh Real Estate Appellate Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that the impugned orders prima facie appeared to be passed without jurisdiction and prioritizing substantial justice over technical limitations.
Tribunal Disposal & Final Award Ruling
The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but exercised its own powers to award the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 30.09.2022, excluding a six-month COVID-19 force majeure period. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but exercised its own powers to award the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 30.09.2022, excluding a six-month COVID-19 force majeure period.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR+1%
Interest Period
from 01.01.2020 to 30.09.2022 (except for the six months force majeure period on account of Covid-19)
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Mahima Pahwa
Respondent Advocate(s)
- Amit Yadav
Official RERA Tribunal Orders (4)
The Tribunal granted the appellant a final two-week extension to file a reply to the respondent's objections, subject to a cost of Rs. 500/- to be used for the legal library.
The Tribunal noted the appellant's compliance with Section 43(5) regarding the deposit of Rs. 6,36,453.84 and granted the respondent 10 days to file objections to the condonation of delay application and grounds of appeal.
The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but exercised its own powers to award the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 30.09.2022, excluding a six-month COVID-19 force majeure period.
The Uttar Pradesh Real Estate Appellate Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that the impugned orders prima facie appeared to be passed without jurisdiction and prioritizing substantial justice over technical limitations.
Need to research all rulings for ratan buildtech private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.