up_reraStatus: Completed
CASE ID: 0901126022262021

Appellant / Complainant

U.P. Avas Evam Vikas Parishad

VS

Respondent

Avinash Pandey

Disputed Amount

28,90,000

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126022262021 by U.P. Avas Evam Vikas Parishad against Avinash Pandey before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 121/03/2022

Further Order

The Tribunal partly allowed the appeal by directing that a reasonable construction period of 36 months be considered instead of the proposed 28 months, and ordered the release of deposited funds to both parties based on interest calculations (MCLR+1%) from 01.05.2015 to 30.09.2019.

3
Stage 210/01/2022

Further Order

The Tribunal granted an adjournment following a request from the respondent's side and scheduled the matter for further orders on 04.02.2022.

4
Stage 309/12/2021

Further Order

The Tribunal allowed the application for condonation of delay, condoning a 37-day delay in filing the appeal due to the COVID-19 pandemic relaxation, and directed the respondent to file a reply by the next hearing on 10.01.2022.

5
Stage 417/11/2021

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and directed the respondent to file an objection to the application for condonation of delay before the next hearing on 09.12.2021.

6
Stage 518/10/2021

Delay condonation

The Tribunal granted the respondent two days to file objections to the application for condonation of delay and directed both parties to upload their pleadings on the e-portal before the next hearing scheduled for 17.11.2021.

7
Stage 617/09/2021

Delay condonation

The Tribunal directed the parties to exchange objections and replies via email and e-portal within specified timelines and listed the matter for 18.10.2021 to consider an application for condonation of delay.

8
Stage 723/04/2021

Delay condonation

No text available.

9
Stage 826/03/2021

Delay condonation

The Tribunal issued notice to the respondent regarding an application for condonation of delay and established a procedural timeline for filing objections and replies via email and the e-portal.

10
Stage 9Final Ruling Order

Tribunal Order #0901126022262021-21-03-2022

The Tribunal partly allowed the appeal by directing that a reasonable construction period of 36 months be considered instead of the proposed 28 months, and ordered the release of deposited funds to both parties based on interest calculations (MCLR+1%) from 01.05.2015 to 30.09.2019.

11
Stage 10Interim Order

Tribunal Order #0901126022262021-09-12-2021

The Tribunal allowed the application for condonation of delay, condoning a 37-day delay in filing the appeal due to the COVID-19 pandemic relaxation, and directed the respondent to file a reply by the next hearing on 10.01.2022.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal partly allowed the appeal by directing that a reasonable construction period of 36 months be considered instead of the proposed 28 months, and ordered the release of deposited funds to both parties based on interest calculations (MCLR+1%) from 01.05.2015 to 30.09.2019. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.

Disposal Winner: PartialInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal partly allowed the appeal by directing that a reasonable construction period of 36 months be considered instead of the proposed 28 months, and ordered the release of deposited funds to both parties based on interest calculations (MCLR+1%) from 01.05.2015 to 30.09.2019.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.05.2015 to 30.09.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • N N Pandey

Respondent Advocate(s)

  • Saurabh Misra

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126022262021-21-03-2022

The Tribunal partly allowed the appeal by directing that a reasonable construction period of 36 months be considered instead of the proposed 28 months, and ordered the release of deposited funds to both parties based on interest calculations (MCLR+1%) from 01.05.2015 to 30.09.2019.

INTERIM_ORDEROrder ID: 0901126022262021-09-12-2021

The Tribunal allowed the application for condonation of delay, condoning a 37-day delay in filing the appeal due to the COVID-19 pandemic relaxation, and directed the respondent to file a reply by the next hearing on 10.01.2022.