Appellant / Complainant
U.P. Avas Evam Vikas Parishad
Respondent
Avinash Pandey
₹28,90,000
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126022262021 by U.P. Avas Evam Vikas Parishad against Avinash Pandey before up_rera.
Further Order
The Tribunal partly allowed the appeal by directing that a reasonable construction period of 36 months be considered instead of the proposed 28 months, and ordered the release of deposited funds to both parties based on interest calculations (MCLR+1%) from 01.05.2015 to 30.09.2019.
Further Order
The Tribunal granted an adjournment following a request from the respondent's side and scheduled the matter for further orders on 04.02.2022.
Further Order
The Tribunal allowed the application for condonation of delay, condoning a 37-day delay in filing the appeal due to the COVID-19 pandemic relaxation, and directed the respondent to file a reply by the next hearing on 10.01.2022.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel and directed the respondent to file an objection to the application for condonation of delay before the next hearing on 09.12.2021.
Delay condonation
The Tribunal granted the respondent two days to file objections to the application for condonation of delay and directed both parties to upload their pleadings on the e-portal before the next hearing scheduled for 17.11.2021.
Delay condonation
The Tribunal directed the parties to exchange objections and replies via email and e-portal within specified timelines and listed the matter for 18.10.2021 to consider an application for condonation of delay.
Delay condonation
The Tribunal issued notice to the respondent regarding an application for condonation of delay and established a procedural timeline for filing objections and replies via email and the e-portal.
Tribunal Order #0901126022262021-21-03-2022
The Tribunal partly allowed the appeal by directing that a reasonable construction period of 36 months be considered instead of the proposed 28 months, and ordered the release of deposited funds to both parties based on interest calculations (MCLR+1%) from 01.05.2015 to 30.09.2019.
Tribunal Order #0901126022262021-09-12-2021
The Tribunal allowed the application for condonation of delay, condoning a 37-day delay in filing the appeal due to the COVID-19 pandemic relaxation, and directed the respondent to file a reply by the next hearing on 10.01.2022.
Tribunal Disposal & Final Award Ruling
The Tribunal partly allowed the appeal by directing that a reasonable construction period of 36 months be considered instead of the proposed 28 months, and ordered the release of deposited funds to both parties based on interest calculations (MCLR+1%) from 01.05.2015 to 30.09.2019. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal partly allowed the appeal by directing that a reasonable construction period of 36 months be considered instead of the proposed 28 months, and ordered the release of deposited funds to both parties based on interest calculations (MCLR+1%) from 01.05.2015 to 30.09.2019.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR+1%
Interest Period
from 01.05.2015 to 30.09.2019
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- N N Pandey
Respondent Advocate(s)
- Saurabh Misra
Official RERA Tribunal Orders (2)
The Tribunal partly allowed the appeal by directing that a reasonable construction period of 36 months be considered instead of the proposed 28 months, and ordered the release of deposited funds to both parties based on interest calculations (MCLR+1%) from 01.05.2015 to 30.09.2019.
The Tribunal allowed the application for condonation of delay, condoning a 37-day delay in filing the appeal due to the COVID-19 pandemic relaxation, and directed the respondent to file a reply by the next hearing on 10.01.2022.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.