Appellant / Complainant
U.P. Awas Evam Vikas Parishad
Respondent
Ghanghor Singh
₹48,76,000
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126022182021 by U.P. Awas Evam Vikas Parishad against Ghanghor Singh before up_rera.
Further Order
The Tribunal partly allowed the appeal by adjusting the construction period to a reasonable 36 months based on Supreme Court precedent and directed the release of deposited funds between the parties according to revised interest calculations.
Further Order
The Tribunal granted the appellant's request to file a rejoinder/replication against the respondent's reply and directed that a copy be served to the respondent via email at least three days before the next hearing.
Further Order
The Tribunal granted the appellant an extension of 10 days to file a replication/rejoinder and scheduled the matter for further orders on January 10, 2022.
For Order
The Tribunal granted an adjournment requested by the appellant's counsel and directed the appellant to file a replication or rejoinder before the next hearing on 09.12.2021.
Delay condonation
The Tribunal allowed the application for condonation of delay by applying the Supreme Court's COVID-19 limitation extension guidelines and directed the defective appeal to be converted into a Regular Appeal.
Delay condonation
The Tribunal granted the respondent two weeks to file objections to the application for condonation of delay and the memo of appeal, with a subsequent hearing scheduled for 25.10.2021.
Delay condonation
The Tribunal issued notice to the respondent regarding an application for condonation of delay and directed the parties to exchange documents via email and upload objections/replies on the e-portal before the next hearing on 23.04.2021.
Tribunal Order #0901126022182021-21-03-2022
The Tribunal partly allowed the appeal by adjusting the construction period to a reasonable 36 months based on Supreme Court precedent and directed the release of deposited funds between the parties according to revised interest calculations.
Tribunal Order #0901126022182021-25-10-2021
The Tribunal allowed the application for condonation of delay by applying the Supreme Court's COVID-19 limitation extension guidelines and directed the defective appeal to be converted into a Regular Appeal.
Tribunal Disposal & Final Award Ruling
The Tribunal partly allowed the appeal by adjusting the construction period to a reasonable 36 months based on Supreme Court precedent and directed the release of deposited funds between the parties according to revised interest calculations. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal partly allowed the appeal by adjusting the construction period to a reasonable 36 months based on Supreme Court precedent and directed the release of deposited funds between the parties according to revised interest calculations.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR+1%
Interest Period
from 02.09.2015 to 30.10.2019
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- N N Pandey
Respondent Advocate(s)
- Harish Pandey
Official RERA Tribunal Orders (2)
The Tribunal partly allowed the appeal by adjusting the construction period to a reasonable 36 months based on Supreme Court precedent and directed the release of deposited funds between the parties according to revised interest calculations.
The Tribunal allowed the application for condonation of delay by applying the Supreme Court's COVID-19 limitation extension guidelines and directed the defective appeal to be converted into a Regular Appeal.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.