Appellant / Complainant
Prateek Realtors India Private Limited
Respondent
Up Real Estate Regulatory Authority
prateek realtors india private limited
₹25,49,036
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126021362024 by Prateek Realtors India Private Limited against Up Real Estate Regulatory Authority before up_rera.
Delay condonation
The Tribunal dismissed the appeal challenging a recovery certificate, ruling that the developer is liable for delay interest until the date of physical possession and directing the appellant to execute the conveyance deed within 45 days.
Delay condonation
The Tribunal granted an adjournment requested by the respondent and scheduled the appeal for hearing on 13.11.2025, directing parties to exchange pleadings in the interim.
Delay condonation
The Tribunal granted the respondents 10 days to file objections and scheduled the appeal for hearing on 29.10.2025.
Delay condonation
The Tribunal granted the respondents ten days to file objections and allowed the appellant seven days to file a rejoinder, scheduling the next hearing for 25.09.2025.
Delay condonation
The appellant's counsel requested an adjournment, and the tribunal rescheduled the appeal for orders/hearing on 03.09.2025.
Delay condonation
The Tribunal granted the respondent 10 days to file objections and directed that a rejoinder affidavit be filed within a week thereafter, scheduling the next hearing for 20.08.2025.
For Order
The Tribunal allowed the appellant's application to implead the complainant as a respondent and noted that the amount of Rs. 25,49,037/- recovered from the appellant has been transmitted to the complainant's bank account.
For Order
The Tribunal directed the appellant's counsel to provide a copy of the memo of appeal to the respondent and to seek instructions regarding whether the recovery certificate for Rs. 25,49,036.23 has been recovered and deposited.
Defect Removal
The appeal was dismissed for want of prosecution as no one appeared to press the matter.
Defect Removal
The case was adjourned due to the illness of the appellant's counsel, with the matter scheduled to be listed for orders on 07.11.2024.
Defect Removal
The Tribunal granted the appellant a 10-day extension to file documents concerning the deposit made by the Tehsildar, Ghaziabad, and scheduled the case for orders on 30.09.2024.
Delay condonation
The Tribunal granted the appellant 10 days to file documentation proving that the amount encashed by the Tehsildar, Ghaziabad, has been deposited with RERA, and scheduled the matter for orders on 11.09.2024.
Delay condonation
The Tribunal granted the appellant a one-week extension to file an amendment application in compliance with a previous order and scheduled the next hearing for August 20, 2024.
Delay condonation
The Tribunal noted the absence of both parties and ordered the defective appeal to be listed for orders or hearing on 23.07.2024.
Delay condonation
The Tribunal directed the appellant to file an amendment application to implead the original complainant/allottee, noting that the appeal was defective due to the failure to array the necessary party.
Tribunal Order #0901126021362024-13-11-2025
The Tribunal dismissed the appeal challenging a recovery certificate, ruling that the developer is liable for delay interest until the date of physical possession and directing the appellant to execute the conveyance deed within 45 days.
Tribunal Order #0901126021362024-15-05-2025
The Tribunal directed the appellant's counsel to provide a copy of the memo of appeal to the respondent and to seek instructions regarding whether the recovery certificate for Rs. 25,49,036.23 has been recovered and deposited.
Tribunal Order #0901126021362024-09-07-2025
The Tribunal allowed the appellant's application to implead the complainant as a respondent and noted that the amount of Rs. 25,49,037/- recovered from the appellant has been transmitted to the complainant's bank account.
Tribunal Order #0901126021362024-10-05-2024
The Tribunal directed the appellant to file an amendment application to implead the original complainant/allottee, noting that the appeal was defective due to the failure to array the necessary party.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal challenging a recovery certificate, ruling that the developer is liable for delay interest until the date of physical possession and directing the appellant to execute the conveyance deed within 45 days. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal challenging a recovery certificate, ruling that the developer is liable for delay interest until the date of physical possession and directing the appellant to execute the conveyance deed within 45 days.
Ruling Awarded To
Respondent
Interest Period
w.e.f. 01.10.2018 till the date of obtaining OC/CC or offer of possession of the unit, whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Pawan Kumar Shukla
- Sachin Kumar Pandey
Respondent Advocate(s)
- Shobhit Mohan Shukla
- Manish Singh
Official RERA Tribunal Orders (4)
The Tribunal dismissed the appeal challenging a recovery certificate, ruling that the developer is liable for delay interest until the date of physical possession and directing the appellant to execute the conveyance deed within 45 days.
The Tribunal directed the appellant's counsel to provide a copy of the memo of appeal to the respondent and to seek instructions regarding whether the recovery certificate for Rs. 25,49,036.23 has been recovered and deposited.
The Tribunal allowed the appellant's application to implead the complainant as a respondent and noted that the amount of Rs. 25,49,037/- recovered from the appellant has been transmitted to the complainant's bank account.
The Tribunal directed the appellant to file an amendment application to implead the original complainant/allottee, noting that the appeal was defective due to the failure to array the necessary party.