up_reraStatus: Completed
CASE ID: 0901126021362024

Appellant / Complainant

Prateek Realtors India Private Limited

VS

Respondent

Up Real Estate Regulatory Authority

Developer Firm

prateek realtors india private limited

Disputed Amount

25,49,036

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126021362024 by Prateek Realtors India Private Limited against Up Real Estate Regulatory Authority before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferNon-Compliance & Execution
2
Stage 113/11/2025

Delay condonation

The Tribunal dismissed the appeal challenging a recovery certificate, ruling that the developer is liable for delay interest until the date of physical possession and directing the appellant to execute the conveyance deed within 45 days.

3
Stage 229/10/2025

Delay condonation

The Tribunal granted an adjournment requested by the respondent and scheduled the appeal for hearing on 13.11.2025, directing parties to exchange pleadings in the interim.

4
Stage 325/09/2025

Delay condonation

The Tribunal granted the respondents 10 days to file objections and scheduled the appeal for hearing on 29.10.2025.

5
Stage 403/09/2025

Delay condonation

The Tribunal granted the respondents ten days to file objections and allowed the appellant seven days to file a rejoinder, scheduling the next hearing for 25.09.2025.

6
Stage 520/08/2025

Delay condonation

The appellant's counsel requested an adjournment, and the tribunal rescheduled the appeal for orders/hearing on 03.09.2025.

7
Stage 630/07/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections and directed that a rejoinder affidavit be filed within a week thereafter, scheduling the next hearing for 20.08.2025.

8
Stage 709/07/2025

For Order

The Tribunal allowed the appellant's application to implead the complainant as a respondent and noted that the amount of Rs. 25,49,037/- recovered from the appellant has been transmitted to the complainant's bank account.

9
Stage 815/05/2025

For Order

The Tribunal directed the appellant's counsel to provide a copy of the memo of appeal to the respondent and to seek instructions regarding whether the recovery certificate for Rs. 25,49,036.23 has been recovered and deposited.

10
Stage 907/11/2024

Defect Removal

The appeal was dismissed for want of prosecution as no one appeared to press the matter.

11
Stage 1030/09/2024

Defect Removal

The case was adjourned due to the illness of the appellant's counsel, with the matter scheduled to be listed for orders on 07.11.2024.

12
Stage 1111/09/2024

Defect Removal

The Tribunal granted the appellant a 10-day extension to file documents concerning the deposit made by the Tehsildar, Ghaziabad, and scheduled the case for orders on 30.09.2024.

13
Stage 1220/08/2024

Delay condonation

The Tribunal granted the appellant 10 days to file documentation proving that the amount encashed by the Tehsildar, Ghaziabad, has been deposited with RERA, and scheduled the matter for orders on 11.09.2024.

14
Stage 1323/07/2024

Delay condonation

The Tribunal granted the appellant a one-week extension to file an amendment application in compliance with a previous order and scheduled the next hearing for August 20, 2024.

15
Stage 1423/05/2024

Delay condonation

The Tribunal noted the absence of both parties and ordered the defective appeal to be listed for orders or hearing on 23.07.2024.

16
Stage 1510/05/2024

Delay condonation

The Tribunal directed the appellant to file an amendment application to implead the original complainant/allottee, noting that the appeal was defective due to the failure to array the necessary party.

17
Stage 16Final Ruling Order

Tribunal Order #0901126021362024-13-11-2025

The Tribunal dismissed the appeal challenging a recovery certificate, ruling that the developer is liable for delay interest until the date of physical possession and directing the appellant to execute the conveyance deed within 45 days.

18
Stage 17Interim Order

Tribunal Order #0901126021362024-15-05-2025

The Tribunal directed the appellant's counsel to provide a copy of the memo of appeal to the respondent and to seek instructions regarding whether the recovery certificate for Rs. 25,49,036.23 has been recovered and deposited.

19
Stage 18Interim Order

Tribunal Order #0901126021362024-09-07-2025

The Tribunal allowed the appellant's application to implead the complainant as a respondent and noted that the amount of Rs. 25,49,037/- recovered from the appellant has been transmitted to the complainant's bank account.

20
Stage 19Interim Order

Tribunal Order #0901126021362024-10-05-2024

The Tribunal directed the appellant to file an amendment application to implead the original complainant/allottee, noting that the appeal was defective due to the failure to array the necessary party.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal challenging a recovery certificate, ruling that the developer is liable for delay interest until the date of physical possession and directing the appellant to execute the conveyance deed within 45 days. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal challenging a recovery certificate, ruling that the developer is liable for delay interest until the date of physical possession and directing the appellant to execute the conveyance deed within 45 days.

Ruling Awarded To

Respondent

Interest Period

w.e.f. 01.10.2018 till the date of obtaining OC/CC or offer of possession of the unit, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Pawan Kumar Shukla
  • Sachin Kumar Pandey

Respondent Advocate(s)

  • Shobhit Mohan Shukla
  • Manish Singh

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126021362024-13-11-2025

The Tribunal dismissed the appeal challenging a recovery certificate, ruling that the developer is liable for delay interest until the date of physical possession and directing the appellant to execute the conveyance deed within 45 days.

INTERIM_ORDEROrder ID: 0901126021362024-15-05-2025

The Tribunal directed the appellant's counsel to provide a copy of the memo of appeal to the respondent and to seek instructions regarding whether the recovery certificate for Rs. 25,49,036.23 has been recovered and deposited.

INTERIM_ORDEROrder ID: 0901126021362024-09-07-2025

The Tribunal allowed the appellant's application to implead the complainant as a respondent and noted that the amount of Rs. 25,49,037/- recovered from the appellant has been transmitted to the complainant's bank account.

INTERIM_ORDEROrder ID: 0901126021362024-10-05-2024

The Tribunal directed the appellant to file an amendment application to implead the original complainant/allottee, noting that the appeal was defective due to the failure to array the necessary party.

TathyaGrid RERA Intelligence AI

Need to research all rulings for prateek realtors india private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →