up_reraStatus: Completed
CASE ID: 0901126020932021

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Pooja Chaddha

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

17 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126020932021 by Lucknow Development Authority against Pooja Chaddha before up_rera.

2
Stage 117/11/2022

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal rejected the appeal filed by Lucknow Development Authority and directed that funds deposited under Section 43(5) of the Act be transferred to the Regulatory Authority for disposal.

3
Stage 229/03/2022

Hearing

The Tribunal heard arguments from both parties and directed the counsels to file a list of dates and events, subsequently reserving the judgment.

4
Stage 314/03/2022

Hearing

No text available.

5
Stage 402/03/2022

Further Order

The Tribunal granted the appellant 48 hours to file a reply to the respondent's objections due to technical difficulties and scheduled the final hearing for March 14, 2022.

6
Stage 519/01/2022

Further Order

No text available.

7
Stage 617/12/2021

Further Order

The Tribunal directed the applicant to file a replication to the appeal and serve a copy to the respondent, scheduling the matter for further orders on 19.01.2022.

8
Stage 723/11/2021

Delay condonation

The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's relaxation of limitation periods due to the COVID-19 pandemic, and directed the applicant to file a replication/rejoinder affidavit.

9
Stage 826/10/2021

Delay condonation

The Tribunal granted the respondent one week to file their Vakalatnama and objections against the limitation application, scheduling the matter for further hearing on 23.11.2021.

10
Stage 922/09/2021

Delay condonation

The Tribunal issued notice to the respondent regarding the application for condonation of delay and directed the parties to exchange pleadings via post and email before the next hearing on 26.10.2021.

11
Stage 1003/05/2021

Defect Removal

No text available.

12
Stage 1109/04/2021

Defect Removal

No text available.

13
Stage 1226/03/2021

Defect Removal

The Tribunal directed the appellant to remove registry defects and ensure complete compliance with Section 43(5) of the Act, warning that failure to do so by the next hearing will result in dismissal.

14
Stage 13Final Ruling Order

Tribunal Order #0901126020932021-17-11-2022

The U.P. Real Estate Appellate Tribunal rejected the appeal filed by Lucknow Development Authority and directed that funds deposited under Section 43(5) of the Act be transferred to the Regulatory Authority for disposal.

15
Stage 14Interim Order

Tribunal Order #0901126020932021-26-03-2021

The Tribunal directed the appellant to remove registry defects and ensure complete compliance with Section 43(5) of the Act, warning that failure to do so by the next hearing will result in dismissal.

16
Stage 15Interim Order

Tribunal Order #0901126020932021-23-11-2021

The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's relaxation of limitation periods due to the COVID-19 pandemic, and directed the applicant to file a replication/rejoinder affidavit.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the appeal filed by Lucknow Development Authority and directed that funds deposited under Section 43(5) of the Act be transferred to the Regulatory Authority for disposal. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the appeal filed by Lucknow Development Authority and directed that funds deposited under Section 43(5) of the Act be transferred to the Regulatory Authority for disposal.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saurabh Misra

Respondent Advocate(s)

  • Hridesh Srivastava

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126020932021-17-11-2022

The U.P. Real Estate Appellate Tribunal rejected the appeal filed by Lucknow Development Authority and directed that funds deposited under Section 43(5) of the Act be transferred to the Regulatory Authority for disposal.

INTERIM_ORDEROrder ID: 0901126020932021-26-03-2021

The Tribunal directed the appellant to remove registry defects and ensure complete compliance with Section 43(5) of the Act, warning that failure to do so by the next hearing will result in dismissal.

INTERIM_ORDEROrder ID: 0901126020932021-23-11-2021

The Tribunal allowed the application for condonation of delay in filing the appeal, citing the Supreme Court's relaxation of limitation periods due to the COVID-19 pandemic, and directed the applicant to file a replication/rejoinder affidavit.