Appellant / Complainant
Yamuna Expressway Industrial Development Authority
Respondent
Vikas Goel
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126020502024 by Yamuna Expressway Industrial Development Authority against Vikas Goel before up_rera.
Hearing
The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the issuance of OC/CC or physical possession, whichever is later.
Hearing
The Tribunal heard arguments regarding an appeal over interest payments for project delays and granted the respondent time to argue entitlement under Section 18(1) of the RERA Act, scheduling the next hearing for 27.01.2026.
Hearing
The Tribunal has granted a request to list Appeal-180/2024 for orders on 20.01.2026, to be heard alongside Appeal No. 557 of 2023.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal to be listed on 08.12.2025 along with Cross Appeal No. 557/2023.
Hearing
The Tribunal has scheduled the matter for orders, to be heard alongside Appeal No. 557 of 2023, on 18.11.2025.
Hearing
The Tribunal granted the appellant counsel ten days to upload a list of relevant High Court and Supreme Court orders regarding injunctions and adjourned the appeal to 28.10.2025.
Hearing
The Tribunal granted the respondent time to specify the force majeure period claimed due to court injunctions and directed them to record the construction commencement date, adjourning the matter to 09.10.2025.
Hearing
The Tribunal has adjourned the appeal to 04.09.2025 following a joint request from the counsel for both parties.
Hearing
The Tribunal granted a request from the appellant's counsel to list Appeal-180/2024 on 29.08.2025, to be heard alongside Appeal No. 557 of 2023.
Hearing
The Tribunal granted an adjournment request from the respondent's counsel and scheduled the appeal for orders/hearing on 12.08.2024.
Hearing
The Tribunal granted a request from both counsels to adjourn the appeal to 23.07.2025, noting that no further adjournments will be permitted.
Hearing
The Tribunal issued a show cause notice to the CEO of the Yamuna Expressway Industrial Development Authority regarding potential penal consequences under the RERA Act, 2016, due to failure to provide possession and lack of OC/CC for the project.
Hearing
The Tribunal granted adjournment applications filed by both the appellant and respondent, rescheduling the hearing for May 7, 2025, to be heard alongside Cross Appeal No. 557/2023.
Hearing
The Tribunal has adjourned the appeal to 16.04.2025 following a joint request from the learned counsel for both parties.
Hearing
The Tribunal granted a request from both counsels for more time and adjourned the matter to 20.03.2025 for hearing/orders, to be heard alongside cross appeal no. 557 of 2023.
Hearing
The Tribunal has adjourned the appeal to 27.02.2025 following a request from the counsels for both parties.
Hearing
The Tribunal has adjourned the appeal to 04.02.2025 for orders or hearing upon the joint request of both parties.
Delay condonation
The Tribunal condoned the delay in filing the cross-appeals and directed the Registry to convert the defective appeal into a regular appeal, scheduling the hearing for January 7, 2025.
Delay condonation
The Tribunal granted a request from the respondent's counsel to adjourn the matter to 22.11.2024 and directed the parties to exchange pleadings in the interim.
Delay condonation
The Tribunal directed the appellant to provide copies of the appeal and the application for condonation of delay to the respondent, setting a timeline for the filing of objections and replies before the next hearing on 21.10.2024.
Delay condonation
The Tribunal granted an adjournment requested by the respondent's counsel and directed the filing of objections within 10 days, with the matter listed for hearing on 09.09.2024.
Delay condonation
The Tribunal granted the respondent 10 days to file a vakalatnama and objections to the condonation of delay application, and scheduled the matter for hearing on 08.08.2024.
Delay condonation
The Tribunal acknowledged the deposit of Rs. 9,85,802/- in compliance with Section 43(5) of the Act and issued notice to the respondent for the hearing of the application for condonation of delay on 23.07.2024.
Tribunal Order #0901126020502024-27-01-2026
The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the issuance of OC/CC or physical possession, whichever is later.
Tribunal Order #0901126020502024-22-11-2024
The Tribunal condoned the delay in filing the cross-appeals and directed the Registry to convert the defective appeal into a regular appeal, scheduling the hearing for January 7, 2025.
Tribunal Order #0901126020502024-07-05-2025
The Tribunal issued a show cause notice to the CEO of the Yamuna Expressway Industrial Development Authority regarding potential penal consequences under the RERA Act, 2016, due to failure to provide possession and lack of OC/CC for the project.
Tribunal Disposal & Final Award Ruling
The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the issuance of OC/CC or physical possession, whichever is later. Awarded in favor of Partial. Awarded interest rate: MCLR + 1 percent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the issuance of OC/CC or physical possession, whichever is later.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR + 1 percent
Interest Period
w.e.f. 21.11.2013 till obtaining OC/CC of the project or till handing over physical possession of the unit, whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Fuhar Gupta
- Prashant Kumar
- Deepti Mishra
Respondent Advocate(s)
- Deepti Mishra
- Hemant Tewari
- Fuhar Gupta
- Prashant Kumar
Official RERA Tribunal Orders (3)
The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the issuance of OC/CC or physical possession, whichever is later.
The Tribunal condoned the delay in filing the cross-appeals and directed the Registry to convert the defective appeal into a regular appeal, scheduling the hearing for January 7, 2025.
The Tribunal issued a show cause notice to the CEO of the Yamuna Expressway Industrial Development Authority regarding potential penal consequences under the RERA Act, 2016, due to failure to provide possession and lack of OC/CC for the project.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.