up_reraStatus: Completed
CASE ID: 0901126020502024

Appellant / Complainant

Yamuna Expressway Industrial Development Authority

VS

Respondent

Vikas Goel

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

28 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126020502024 by Yamuna Expressway Industrial Development Authority against Vikas Goel before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 127/01/2026

Hearing

The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the issuance of OC/CC or physical possession, whichever is later.

3
Stage 220/01/2026

Hearing

The Tribunal heard arguments regarding an appeal over interest payments for project delays and granted the respondent time to argue entitlement under Section 18(1) of the RERA Act, scheduling the next hearing for 27.01.2026.

4
Stage 308/12/2025

Hearing

The Tribunal has granted a request to list Appeal-180/2024 for orders on 20.01.2026, to be heard alongside Appeal No. 557 of 2023.

5
Stage 418/11/2025

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal to be listed on 08.12.2025 along with Cross Appeal No. 557/2023.

6
Stage 528/10/2025

Hearing

The Tribunal has scheduled the matter for orders, to be heard alongside Appeal No. 557 of 2023, on 18.11.2025.

7
Stage 609/10/2025

Hearing

The Tribunal granted the appellant counsel ten days to upload a list of relevant High Court and Supreme Court orders regarding injunctions and adjourned the appeal to 28.10.2025.

8
Stage 704/09/2025

Hearing

The Tribunal granted the respondent time to specify the force majeure period claimed due to court injunctions and directed them to record the construction commencement date, adjourning the matter to 09.10.2025.

9
Stage 829/08/2025

Hearing

The Tribunal has adjourned the appeal to 04.09.2025 following a joint request from the counsel for both parties.

10
Stage 912/08/2025

Hearing

The Tribunal granted a request from the appellant's counsel to list Appeal-180/2024 on 29.08.2025, to be heard alongside Appeal No. 557 of 2023.

11
Stage 1023/07/2025

Hearing

The Tribunal granted an adjournment request from the respondent's counsel and scheduled the appeal for orders/hearing on 12.08.2024.

12
Stage 1130/05/2025

Hearing

The Tribunal granted a request from both counsels to adjourn the appeal to 23.07.2025, noting that no further adjournments will be permitted.

13
Stage 1207/05/2025

Hearing

The Tribunal issued a show cause notice to the CEO of the Yamuna Expressway Industrial Development Authority regarding potential penal consequences under the RERA Act, 2016, due to failure to provide possession and lack of OC/CC for the project.

14
Stage 1316/04/2025

Hearing

The Tribunal granted adjournment applications filed by both the appellant and respondent, rescheduling the hearing for May 7, 2025, to be heard alongside Cross Appeal No. 557/2023.

15
Stage 1420/03/2025

Hearing

The Tribunal has adjourned the appeal to 16.04.2025 following a joint request from the learned counsel for both parties.

16
Stage 1527/02/2025

Hearing

The Tribunal granted a request from both counsels for more time and adjourned the matter to 20.03.2025 for hearing/orders, to be heard alongside cross appeal no. 557 of 2023.

17
Stage 1604/02/2025

Hearing

The Tribunal has adjourned the appeal to 27.02.2025 following a request from the counsels for both parties.

18
Stage 1707/01/2025

Hearing

The Tribunal has adjourned the appeal to 04.02.2025 for orders or hearing upon the joint request of both parties.

19
Stage 1822/11/2024

Delay condonation

The Tribunal condoned the delay in filing the cross-appeals and directed the Registry to convert the defective appeal into a regular appeal, scheduling the hearing for January 7, 2025.

20
Stage 1921/10/2024

Delay condonation

The Tribunal granted a request from the respondent's counsel to adjourn the matter to 22.11.2024 and directed the parties to exchange pleadings in the interim.

21
Stage 2009/09/2024

Delay condonation

The Tribunal directed the appellant to provide copies of the appeal and the application for condonation of delay to the respondent, setting a timeline for the filing of objections and replies before the next hearing on 21.10.2024.

22
Stage 2108/08/2024

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel and directed the filing of objections within 10 days, with the matter listed for hearing on 09.09.2024.

23
Stage 2223/07/2024

Delay condonation

The Tribunal granted the respondent 10 days to file a vakalatnama and objections to the condonation of delay application, and scheduled the matter for hearing on 08.08.2024.

24
Stage 2323/05/2024

Delay condonation

The Tribunal acknowledged the deposit of Rs. 9,85,802/- in compliance with Section 43(5) of the Act and issued notice to the respondent for the hearing of the application for condonation of delay on 23.07.2024.

25
Stage 24Final Ruling Order

Tribunal Order #0901126020502024-27-01-2026

The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the issuance of OC/CC or physical possession, whichever is later.

26
Stage 25Interim Order

Tribunal Order #0901126020502024-22-11-2024

The Tribunal condoned the delay in filing the cross-appeals and directed the Registry to convert the defective appeal into a regular appeal, scheduling the hearing for January 7, 2025.

27
Stage 26Interim Order

Tribunal Order #0901126020502024-07-05-2025

The Tribunal issued a show cause notice to the CEO of the Yamuna Expressway Industrial Development Authority regarding potential penal consequences under the RERA Act, 2016, due to failure to provide possession and lack of OC/CC for the project.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the issuance of OC/CC or physical possession, whichever is later. Awarded in favor of Partial. Awarded interest rate: MCLR + 1 percent.

Disposal Winner: PartialInterest Rate: MCLR + 1 percentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the issuance of OC/CC or physical possession, whichever is later.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR + 1 percent

Interest Period

w.e.f. 21.11.2013 till obtaining OC/CC of the project or till handing over physical possession of the unit, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Fuhar Gupta
  • Prashant Kumar
  • Deepti Mishra

Respondent Advocate(s)

  • Deepti Mishra
  • Hemant Tewari
  • Fuhar Gupta
  • Prashant Kumar

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126020502024-27-01-2026

The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the issuance of OC/CC or physical possession, whichever is later.

INTERIM_ORDEROrder ID: 0901126020502024-22-11-2024

The Tribunal condoned the delay in filing the cross-appeals and directed the Registry to convert the defective appeal into a regular appeal, scheduling the hearing for January 7, 2025.

INTERIM_ORDEROrder ID: 0901126020502024-07-05-2025

The Tribunal issued a show cause notice to the CEO of the Yamuna Expressway Industrial Development Authority regarding potential penal consequences under the RERA Act, 2016, due to failure to provide possession and lack of OC/CC for the project.