up_reraStatus: Completed
CASE ID: 0901126020362021

Appellant / Complainant

Roopali Grover

VS

Respondent

Golfgreen Infra Pvt. Ltd

Developer Firm

golfgreen infra pvt. ltd

Disputed Amount

1,07,38,802

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

30 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126020362021 by Roopali Grover against Golfgreen Infra Pvt. Ltd before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 109/05/2024

for delivery of Judgment/Order

The Appellate Tribunal set aside the Regulatory Authority's order to provide possession and instead directed the respondent to refund the entire deposited amount with interest at MCLR+1% within 45 days due to the appellant's right to withdraw from the project.

3
Stage 212/03/2024

Hearing

The appellant is challenging the Regulatory Authority's order regarding delay interest and possession terms, specifically contesting the validity of 'deemed OC/CC' used by the respondent to claim possession was timely.

4
Stage 328/02/2024

Hearing

The Tribunal decided to proceed ex parte against the respondent due to their repeated failure to appear despite being aware of the proceedings, and issued a warning to the appellant's counsel regarding unprepared arguments.

5
Stage 405/02/2024

Hearing

The Tribunal directed the respondent to ensure their counsel's presence at future hearings, warning that the respondent will be summoned if they continue to fail to appear without adjournment requests. The matter is listed for hearing on 28.02.2024.

6
Stage 501/02/2024

Hearing

The Tribunal noted the absence of the respondent and, upon the appellant's request, adjourned the matter to 05.02.2024 to allow for the filing of physical copies of documents.

7
Stage 612/09/2023

Hearing

No text available.

8
Stage 724/07/2023

Hearing

No text available.

9
Stage 818/07/2023

Hearing

The Tribunal adjourned the appeal to 24.07.2023 due to the non-appearance of the respondent's counsel and noted that the matter will proceed based on available records if no one appears on the next date.

10
Stage 918/08/2022

Hearing

The Tribunal heard arguments from the appellant's counsel and subsequently reserved the judgment for further deliberation.

11
Stage 1008/07/2022

Hearing

The Tribunal granted an adjournment requested by the respondent and rescheduled the hearing for August 18, 2022.

12
Stage 1124/05/2022

Hearing

The Tribunal directed the respondent to deposit a previously imposed cost of Rs. 10,000 for library books and ordered both parties to file written arguments within 15 days.

13
Stage 1219/04/2022

Hearing

The Tribunal directed the parties to exchange lists of dates, events, and cited cases at least seven days before the next hearing, and ordered the respondent to deposit Rs. 10,000/- in the Tribunal fund.

14
Stage 1325/02/2022

Hearing

The Tribunal noted the filing of a rejoinder by the appellant and a reply via email by the respondent, subsequently scheduling the case for a hearing on 19.04.2022.

15
Stage 1417/01/2022

Hearing

No text available.

16
Stage 1522/12/2021

Hearing

The respondent declined to press their application to recall the cost imposition of Rs. 10,000/-, and the appellant was directed to file a rejoinder to the respondent's reply.

17
Stage 1606/12/2021

Hearing

No text available.

18
Stage 1712/11/2021

Hearing

The Tribunal directed the Registry to convert the defective appeal into a regular appeal as it was found to be within the limitation period and free of defects. Additionally, the parties were granted time to file objections and replies via email and instructed to upload pleadings on the e-portal.

19
Stage 1822/09/2021

Hearing

The Tribunal issued a notice to the respondent via registered post and e-mail and directed the appellant to take necessary steps within a week, scheduling the next hearing for 12.11.2021.

20
Stage 1906/09/2021

Defect Removal

The Tribunal accepted the appellant's claim regarding the filing date of the appeal and issued a notice to the respondent, scheduling the matter for a subsequent hearing.

21
Stage 2030/04/2021

Defect Removal

No text available.

22
Stage 2105/04/2021

Defect Removal

No text available.

23
Stage 22Final Ruling Order

Tribunal Order #0901126020362021-09-05-2024

The Appellate Tribunal set aside the Regulatory Authority's order to provide possession and instead directed the respondent to refund the entire deposited amount with interest at MCLR+1% within 45 days due to the appellant's right to withdraw from the project.

24
Stage 23Interim Order

Tribunal Order #0901126020362021-12-03-2024

The appellant is challenging the Regulatory Authority's order regarding delay interest and possession terms, specifically contesting the validity of 'deemed OC/CC' used by the respondent to claim possession was timely.

25
Stage 24Interim Order

Tribunal Order #0901126020362021-05-02-2024

The Tribunal directed the respondent to ensure their counsel's presence at future hearings, warning that the respondent will be summoned if they continue to fail to appear without adjournment requests. The matter is listed for hearing on 28.02.2024.

26
Stage 25Interim Order

Tribunal Order #0901126020362021-24-05-2022

The Tribunal directed the respondent to deposit a previously imposed cost of Rs. 10,000 for library books and ordered both parties to file written arguments within 15 days.

27
Stage 26Interim Order

Tribunal Order #0901126020362021-28-02-2024

The Tribunal decided to proceed ex parte against the respondent due to their repeated failure to appear despite being aware of the proceedings, and issued a warning to the appellant's counsel regarding unprepared arguments.

28
Stage 27Interim Order

Tribunal Order #0901126020362021-19-04-2022

The Tribunal directed the parties to exchange lists of dates, events, and cited cases at least seven days before the next hearing, and ordered the respondent to deposit Rs. 10,000/- in the Tribunal fund.

29
Stage 28Interim Order

Tribunal Order #0901126020362021-12-11-2021

The Tribunal directed the Registry to convert the defective appeal into a regular appeal as it was found to be within the limitation period and free of defects. Additionally, the parties were granted time to file objections and replies via email and instructed to upload pleadings on the e-portal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal set aside the Regulatory Authority's order to provide possession and instead directed the respondent to refund the entire deposited amount with interest at MCLR+1% within 45 days due to the appellant's right to withdraw from the project. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.

Disposal Winner: AppellantInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal set aside the Regulatory Authority's order to provide possession and instead directed the respondent to refund the entire deposited amount with interest at MCLR+1% within 45 days due to the appellant's right to withdraw from the project.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1%

Interest Period

from the date of deposit till the date of realisation of the amount

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Mandeep Singh
  • Mohit Kumar Bansal

Respondent Advocate(s)

  • Anurag Srivastava

Official RERA Tribunal Orders (7)

FINAL_ORDEROrder ID: 0901126020362021-09-05-2024

The Appellate Tribunal set aside the Regulatory Authority's order to provide possession and instead directed the respondent to refund the entire deposited amount with interest at MCLR+1% within 45 days due to the appellant's right to withdraw from the project.

INTERIM_ORDEROrder ID: 0901126020362021-12-03-2024

The appellant is challenging the Regulatory Authority's order regarding delay interest and possession terms, specifically contesting the validity of 'deemed OC/CC' used by the respondent to claim possession was timely.

INTERIM_ORDEROrder ID: 0901126020362021-05-02-2024

The Tribunal directed the respondent to ensure their counsel's presence at future hearings, warning that the respondent will be summoned if they continue to fail to appear without adjournment requests. The matter is listed for hearing on 28.02.2024.

INTERIM_ORDEROrder ID: 0901126020362021-24-05-2022

The Tribunal directed the respondent to deposit a previously imposed cost of Rs. 10,000 for library books and ordered both parties to file written arguments within 15 days.

INTERIM_ORDEROrder ID: 0901126020362021-28-02-2024

The Tribunal decided to proceed ex parte against the respondent due to their repeated failure to appear despite being aware of the proceedings, and issued a warning to the appellant's counsel regarding unprepared arguments.

INTERIM_ORDEROrder ID: 0901126020362021-19-04-2022

The Tribunal directed the parties to exchange lists of dates, events, and cited cases at least seven days before the next hearing, and ordered the respondent to deposit Rs. 10,000/- in the Tribunal fund.

INTERIM_ORDEROrder ID: 0901126020362021-12-11-2021

The Tribunal directed the Registry to convert the defective appeal into a regular appeal as it was found to be within the limitation period and free of defects. Additionally, the parties were granted time to file objections and replies via email and instructed to upload pleadings on the e-portal.