up_reraStatus: Completed
CASE ID: 0901126020342023

Appellant / Complainant

Ratan Buildtech Private Limited

VS

Respondent

Amar Singh Chauhan

Developer Firm

ratan buildtech private limited

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

23 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126020342023 by Ratan Buildtech Private Limited against Amar Singh Chauhan before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 114/05/2025

Hearing

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but settled the dispute directly by awarding the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 14.10.2022, excluding the COVID-19 force majeure period.

3
Stage 221/04/2025

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel but stipulated that no further adjournments will be permitted and directed that alternative arrangements must be made if the counsel is unable to appear at the next hearing on 14.05.2025.

4
Stage 321/03/2025

For Order

Upon a joint request from the counsel for both parties, the Tribunal has adjourned the matter and scheduled it for orders on 21.04.2025.

5
Stage 427/02/2025

For Order

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and scheduled the case for orders on 21.03.2025.

6
Stage 510/02/2025

For Order

The Tribunal has rescheduled the hearing for Appeal-414/2023 to 27.02.2025 following a joint request from the counsels for both parties.

7
Stage 627/01/2025

For Order

The Tribunal has scheduled the matter for orders or hearing on February 10, 2025.

8
Stage 702/01/2025

For Order

The Tribunal has granted a request by the appellant's counsel to reschedule the hearing of Appeal-414/2023 to 27.01.2025.

9
Stage 818/09/2024

For Order

The Tribunal heard arguments from both parties regarding the applicability of previous judgments on delay interest and has reserved its judgment for a later date.

10
Stage 914/08/2024

For Order

The Tribunal granted a joint request from the counsel for both parties to adjourn the matter, scheduling it for orders/hearing on 18.09.2024.

11
Stage 1016/07/2024

For Order

The Tribunal has scheduled the appeal for orders/hearing on 14.08.2024, referring to a previous order passed in Appeal No. 260/2023.

12
Stage 1116/05/2024

For Order

No text available.

13
Stage 1210/05/2024

For Order

The Tribunal has scheduled the appeal for a hearing on 16.05.2024 following information from the appellant's counsel regarding similar cases being listed on that date.

14
Stage 1324/04/2024

For Order

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for hearing on 10.05.2024.

15
Stage 1429/03/2024

For Order

The Tribunal refers the parties to a previous order passed in Appeal No. D382/2023 for directions.

16
Stage 1515/03/2024

For Order

The Tribunal granted an adjournment to the appellant to examine potential deficiencies in compliance with Section 43(5) of the Act and scheduled the next hearing for March 29, 2024.

17
Stage 1613/02/2024

For Order

The Tribunal noted the illness of the respondent's counsel and adjourned the matter, scheduling the appeal for a hearing on 15.03.2024.

18
Stage 1705/01/2024

For Order

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the next hearing for February 13, 2024.

19
Stage 1828/09/2023

For Order

No text available.

20
Stage 1917/08/2023

Notice

The Tribunal accepted the appellant's affidavit of proof of service and granted the respondent a 10-day extension to file objections, directing subsequent exchange of pleadings via email and e-portal.

21
Stage 2021/06/2023

Admission

The Tribunal issued notice to the respondent regarding the appeal filed by Ratan Buildtech Private Limited and outlined the procedural requirements for service of notice and filing of objections.

22
Stage 21Final Ruling Order

Tribunal Order #0901126020342023-14-05-2025

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but settled the dispute directly by awarding the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 14.10.2022, excluding the COVID-19 force majeure period.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but settled the dispute directly by awarding the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 14.10.2022, excluding the COVID-19 force majeure period. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.

Disposal Winner: PartialInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but settled the dispute directly by awarding the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 14.10.2022, excluding the COVID-19 force majeure period.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.01.2020 to 14.10.2022 (except for the six months force majeure period on account of Covid-19)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Mahima Pahwa
  • Prashant Kumar Singh

Respondent Advocate(s)

  • Amit Yadav

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126020342023-14-05-2025

The Tribunal quashed the Adjudicating Officer's order due to lack of jurisdiction but settled the dispute directly by awarding the respondent delay interest at MCLR+1% for the period from 01.01.2020 to 14.10.2022, excluding the COVID-19 force majeure period.

TathyaGrid RERA Intelligence AI