Appellant / Complainant
U.P. Awas Evam Vikas Parishad
Respondent
Prachi Vibhawri Mishra
₹30,00,000
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126020312022 by U.P. Awas Evam Vikas Parishad against Prachi Vibhawri Mishra before up_rera.
For Order
The Tribunal partially allowed the appeal by modifying the interest liability period for the appellant, directing that interest at MCLR+1% be paid from 02.03.2018 to 20.11.2020 based on a reasonable construction period of 36 months.
Hearing
The Tribunal allowed the application for condonation of delay in filing the appeal, citing COVID-19 related relaxations granted by the Supreme Court, and directed the Registry to register the defective appeal as a regular appeal.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for July 15, 2022.
Delay condonation
The Tribunal directed the appellant to rectify defects in its annexures and re-upload a proper index, while issuing notice to the respondent regarding the application for condonation of delay.
Tribunal Order #0901126020312022-26-08-2022
The Tribunal partially allowed the appeal by modifying the interest liability period for the appellant, directing that interest at MCLR+1% be paid from 02.03.2018 to 20.11.2020 based on a reasonable construction period of 36 months.
Tribunal Order #0901126020312022-15-07-2022
The Tribunal allowed the application for condonation of delay in filing the appeal, citing COVID-19 related relaxations granted by the Supreme Court, and directed the Registry to register the defective appeal as a regular appeal.
Tribunal Order #0901126020312022-28-04-2022
The Tribunal directed the appellant to rectify defects in its annexures and re-upload a proper index, while issuing notice to the respondent regarding the application for condonation of delay.
Tribunal Disposal & Final Award Ruling
The Tribunal partially allowed the appeal by modifying the interest liability period for the appellant, directing that interest at MCLR+1% be paid from 02.03.2018 to 20.11.2020 based on a reasonable construction period of 36 months. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal partially allowed the appeal by modifying the interest liability period for the appellant, directing that interest at MCLR+1% be paid from 02.03.2018 to 20.11.2020 based on a reasonable construction period of 36 months.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR+1%
Interest Period
from 02.03.2018 to 20.11.2020
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- N N Pandey
Respondent Advocate(s)
- Alok Keerti Mishra
Official RERA Tribunal Orders (3)
The Tribunal partially allowed the appeal by modifying the interest liability period for the appellant, directing that interest at MCLR+1% be paid from 02.03.2018 to 20.11.2020 based on a reasonable construction period of 36 months.
The Tribunal allowed the application for condonation of delay in filing the appeal, citing COVID-19 related relaxations granted by the Supreme Court, and directed the Registry to register the defective appeal as a regular appeal.
The Tribunal directed the appellant to rectify defects in its annexures and re-upload a proper index, while issuing notice to the respondent regarding the application for condonation of delay.